SUBJECT:

NOTICE OF VIOLATION AND PROPOSED IMPOSITION OF CIVIL PENALTIES -

$500.000 (NRC Inspection Report Nos. 50-302/95-13 and 50-302/95-22 and Investigation Report Nos. 2-94-036 and 2-94-0365)

Dear Mr. Beard:

This will acknowledge receipt of your letter dated September 9.1996, and your Jayment of the $500.000 civil penalty proposed by the NRC in our letter to

lorida Power Corporation (FPC) dated June 10, 1996. We have evaluated your l

response and found that it meets the requirements of 10 CFR 2.201 and 10 CFR 2.205.

However, two issues regarding your res)onse to the subject Notice of Violation and Proposed Imposition of Civil Jenalties (Notice)

warrant additional discussion.

First, although your response to Violation B in Part I of the Notice adequately addressed the specific citation of operations staff performance

!

with respect to 10 CFR 50.59 compliance and the conduct of unauthorized tests.

!

subsequent inspection effort has identified that compliance with 10 CFR 50.59 is a broader issue that also encompasses engineering and the design review processes As already discussed with you, these emerging issues will be the subject of a predecisional enforcement conference in the near future.

In addition, because performance deficiencies described in our June 10. 1996, letter appear to be continuing. it is important for FPC to develop and implement an effective performance measurement program to identify adverse trends and to monitor the effectiveness of corrective actions including the adequacy of training and management oversight. Such a program was discussed

'

with you in a management meeting conducted on August 28, 1996.

Please be i

advised that the NRC will monitor the progress of your implementation of.this

,

l program to determine its effectiveness in improving overall plant performance.

,

!

Second, by letter dated August 6.1996. NRC requested that you supplement your response to Violation B in Part I of the Notice for EA 95-126 to also address Unresolved Item (URI) 50-302/96-04-08 identified in our Inspection Report t

transmitted to you by letter dated June 17, 1996. This URI identified four additional tests, not described in the safety analysis report, for which

,

i safety evaluations were not documented as required by 10 CFR 50.59.

The URI

'

addressed:

(1) tests conducted in the 1980s and 1990s which involved shutting l

off spent fuel pool cooling pumps to gauge heatup rate: (2) a test conducted on June 20. 1994, which involved shutting off the reactor cavity cooling i0

!

9610310053 961018 PDR ADOCK 05000302

,}('

-

O PDR

_

_

_

-..

. - _..

.

_-.

.

-

. -_

.

- -

-... -

.

FPC

system supply pumps to gauge teactor cavity heatup rate: (3) a test conducted on January 10. 1994 which involved shutting off reactor building penetration cooling fans to gauge heatup rate; and (4) a test conducted in the early 1980s to assess instrument air system pressure decay by shutting off the compressors during plant operations.

Based on our original inspection findings and your response, we have determined that these four tests constitute violations of 10 CFR 50.59.

Violation B in Part I of the Notice for EA 95-126 identified two examples of the failure to comply with the requirements of 10 CFR 50.59 by conduct of unauthorized tests on September 4 and 5, 1996.

Due to the circumstances of each of the four additional tests and the similarity of the tests and their root cause to those conducted on September 4 and 5, 1994, the NRC has determined to disposition these four unauthorized tests as examples three, four five, and six of Violation B in Part I of the Notice for EA 95-126.

No additional written response is required to address your actions associated with the subject enforcement action or the additional violations resulting from URI 50-302/96-04-08. We will continue to examine the implementation and adequacy of your corrective actions during future inspections.

This letter also serves as closure for URI 50-302/96-04-08.

We appreciate your cooperation in this matter.

Sincerely

.

Original Signed by R. A. Reyes

!

l Stewart D. Ebneter l

Regional Administrator Docket No. 50-302 License No. DRP-72 cc:

Gary L. Boldt. Vice President Nuclear Production (SA2C)

Florida Power Corporation Crystal River Energy Complex 15760 West Power Line Street Crystal River. FL 34428-670G B. J. Hickle. Director Nuclear Plant Operations (NA2C)

.

Florida Power Corporation Crystal River Energy Complex 15760 West Power Line Street

)

"

Crystal River. FL 34428-6708 cc (cont'd on Page 3)

i

,

-.- -

.-.

--

..

.

-

-

.. -

-.-

.

..

-

. -

_

.

k

.

!

-

.

FPC

Distribution:

,

PUBLIC

.

EJulian, SECY BKeeling, CA

'

JTaylor. ED0'

JMilhoan, DEDR FMiraglia, NRR

,

RZimmerman. NRR SEbneter, RII LChandler. OGC JGoldberg. 0GC i

LClark, OGC

'

JLieberman, OE Enforcement Coordinators RI. RIII. RIV

'

EHayden. OPA EJordan. AE00 GCaputo. 01 HBell, OIG

OE:EA File (B. Summers OE) (2)

JBeall, OE

,

LRagahaven NRR FHebdon. NRR SRichards. NRR GTracy, EDO

.

BBurton, EDO AGibson, RII

-

JJohnson. RII

'

,

CEvans, RII

'

'

Buryc, RII Klandis. RII

!

TPeebles, RII LMellen, RII

'

\\ g(qb RSchin. RII EGirard. RII Ip \\g j

CRapp, RII

l KClark, RII

\\

>

h RTrojanowski. RII

\\f NRC Resident Inspector

/

U.S. Nuclear Regulatory CommMsion f

6745N.TallahasseeRoad/

/

Eo (

Crystal River. FL 34428-n j

RFND TO PtAt 10 00rtNENNW1 k Vid NO

[

/

l OFFICE R1[DRS Ri!.DP

EICS RII:0RA H0 E RII:0P SIGNATURE ({

NAME AGib ohnson CEvan Lieberman

,faeyes

_

DATE 10 / O / 96 10/II/96 10 /

/ 96 10 / // / 96 10hfh 10 /

A

,

COPY?

%) NO YES M

VES NO YES M) M ' yn YES [NO)

'

0FflCIAL RECORD M PY DOCUMEN1 liAME: H : \\ 1950 PEN. ENF \\ 9517tiCRMI \\ ACK. LET

"

,

-

r-

-

,..

,