ENS Event | |
---|---|
20:00 Dec 18, 2013 | |
Title | Safety Function for the Hpci Suction Automatic Low Cst Level Swap Over Inoperable |
Event Description | During the performance of surveillance testing on 12/17/2013 for the HPCI CST low water level switch instrument functional test, the safety function for the low CST level suction swap-over was lost.
While performing testing, 23LS-75B setpoint was found to be below the TS required value with 23LS-74B already declared inoperable. Tech Spec 3.3.5.1 Condition D was entered and within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> of finding 23LS-75B setpoint below the TS required value, this switch was adjusted to within tolerance as allowed by procedure and tested satisfactory. Both switches were inoperable concurrently for a period of less than 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from time of discovery of 23LS-75B being out of tolerance. This issue has been discussed with the NRC Resident Inspector. |
Where | |
---|---|
Fitzpatrick ![]() New York (NRC Region 1) | |
Reporting | |
10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | |
LER: | 05000333/LER-2013-006 |
Time - Person (Reporting Time:+-1.07 h-0.0446 days <br />-0.00637 weeks <br />-0.00147 months <br />) | |
Opened: | John Walkowiak 18:56 Dec 18, 2013 |
NRC Officer: | Donald Norwood |
Last Updated: | Dec 18, 2013 |
49660 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 49660\u003C/a\u003E - \u003Ca href=\"/FitzPatrick\" title=\"FitzPatrick\"\u003EFitzPatrick\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003ESafety Function for the Hpci Suction Automatic Low Cst Level Swap Over Inoperable\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 49660 - FitzPatrick\n","link":"","lat":43.52241111111111,"lon":-76.39899444444444,"icon":"/w/images/b/be/Constellation_icon.png"}],"imageoverlays":null} | |
Unit 1 | |
---|---|
Reactor critical | Critical |
Scram | No |
Before | Power Operation (100 %) |
After | Power Operation (100 %) |
FitzPatrick ![]() | |
WEEKMONTHYEARENS 571202024-05-09T20:29:0009 May 2024 20:29:00
[Table view]10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident High Pressure Coolant Injection Inoperable ENS 558712022-04-29T16:51:00029 April 2022 16:51:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident High Pressure Coolant Injection (HPCI) Inoperable ENS 555932021-11-18T22:02:00018 November 2021 22:02:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident High Pressure Coolant Injection Inoperable Due to Isolation Valve Failure to Automatically Open ENS 546572020-04-10T07:00:00010 April 2020 07:00:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident High Pressure Core Injection System Declared Inoperable ENS 526642017-04-04T11:35:0004 April 2017 11:35:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident High Pressure Coolant Injection Inadvertently Isolated During Conduct of Maintenance Surveillance ENS 516132015-12-18T22:22:00018 December 2015 22:22:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident Both Trains of Containment Atmosphere Dilution System Inoperable ENS 509792015-04-12T22:00:00012 April 2015 22:00:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident Temporary Loss of Control Room Envelope Boundary ENS 505322014-10-13T23:35:00013 October 2014 23:35:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident High Pressure Core Injection Degraded Accident Mitigation Capability ENS 502102014-06-18T19:45:00018 June 2014 19:45:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident Loss of Hpci Room Cooling ENS 496602013-12-18T20:00:00018 December 2013 20:00:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident Safety Function for the Hpci Suction Automatic Low Cst Level Swap Over Inoperable ENS 484102012-10-16T11:00:00016 October 2012 11:00:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident Shutdown Cooling Isolation Capability Lost ENS 482702012-09-03T06:25:0003 September 2012 06:25:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident Hpci Inoperable Due to Erroneous Indication on Flow Indicating Controller ENS 482582012-08-30T16:15:00030 August 2012 16:15:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident Hpci Inoperable Due to Failed Pressure Control Valve ENS 463552010-10-23T04:45:00023 October 2010 04:45:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident Hpci Declared Inoperable Due to Power Supply Failure ENS 450082009-04-22T15:21:00022 April 2009 15:21:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident High Pressure Coolant Injection (Hpci) System Inoperable ENS 429642006-11-04T23:10:0004 November 2006 23:10:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident Hpci Inoperable 2024-05-09T20:29:00 | |