IR 05000220/2021010
| ML21235A048 | |
| Person / Time | |
|---|---|
| Site: | Nine Mile Point |
| Issue date: | 08/24/2021 |
| From: | Glenn Dentel Division of Operating Reactors |
| To: | Rhoades D Exelon Generation Co, Exelon Nuclear |
| References | |
| IR 2021010 | |
| Download: ML21235A048 (8) | |
Text
August 24, 2021
SUBJECT:
NINE MILE POINT NUCLEAR STATION - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000220/2021010 AND 05000410/2021010
Dear Mr. Rhoades:
On August 12, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Nine Mile Point Nuclear Station and discussed the results of this inspection with Mr. Adam Schuerman and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Glenn T. Dentel, Chief Engineering Branch 2 Division of Operating Reactor Safety
Docket Nos. 05000220 and 05000410 License Nos. DPR-63 and NPF-69
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000220 and 05000410
License Numbers:
Report Numbers:
05000220/2021010 and 05000410/2021010
Enterprise Identifier: I-2021-010-0016
Licensee:
Exelon Generation Company, LLC
Facility:
Nine Mile Point Nuclear Station
Location:
Oswego, NY
Inspection Dates:
July 26, 2021 to August 12, 2021
Inspectors:
C. Bickett, Senior Reactor Inspector
L. Dumont, Reactor Inspector
C. Hobbs, Reactor Inspector
D. Kern, Senior Reactor Inspector
M. Patel, Senior Reactor Inspector
Approved By:
Glenn T. Dentel, Chief
Engineering Branch 2
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Nine Mile Point Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.
Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.
However, all the inspection activities were performed onsite.
REACTOR SAFETY
===71111.21N.05 - Fire Protection Team Inspection (FPTI)
Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)===
The inspectors verified that the following systems credited in the approved fire protection program could perform their licensing basis function:
- (1) Unit 1 Emergency Cooling System
- (2) Unit 1 Core Spray System
- (3) Unit 1 Fire Protection Water Supply System
- (4) Unit 1 Fire Barriers
- (5) Unit 2 Safety Relief Valves
- (6) Unit 2 Residual Heat Removal System
- (7) Unit 2 Fire Protection Water Supply System
- (8) Unit 2 Fire Barriers
Fire Protection Program Administrative Controls (IP Section 03.02) (4 Samples)
The inspectors verified that the selected administrative control or process was implemented in accordance with the current licensing basis. The inspectors ensured that the fire protection program contained adequate procedures to implement the selected administrative control and that the selected administrative control met the requirements of all committed industry standards.
- (1) Unit 1 Fire Protection System Impairment Control
- (2) Unit 1 National Fire Protection Association (NFPA) 805 Monitoring Program
- (3) Unit 2 Fire Protection System Impairment Control
- (4) Unit 2 Combustible Control Program
Fire Protection Program Changes/Modifications (IP Section 03.03) (4 Samples)
The inspectors reviewed the following changes to ensure that they did not constitute an adverse effect on the ability to safely shutdown post-fire and did not degrade assumptions and performance capability stated in the safe shutdown analysis. The inspectors verified that fire protection program documents and procedures affected by the changes were updated.
- (1) Unit 1 ECP-20-000210, Upgrade Diesel Fire Pump Alternate Supply Fuse
- (2) Unit 1 ECP-21-000074, Extend Surveillance Testing Interval of the Electric Fire Pump
- (3) Unit 2 FPEE2-19-001, Use of Non-IEEE-383 Rated Cabling on the Refueling Floor
- (4) Unit 2 FPEE2-20-001, Review of Fire Damper Testing
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On August 12, 2021, the inspectors presented the triennial fire protection inspection results to Mr. Adam Schuerman and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.21N.05 Calculations
S13.1-100F002
Fire Protection Water Supply
Corrective Action
Documents
03992068
04177783
208724
263696
268283
288697
04328835
04337624
04359366
04368005
04374440
04388247
04415668
04424579
04425591
04425598
04426317
Corrective Action
Documents
Resulting from
Inspection
04434317
04437318
04437336
04437464
04437709
04439263
04440093
04440187
04440250
04440254
Engineering
Changes
ECP-21-000074
Extend the Testing Frequency of the Unit 1 Electric Fire
Pump, Unit 2 Electric Fire Pump, and Unit 2 Diesel Fire
Pump from Monthly to Quarterly
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Engineering
Evaluations
FPEE2-19-001
Use of Non IEEE-383 Rated Cabling on the Refuel Floor
FPEE2-20-001
Review of Fire Damper Testing
Miscellaneous
DCD-805
Nine Mile Point Unit 1 NFPA 805 Design Criteria
E208
Nine Mile Point Unit 1 Nuclear Safety Capability
Assessment
N1-PRA-005.20
Nine Mile Point Unit 1 Probabilistic Risk Assessment Fire
Protection Water Injection System Notebook
Procedures
N1-FRE-F001
Fire Risk Evaluation Report
N1-PM-C3
Electric and Diesel Fire Pump Performance Tests
05/05/2021
N1-SOP-21.1
Fire in Plant
N1-SOP-21.2
Control Room Evacuation
N2-FSP-FPP-
R001
Fire Rated Assemblies and Watertight Penetration Visual
Inspection
00500
N2-FSP-FPP-
R002
Fire Damper Operation and Inspection
013T1
N2-OP-52
N2-OP-78
Remote Shutdown System
N2-SOP-34
Stuck Open Safety Relief Valve
N2-SOP-78
Control Room Evacuation
NMP2-P306C
Cable and Mechanical Penetration Stops and Seals
Fire Protection System Impairment Control
Control of Transient Combustible Material
OP-NM-102-106
Operator Response Time Program at Nine Mile Point
OP-NM-201-105
Compensatory Measures for Inoperable Fire Protection
Systems and Components
Work Orders
C92692919
C92757601
C93175479
C93636525
C93672489
C93710683