Final SALP Repts 50-282/93-01 & 50-306/93-01 for 910501-930131
ML20035G805
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 01/31/1993
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20035G800 List:
References
50-282-93-01-01, 50-282-93-1-1, 50-306-93-01, 50-306-93-1, NUDOCS 9304300042
Download: ML20035G805 (2)


Text

'

i

.

I i

i Enclosure 1

,

SALP 10

.

FINAL SALP REPORT i

!

>

t U.S. NUCLEAR REGULATORY COMMISSION

REGION III

l

.

t SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE P

Inspection Report No. 50-282/93001; 50-306/93001 i

i i

NORTHERN STATES POWER COMPANY

!

';

PRAIRIE ISLAND NUCLEAR GENERATING PLANT l

l

!

May 1, 1991, Through January 31, 1993 l

l

!

!

!

J

!

l

!

t 9304300042 930423

$

PDR ADOCK 05000282

'O PE4t i

.

. s i

!

Enclosure 1

}

PRAIRIE ISLAND NUCLEAR GENERATING PLANT

!

f

'

A.

Summary of Meetina with Northern States Power Company on April 23. 1993 The findings and conclusions of the SALP Board are documented in

!

Report No. 50-282/93001; 50-306/93001 and were discussed with the licensee

'

,

on April 23, 1993, at the Prairie Island Training Center in Welch,

Minnesota.

e While the meeting was primarily a discussion between the licensee and NRC, it was open to members of the public as observers.

.

The following licensee and NRC personnel were in attendance, as well f

as the noted observers.

,

Northern States Power Company r

M. Wadley, Plant Manager

[

E. Watzl, Site General Manager

.)

D. Antony, Vice-President, Nuclear Generation

!

L. Eliason, President, NSP Generation i

Other NSP Employees

!

,

Nuclear Reaulatory Commission

.i H. Miller, Deputy Regional Administrator

'!

W. Shafer, Chief, Reactor Projects Branch 2

'

B. Jorgensen, Chief, Reactor Projects Section 2A

.

M. Dapas, Senior Resident Inspector, Prairie Island i

S. Ray, Senior Resident Inspector,1 onticello l

M M. Gamberoni, Licensing Project Manager, NRR l

R. Bywater, Reactor Engineer, Reactor Projects Section 2A

!

W. Stearns, Resident Inspector, Monticello l

i Other l

!

R. Cyr, Mayor, City of Red Wing R. Wilhelm, Chairman, Pierce County Board,

Ellsworth, Wisconsin

>

Others Members of the Public B.

Comments Received from Licensee i

Northern States Power Company's response to the Prairie Island Initial

'l SALP 10 Report dated April 23, 1993, had no comments requiring revision to-

!

the. specific content of the report.

Because there is no revision, the i

!

Initial SALP Report is considered the Final SALP Report.

,