December 10, 2008
SUBJECT:
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 NRC SECURITY BASELINE INSPECTION REPORT 05000266/2008404(DRS);
Dear Mr. Meyer:
On November 25, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Point Beach Nuclear Plant and at Florida Power and Light Corporate Headquarters in Juno Beach, Florida. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on November 25, 2008, with Mr. Jim Costedio and other members of your staff.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, no findings of significance were identified. However, a licensee-identified violation which was determined to be of very low security significance is listed in this report. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section VI.A.1 of the NRC Enforcement Policy because of the very low security significance of the violation and because it was entered into your corrective action program. If you contest this non-cited violation, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Point Beach Nuclear Plant.
Enclosure Contains Sensitive Unclassified Non-Safeguards Information. Upon separation, this page is decontrolled. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
However, because of the security-related concerns contained in the enclosures, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.
Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
Sincerely,
/RA/
Eric Duncan, Chief Plant Support Branch Division of Reactor Safety
Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27
Nonpublic Enclosure: Inspection Report 05000266/2008404(DRS);
w/Attachment: Supplemental Information
See Attached Distribution