MONTHYEARDCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System DCL-23-092, Material Status Report for the Period Ending August 31, 20232023-09-28028 September 2023 Material Status Report for the Period Ending August 31, 2023 DCL-23-077, License Amendment Request 23-02 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-27027 September 2023 License Amendment Request 23-02 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors DCL-23-083, Upcoming Meeting with Nuclear Security and Incident Response Staff2023-09-13013 September 2023 Upcoming Meeting with Nuclear Security and Incident Response Staff DCL-23-078, Nuclear Material Transaction Report for New Fuel2023-09-0606 September 2023 Nuclear Material Transaction Report for New Fuel DCL-23-070, Withdrawal of Request Regarding Senior Reactor Operator License Application2023-08-16016 August 2023 Withdrawal of Request Regarding Senior Reactor Operator License Application DCL-23-068, Nuclear Material Transaction Report for New Fuel2023-08-0909 August 2023 Nuclear Material Transaction Report for New Fuel DCL-23-066, Nuclear Material Transaction Report for New Fuel2023-08-0303 August 2023 Nuclear Material Transaction Report for New Fuel DCL-23-065, Letter DCL-23-065 Request That Exam Material Be Withheld from Public Disclosure2023-07-27027 July 2023 Letter DCL-23-065 Request That Exam Material Be Withheld from Public Disclosure DCL-23-064, Nuclear Material Transaction Report for New Fuel2023-07-26026 July 2023 Nuclear Material Transaction Report for New Fuel DCL-23-054, License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-07-13013 July 2023 License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-23-055, Nuclear Material Transaction Report for New Fuel2023-07-0606 July 2023 Nuclear Material Transaction Report for New Fuel DCL-23-042, Independent Spent Fuel Storage Installation, Submittal of Quality Assurance Program Description, Revision 02023-05-24024 May 2023 Independent Spent Fuel Storage Installation, Submittal of Quality Assurance Program Description, Revision 0 DCL-23-032, Independent Spent Fuel Storage Installation Docket No. 72-27, Materials License Number SNM-2514 Humboldt Bay Independent Spent Fuel Storage Installation - NRC Requested Notification of Withdrawal from Voluntary Program2023-05-22022 May 2023 Independent Spent Fuel Storage Installation Docket No. 72-27, Materials License Number SNM-2514 Humboldt Bay Independent Spent Fuel Storage Installation - NRC Requested Notification of Withdrawal from Voluntary Program DCL-23-041, 10 CFR 50.46 Annual Report of Emergency Core Cooling System Evaluation Model Changes for Peak Cladding Temperature for 20222023-05-22022 May 2023 10 CFR 50.46 Annual Report of Emergency Core Cooling System Evaluation Model Changes for Peak Cladding Temperature for 2022 DCL-23-038, Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule2023-05-15015 May 2023 Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule DCL-23-034, 2022 Annual Nonradiological Environmental Operating Report2023-05-0101 May 2023 2022 Annual Nonradiological Environmental Operating Report DCL-23-036, 2022 Annual Radiological Environmental Operating Report2023-05-0101 May 2023 2022 Annual Radiological Environmental Operating Report DCL-23-025, 2022 Annual Radioactive Effluent Release Report2023-05-0101 May 2023 2022 Annual Radioactive Effluent Release Report DCL-2023-512, Submittal of Receiving Water Monitoring Program 2022 Annual Report2023-04-27027 April 2023 Submittal of Receiving Water Monitoring Program 2022 Annual Report DCL-23-035, Response to Request for Additional Information on Request Regarding Senior Reactor Operator License Application2023-04-24024 April 2023 Response to Request for Additional Information on Request Regarding Senior Reactor Operator License Application DCL-23-028, Technical Specification Bases, Revision 142023-04-24024 April 2023 Technical Specification Bases, Revision 14 DCL-2023-511, Report on Discharge Monitoring for the First Quarter of 20232023-04-20020 April 2023 Report on Discharge Monitoring for the First Quarter of 2023 DCL-23-031, Submittal of Annual Report of Occupational Radiation Exposure for 20222023-04-19019 April 2023 Submittal of Annual Report of Occupational Radiation Exposure for 2022 DCL-23-024, Independent Spent Fuel Storage Installation, Response to Nrg Request for Additional Information for Revision to License Amendment Request 22-01 Request for Approval of Alternative Security Measures for Early Warning System2023-04-0404 April 2023 Independent Spent Fuel Storage Installation, Response to Nrg Request for Additional Information for Revision to License Amendment Request 22-01 Request for Approval of Alternative Security Measures for Early Warning System DCL-23-022, 2023 Annual Statement of Insurance for Pacific Gas and Electric Companys Diablo Canyon Power Plant2023-03-29029 March 2023 2023 Annual Statement of Insurance for Pacific Gas and Electric Companys Diablo Canyon Power Plant DCL-23-023, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22023-03-28028 March 2023 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 DCL-23-021, Independent Spent Fuel Storage Installation, Emergency Plan Update2023-03-23023 March 2023 Independent Spent Fuel Storage Installation, Emergency Plan Update DCL-23-020, Responses to NRC Questions Regarding License Renewal Efforts2023-03-17017 March 2023 Responses to NRC Questions Regarding License Renewal Efforts DCL-23-009, Owner'S Activity Report for Unit 2 Twenty-Third Refueling Outage2023-02-22022 February 2023 Owner'S Activity Report for Unit 2 Twenty-Third Refueling Outage DCL-23-008, Request Regarding Senior Reactor Operator License Application2023-02-22022 February 2023 Request Regarding Senior Reactor Operator License Application DCL-2023-503, Annual Sea Turtle Report2023-01-26026 January 2023 Annual Sea Turtle Report DCL-2023-502, (DCPP) 4th Quarter 2022 Report on Discharge Self-Monitoring2023-01-18018 January 2023 (DCPP) 4th Quarter 2022 Report on Discharge Self-Monitoring DCL-22-091, Revised Steam Generator Tube Inspection Report for Twenty-First Refueling Outage2022-12-20020 December 2022 Revised Steam Generator Tube Inspection Report for Twenty-First Refueling Outage DCL-22-089, Core Operating Limits Report for Unit 2 Cycle 242022-12-20020 December 2022 Core Operating Limits Report for Unit 2 Cycle 24 DCL-22-085, Request to Resume Review of the License Renewal Application or, Alternatively, for an Exemption from 10 CFR 2.109(b), Concerning a Timely Renewal Application2022-10-31031 October 2022 Request to Resume Review of the License Renewal Application or, Alternatively, for an Exemption from 10 CFR 2.109(b), Concerning a Timely Renewal Application DCL-22-041, Site-Specific Decommissioning Cost Estimate, Revision 12022-10-12012 October 2022 Site-Specific Decommissioning Cost Estimate, Revision 1 DCL-22-042, Post-Shutdown Decommissioning Activities Report, Revision 12022-10-12012 October 2022 Post-Shutdown Decommissioning Activities Report, Revision 1 2024-01-29
[Table view] |
Text
Pacific Gas and Electric Company*
James M. Welsch Diablo Canyon Power Plant Vice President P.O. Box 56 Nuclear Generation and Avila Beach, CA 93424 Chief Nuclear Officer 805.545.3242 E-Mail: James. Welsch@pge.com May 14, 2018 PG&E Letter DCL-18-036 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Change of Commitment Dates for Full Implementation of Open Phase Detection System
References:
- 1. PG&E Letter DCL-14-118, "Supplement to Response to NRC Request for Additional Information Regarding Response to NRC Bulletin 2012-01 ,"dated December 22, 2014
- 2. PG&E Letter DCL-14-009, "Response to NRC Request for Additional Information Regarding Response to NRC Bulletin 2012-01 ,"dated February 3, 2014
Dear Commissioners and Staff:
In Reference 1, Pacific Gas and Electric Company (PG&E) committed to the following schedule for implementation of the Open Phase Detection system at Diablo Canyon Power Plant (DCPP) Units 1 and 2:
- Unit 1: Complete installation during the Unit 1 twentieth refueling outage (1 R20). Trip functions to be enabled by June 30, 2018.
- Unit 2: Complete installation during the Unit 2 twentieth refueling outage (2R20). Trip functions to be enabled by December 31, 2018.
In Reference 1, PG&E additionally stated that the planned schedule for implementation of the Open Phase Detection system may be revised based on various factors. PG&E is hereby extending the schedule for enabling the trip functions for Units 1 and 2 to December 31,2019.
A member of the STARS Alliance Callaway o Diablo Canyon o Palo Verde o Wolf Creek
Document Control Desk PG&E Letter DCL-18-036 May 14, 2018 Page 2 PG&E selected the Open Phase Detection system that was developed by the Electric Power Research Institute and Power System Sentinel Technologies, LLC.
This system was installed in each DCPP unit as previously committed. However, to improve the reliability of the equipment, digital injection source power supplies are being replaced with analog injection source power supplies. This hardware change was completed for Unit 2 in March 2018 and is planned to be completed for Unit 1 in May 2018.
PG&E is extending the Open Phase Detection system monitoring period to gather more operating experience (OE) with this new hardware configuration before enabling the Open Phase Detection system trip functions at DCPP. Additional time will also provide more OE both from DCPP and from across the industry relative to the types and characteristics of grid disturbances that could cause spurious Open Phase Detection system actuations.
The information obtained during the additional monitoring period will better inform the determination of the actuation setpoints and time delays for the system. This will minimize the potential for inadvertent system actuations once the trip functions have been enabled. Inadvertent system actuations during normal power operations would unnecessarily (1) reduce the availability of offsite power and (2) cause the emergency diesel generators on the affected DCPP unit to start and run unloaded.
The extended monitoring period will not adversely impact the safe operation of DCPP Units 1 and 2 as summarized below:
- PG&E has taken interim corrective actions in response to this industry issue, as documented in Reference 2. As part of these interim corrective actions, PG&E will continue the daily visual inspection of the 230 kV tie-line for an open phase. As stated in Reference 2, "[t]he scope of the inspection includes the line termination at the standby/startup transformers of each unit up to switchyard disconnect switches (i.e., interface with the 230 kV busses)."
- The Open Phase Detection system alarm feature itself helps operators diagnose any potential open phase condition (OPC) in offsite power.
- During normal power operation at DCPP, an OPC affecting the immediately available 230 kV source would not impact either operating unit because the station auxiliary equipment is not connected to it. Operators would promptly respond per procedural guidance and correct the OPC in a timely manner.
The Open Phase Detection trip function for the delayed access 500 kV source to DCPP is not enabled during normal power operation.
A membe r of th e STARS Alli ance Cal l aw ay
Document Control Desk PG&E Letter DCL-18-036 May 14, 2018 Page 3 This commitment change is processed in accordance with the Nuclear Energy Institute guidance for deviations to the OPC Initiative and NEI 99-04, "Guidelines for Managing NRC Commitment Changes."
If you have any questions or require additional information regarding this schedule extension, please contact Mr. Hossein Hamzehee, DCPP Regulatory Services Manager, at 805-545-4720.
Sincerely,
~~
Vice President, Nuclear Generation and Chief Nuclear Officer jmsp/4927 cc: Kriss M. Kennedy, NRC Region IV Administrator Christopher W. Newport, NRC Senior Resident Inspector Balwant K. Singal, NRC Senior Project Manager Diablo Canyon Distribution A member of the STARS Al li ance Callaw ay