MONTHYEARCPSES-201001000, Operator Licensing Examination Data, Form 5362010-07-28028 July 2010 Operator Licensing Examination Data, Form 536 CPSES-200901377, Operator Licensing Examination Data2009-09-29029 September 2009 Operator Licensing Examination Data CPSES-200701127, Response to Request for Additional Information Related to License Amendment Request (LAR) 06-009, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times.2007-11-15015 November 2007 Response to Request for Additional Information Related to License Amendment Request (LAR) 06-009, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times. CPSES-200701495, Withdrawal of License Amendment Request (LAR) 06-007, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Offsite Circuits2007-10-22022 October 2007 Withdrawal of License Amendment Request (LAR) 06-007, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Offsite Circuits CPSES-200701530, Additional Information in Connection with the Indirect Transfer of Facility Operating Licenses and Conforming License Amendments2007-10-0909 October 2007 Additional Information in Connection with the Indirect Transfer of Facility Operating Licenses and Conforming License Amendments CPSES-200701496, Information Required by Order Approving the Indirect Transfer of Facility Operating Licenses and Conforming License Amendments2007-10-0202 October 2007 Information Required by Order Approving the Indirect Transfer of Facility Operating Licenses and Conforming License Amendments CPSES-200701351, Transmittal of First-Half 2007 Fitness-for-Duty Program Performance Data2007-08-29029 August 2007 Transmittal of First-Half 2007 Fitness-for-Duty Program Performance Data CPSES-200701076, Revision to the Operating License and Technical Specifications 1.0, Use and Application and 3.7.17, Spent Fuel Assembly Storage to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt2007-08-28028 August 2007 Revision to the Operating License and Technical Specifications 1.0, Use and Application and 3.7.17, Spent Fuel Assembly Storage to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt CPSES-200701302, Relief Request B-4 to the Unit 2 Inservice Inspection (ISI) Program Plan from the 1998 Edition of ASME Code, Section XI, Through 2000 Addenda (Interval Start Date - August 03, 2004, Second Interval)2007-08-22022 August 2007 Relief Request B-4 to the Unit 2 Inservice Inspection (ISI) Program Plan from the 1998 Edition of ASME Code, Section XI, Through 2000 Addenda (Interval Start Date - August 03, 2004, Second Interval) CPSES-200701324, Supplement to License Amendment Request (LAR) 07-003 Revision to Technical Specification 3.1, Reactivity Control Systems, 3.2, Power Distribution Limits, 3.3, Instrumentation, and 5.6.5 B, Core Operating Limits2007-08-16016 August 2007 Supplement to License Amendment Request (LAR) 07-003 Revision to Technical Specification 3.1, Reactivity Control Systems, 3.2, Power Distribution Limits, 3.3, Instrumentation, and 5.6.5 B, Core Operating Limits CPSES-200701323, License Amendment Request 07-006, Revision to Technical Specification 3.1.4, Rod Group Alignment Limits, Table 3.3.1-1, Reactor Trip System Instrumentation, Table 3.3.2-1, Engineered Safety Feature Actuation System..2007-08-16016 August 2007 License Amendment Request 07-006, Revision to Technical Specification 3.1.4, Rod Group Alignment Limits, Table 3.3.1-1, Reactor Trip System Instrumentation, Table 3.3.2-1, Engineered Safety Feature Actuation System.. CPSES-200701279, Mitigation of Alloy 82/182 Pressurizer Butt Welds in 20082007-08-0303 August 2007 Mitigation of Alloy 82/182 Pressurizer Butt Welds in 2008 CPSES-200701284, (Cpses), Operator Licensing Examination Data2007-08-0202 August 2007 (Cpses), Operator Licensing Examination Data CPSES-200701238, Submittal of the CPSES Units 1 and 2 Large and Small Break LOCA Analyses2007-07-31031 July 2007 Submittal of the CPSES Units 1 and 2 Large and Small Break LOCA Analyses CPSES-200701178, Supplement to Application for Order Approving Indirect Transfer of Control of Licenses and License Amendments to Reflect Proposed Licensee Name Change (TAC Nos. MD5289 and MD5280), Enclosures 1, 4, 5, 6 & 72007-07-20020 July 2007 Supplement to Application for Order Approving Indirect Transfer of Control of Licenses and License Amendments to Reflect Proposed Licensee Name Change (TAC Nos. MD5289 and MD5280), Enclosures 1, 4, 5, 6 & 7 CPSES-200701126, Response to Request for Additional Information to License Amendment Request (LAR) 06-007 Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Offsite Circuits2007-07-18018 July 2007 Response to Request for Additional Information to License Amendment Request (LAR) 06-007 Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Offsite Circuits CPSES-200701174, Submittal of Twelfth Refueling Outage (1RF12) Inservice Inspection Summary Report (1998 Edition of ASME Code Section XI Through 2000 Addenda, Interval Start Date - 08/03/2000, Second Interval)2007-07-17017 July 2007 Submittal of Twelfth Refueling Outage (1RF12) Inservice Inspection Summary Report (1998 Edition of ASME Code Section XI Through 2000 Addenda, Interval Start Date - 08/03/2000, Second Interval) CPSES-200701065, Response to NRC Generic Letter 2007-01, Inaccessible or Underground Power Cable Failures That Disable Accident Mitigation Systems or Cause Plant Transients.2007-06-21021 June 2007 Response to NRC Generic Letter 2007-01, Inaccessible or Underground Power Cable Failures That Disable Accident Mitigation Systems or Cause Plant Transients. CPSES-200700951, (Cpses), Unit 1, Pressurizer Weld Overlay 60 Day Report and Update for Unit 1 Reactor Pressure Vessel Head Replacement Regarding Revised Order EA-03-0092007-06-19019 June 2007 (Cpses), Unit 1, Pressurizer Weld Overlay 60 Day Report and Update for Unit 1 Reactor Pressure Vessel Head Replacement Regarding Revised Order EA-03-009 CPSES-200701059, Submittal of Startup Report, Cycle 132007-06-13013 June 2007 Submittal of Startup Report, Cycle 13 CPSES-200700738, License Amendment Request (LAR) 07-001 Revision to Technical Requirements Surveillance 13.3.33.2 Frequency for the Turbine Stop and Control Valves2007-05-22022 May 2007 License Amendment Request (LAR) 07-001 Revision to Technical Requirements Surveillance 13.3.33.2 Frequency for the Turbine Stop and Control Valves CPSES-200700915, Supplemental Response to Request for Information on Generic Letter 2003-01, Control Room Habitability2007-05-0707 May 2007 Supplemental Response to Request for Information on Generic Letter 2003-01, Control Room Habitability CPSES-200700871, Transmittal of Year 2006 Radioactive Effluent Release Report2007-04-30030 April 2007 Transmittal of Year 2006 Radioactive Effluent Release Report CPSES-200700859, Submittal of the Annual Non-Radiological Environmental Operating Report for 20062007-04-27027 April 2007 Submittal of the Annual Non-Radiological Environmental Operating Report for 2006 CPSES-200700517, Application for Order Approving Indirect Transfer of Control of Licenses and License Amendments to Reflect Proposed Licensee Name Change2007-04-18018 April 2007 Application for Order Approving Indirect Transfer of Control of Licenses and License Amendments to Reflect Proposed Licensee Name Change CPSES-200700719, Nuclear Liability Insurance2007-04-10010 April 2007 Nuclear Liability Insurance CPSES-200700605, License Amendment Request (LAR) 07-003, Revision to Technical Specifications 3.1, Reactivity Control Systems, 3.2, Power Distribution Limits, 3.3, Instrumentation, & 5.6.5b, Core Operating Limits Report2007-04-10010 April 2007 License Amendment Request (LAR) 07-003, Revision to Technical Specifications 3.1, Reactivity Control Systems, 3.2, Power Distribution Limits, 3.3, Instrumentation, & 5.6.5b, Core Operating Limits Report CPSES-200700708, Evaluation of Pressurizer Weld Overlay Confirmatory Analyses2007-04-0505 April 2007 Evaluation of Pressurizer Weld Overlay Confirmatory Analyses CPSES-200700691, Core Operating Limits Report, Cycle 132007-04-0404 April 2007 Core Operating Limits Report, Cycle 13 CPSES-200700663, Transmittal of the Annual Radiological Environmental Operating Report for 20062007-03-30030 March 2007 Transmittal of the Annual Radiological Environmental Operating Report for 2006 CPSES-200700607, Property Damage Insurance2007-03-29029 March 2007 Property Damage Insurance CPSES-200700606, Decommissioning Report2007-03-29029 March 2007 Decommissioning Report CPSES-200700573, Request to Withdraw Relief Request A-72007-03-22022 March 2007 Request to Withdraw Relief Request A-7 CPSES-200700571, Supplement to License Amendment Request (LAR) 05-06; Revision to Technical Specification 5.6.5 Revise Listing of LOCA and Non-LOCA Analysis Methodologies (TAC Nos. MD0185/0186)2007-03-19019 March 2007 Supplement to License Amendment Request (LAR) 05-06; Revision to Technical Specification 5.6.5 Revise Listing of LOCA and Non-LOCA Analysis Methodologies (TAC Nos. MD0185/0186) CPSES-200700515, Day Response to NRC Generic Letter 2007-01, Inaccessible or Underground Power Cable Failures That Disable Accident Mitigation Systems or Cause Plant Transients.2007-03-0909 March 2007 Day Response to NRC Generic Letter 2007-01, Inaccessible or Underground Power Cable Failures That Disable Accident Mitigation Systems or Cause Plant Transients. CPSES-200700454, Transmittal of Second-Half 2006 Fitness-For-Duty Program Performance Data2007-02-28028 February 2007 Transmittal of Second-Half 2006 Fitness-For-Duty Program Performance Data CPSES-200700451, Annual Operating Report for 20062007-02-28028 February 2007 Annual Operating Report for 2006 CPSES-200700422, Response to Request for Additional Information Related to Txu Power'S Request for Review of Previously Submitted Topical Reports2007-02-22022 February 2007 Response to Request for Additional Information Related to Txu Power'S Request for Review of Previously Submitted Topical Reports CPSES-200700414, Transmittal of Inservice Inspection Program Plan, Revision 5 (Unit 1: ASME Code Section XI 1998 Edition, 1999 and 2000 Addenda, Interval Start Date - 08/13/200, Second Interval)2007-02-22022 February 2007 Transmittal of Inservice Inspection Program Plan, Revision 5 (Unit 1: ASME Code Section XI 1998 Edition, 1999 and 2000 Addenda, Interval Start Date - 08/13/200, Second Interval) CPSES-200700391, Inspection and Mitigation of Alloy 82/182 Pressurizer Butt Welds2007-02-20020 February 2007 Inspection and Mitigation of Alloy 82/182 Pressurizer Butt Welds CPSES-200700346, Guarantees of Payment of Deferred Premiums, Submits Form 10-Q for the Period Ending September 30, 20062007-02-0808 February 2007 Guarantees of Payment of Deferred Premiums, Submits Form 10-Q for the Period Ending September 30, 2006 CPSES-200700229, Comanche, Response to Request for Additional Information, Relief Request B-6 for the Unit 1 Inservice Inspection (ISI) Program Plan from the 1998 Edition of ASME Code, Section XI, Through 2000 Addenda (Interval Start Date..2007-02-0202 February 2007 Comanche, Response to Request for Additional Information, Relief Request B-6 for the Unit 1 Inservice Inspection (ISI) Program Plan from the 1998 Edition of ASME Code, Section XI, Through 2000 Addenda (Interval Start Date.. CPSES-200700169, Inspection and Mitigation of Alloy 82/182 Pressurizer Butt Welds2007-01-30030 January 2007 Inspection and Mitigation of Alloy 82/182 Pressurizer Butt Welds CPSES-200700147, Response to Request for Additional Information Regarding Resolution of Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power2007-01-29029 January 2007 Response to Request for Additional Information Regarding Resolution of Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power CPSES-200700127, Submittal of Unit 2 Ninth Refueling Outage (2RF09) Inservice Inspection (ISI) Summary Report (Unit 2: 1998 Edition of ASME Code Section XI, Through 2000 Addenda, Interval Start Date - August 3, 2004, Second Interval)2007-01-24024 January 2007 Submittal of Unit 2 Ninth Refueling Outage (2RF09) Inservice Inspection (ISI) Summary Report (Unit 2: 1998 Edition of ASME Code Section XI, Through 2000 Addenda, Interval Start Date - August 3, 2004, Second Interval) CPSES-200700130, License Amendment Request (LAR) 06-009, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Diesel Generators2007-01-18018 January 2007 License Amendment Request (LAR) 06-009, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Diesel Generators CPSES-200700146, License Amendment Request (LAR) 06-007, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Offsite Circuits2007-01-18018 January 2007 License Amendment Request (LAR) 06-007, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Offsite Circuits CPSES-200700099, Annual Report of Changes in Peak Cladding Temperature2007-01-10010 January 2007 Annual Report of Changes in Peak Cladding Temperature CPSES-200602341, License Amendment Request (LAR) 06-006, Revision to Technical Specification (TS) 5.5.8, Inservice Testing Program2006-12-19019 December 2006 License Amendment Request (LAR) 06-006, Revision to Technical Specification (TS) 5.5.8, Inservice Testing Program CPSES-200602340, License Amendment Request (LAR) 06-012, Revision to Technical Specification 3.7.5, Auxiliary Feedwater System, TS 3.8.1, AC Sources - Operating, & TS 3.8.9, Distribution Systems - Operating.2006-12-19019 December 2006 License Amendment Request (LAR) 06-012, Revision to Technical Specification 3.7.5, Auxiliary Feedwater System, TS 3.8.1, AC Sources - Operating, & TS 3.8.9, Distribution Systems - Operating. 2010-07-28
[Table view] |
Text
v4' Power TXU Power Mike Blevins Comanche Peak Steam Senior Vice President & Ref: 10CFR50.90 Electric Station Chief Nuclear Officer P. 0. Box 1002 (E01)
Glen Rose, TX 76043 Tel: 254 897 5209 Fax: 254 897 6652 mike.blevinsftxu.com CPSES-200501761 Log# TXX-05157 August 31, 2005 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)
DOCKET NOS. 50-445 AND 50-446 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION FOR LICENSE AMENDMENT REQUEST (LAR) 04-002: REVISION TO TECHNICAL SPECIFICATION (TS) 3.3.2 ENGINEERED SAFETY FEATURES ACTUATION SYSTEM (ESFAS)
INSTRUMENTATION (TAC NO. MB2620/2621)
REF: 1) TXU Energy letter logged TXX-04049 from Mike Blevins to the NRC dated April 13, 2004
- 2) NRC letter from Mohan C. Thadani to Michael R. Blevins dated February 16, 2005
- 3) Letter from Alexander Marion, Nuclear Energy Institute, to James E. Lyons, Deputy Director, Division of Licensing Project Management dated March 18, 2005
- 4) TXU Power letter logged TXX-05067 from Mike Blevins to the NRC dated March 18, 2005
- 5) Letter from James A. Lyons, Deputy Director, Division of Licensing Project Management to Alexander Marion, Nuclear Energy Institute dated March 31, 2005.
- 6) Facsimile transmission from David H. Jaffe, NRC, to Rob Slough, TXU Power dated April 11, 2005.
Gentlemen:
In reference I above, TXU Generation Company LP (TXU Power) transmitted an application for amendment to Facility Operating License Number NPF-87 and NPF-89 for CPSES Unit 1 and Unit 2. The proposed amendment would revise the trip setpoint allowable value for Refueling Water Storage Tank (RWST) Level Low-Low (ESFAS function 7.b) for Unit 2 to be the same as for Unit 1. This change would A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway
r4 TXX-05157 Page 2 of 4 also revise the frequency for calibration of the RWST water level transmitters for both units from 9 months to 18 months. Reference 2 forwarded a request for additional information to support the amendment application.
As part of a proposed generic resolution to the issues pertaining to the use of the Instrumentation, Systems, and Automation Society (ISA) Standard, ISA 67.04, Part II, Method 3, reference 3 forwarded a request from the Nuclear Energy Institute for the NRC staff to withdraw Requests for Additional Information (RAIs) concerning license amendment requests (LARs) involving instrument setpoints that are based on ISA Method 3.
Reference 4 provided TXU Power's response to the Staffs request for additional information in reference 2 and stated TXU Power's intention to conform to the industry resolution of this issue in any future submittals involving setpoints.
On March 31, 2005, reference 5 provided NRC's response to the Nuclear Energy Institute's letter of March 18, 2005 (reference 3). Reference 6 forwarded the NRC letter of March 31, 2005 (reference 5) to TXU Power for action.
This letter provides TXU Power's response to the request for additional information forwarded in reference 6.
In reference 5, the NRC stated ". . .the licensee's response ... needs to contain the following in order for the staff to complete its review:
- 1. An explicit regulatory commitment to adopt the final TSTF Technical Specification change to come into conformance with the existing understanding of the requirements of 10CFR50.36.
- 2. An explicit regulatory commitment to assess the operability of tested instrumentation based on the previous as-left instrument setting and accounting for the uncertainties associated with the test or calibration.
- 3. A revision to the Technical Specifications for the LSSS being changed by the LAR to incorporate a footnote that states:
The as-left instrument setting shall be returned to a setting within the tolerance band of the trip setpoint established to protect the safety limit."
TXU Power hereby makes an explicit regulatory commitment to submit a license amendment request to adopt the final TSTF Technical Specification changes, as they may be applicable to CPSES, for the first proposed setpoint related change occurring more than 120 days after the approved TSTF is made available for adoption via the consolidated line item improvement process (CLIIP).
TXX-05157 Page 3 of 4 TXU Power currently assesses the operability and performance of the RWST Level Low-Low instrumentation, when tested, based on as-found instrument setting compared to calibration tolerances and allowable values. These values account for uncertainties associated with the test or calibration and instrument drift. If the instrument is found beyond the Allowable Value, it is declared inoperable; if it is found outside the calibration tolerance about the Nominal Trip Setpoint but within, or more conservative than, the Allowable Value, the channel is evaluated in the corrective action program for performance, reliability, and continued long-term operability. TXU Power will include any changes or clarifications to this practice in the future License Amendment Request committed to above.
The attachment to this letter contains proposed changes to the CPSES Unit I and Unit 2 Technical Specifications which incorporate the footnote as requested in item 3 of reference 5. These new pages replace the pages previously submitted in Attachments 2 and 4 of reference 1. These provisions were already contained in the TS Bases.
The additional information provided in this letter and attachment does not impact the conclusions of the No Significant Hazards Consideration provided in reference 1. In accordance with 10 CFR 50.91, a copy of this submittal is being provided to the designated Texas State official.
This communication contains the following new commitments which will be completed or incorporated into the CPSES licensing basis as noted:
Number Commitment Due Date/Event 27364 Submit a license amendment For the first proposed setpoint related request to adopt the final TSTF change occurring more than 120 days technical specification change, as after the approved TSTF is made it may be applicable to CPSES. available for adoption via the consolidated line item improvement process (CLIIP).
The Commitment number is used by TXU Power for the internal tracking of CPSES commitments.
Should you have any questions, please contact Robert A. Slough at (254) 897-5727.
TXX-05157 Page 4 of 4 I state under penalty of pedury that the foregoing is true and correct.
Executed on August 31, 2005.
Sincerely, TXU Generation Company LP By: TXU Generation Management Company LLC Its General Partner Mike Blevins By:
Fred W. Madden Director, Regulatory Affairs RAS Attachment c - B. S. Mallett, Region IV M. C. Thadani, NRR Resident Inspectors, CPSES Ms. Alice Rogers Bureau of Radiation Control Texas Department of Public Health 1100 West 49th Street Austin, Texas 78756-3189
Attachment to TXX-05157 ESFAS Instrumentation Page 1 of 2 3.3.2 Table 3.3.2-1 (page 6 of 6)
Engineered Safety Feature Actuation System Instrumentation APPLICABLE MODES OR OTHER SPECIFIED REQUIRED SURVEILLANCE ALLOWABLE FUNCTION CONDITIONS CHANNELS CONDITIONS REQUIREMENTS VALUE(a)
- 7. Automatic Switchover to Containment Sump
- a. Automatic 1, 2, 3, 4 2 trains C SR 3.3.2.2 NA Actuation Logic SR 3.3.2.4 and Actuation SR 3.3.2.6 Relays
- b. Refueling 1,2,3,4 4 K SR 3.3.2.1 2 43.9% 73 Water Storage SR 3.3.2.5 Instrument spq+ I Tank (RWST) SR 3.3.2.10 Level - Low SR3.3.2.1 A 73 Low p Coincident with Refer to Function 1 (Safety Injection) for all initiation functions and requirements.
Safety Injection
- 8. ESFAS Interlocks
- a. Reactor Trip, 1,2,3 1 per train, 2 F SR 3.3.2.11 NA P-4 trains
- b. Pressurizer 1,2,3 3 L SR 3.3.2.5 s 1975.2 psig Pressure, P-11 SR 3.3.2.9 (Unit 1) s 1976.4 psig (Unit 2)
(a) The Allowable Value defines the limiting safety system setting. See the Bases for the Trip Setpoints.
(q) Theas-left instrument setting shall be retumed to a setting within the tolerance band of the Trip Setpoint established to protect the safety limit.
COMANCHE PEAK - UNITS 1 AND 2 3.3-34 Amendment No. -73
Attachment to TXX-05nnn ESFAS Instrumentation Page 2 of 2 3.3.2 Table 3.3.2-1 (page 6 of 6)
Engineered Safety Feature Actuation System Instrumentation APPLICABLE MODES OR OTHER SPECIFIED REQUIRED SURVEILLANCE ALLOWABLE FUNCTION CONDITIONS CHANNELS CONDITIONS REQUIREMENTS VALUE(a)
- 7. Automatic Switchover to Containment Sump
- a. Automatic 1, 2, 3, 4 2 trains C SR 3.3.2.2 NA Actuation Logic SR 3.3.2.4 and Actuation SR 3.3.2.6 Relays
- b. Refueling 1, 2, 3, 4 4 K SR 3.3.2.1 2 43.9%
Water Storage SR 3.3.2.5 Instrument span (q)
Tank (RWST) SR 3.3.2.9 Level - Low SR 3.3.2.10 Low Coincident with Refer to Function 1 (Safety Injection) for all initiation functions and requirements.
Safety Injection
- 8. ESFAS Interlocks
- a. Reactor Trip, 1,2,3 1 per train, 2 F SR 3.3.2.11 NA P-4 trains
- b. Pressurizer 1,2,3 3 L SR 3.3.2.5 S 1975.2 psig Pressure, P-11 SR 3.3.2.9 (Unit 1) s 1976.4 psig (Unit 2)
(a) The Allowable Value defines the limiting safety system setting. See the Bases for the Trip Setpoints.
(q) The as-left instrument setting shall be retumed to a setting within the tolerance band of the Trip Setpoint established to protect the safety limit. I COMANCHE PEAK - UNITS 1 AND 2 3.3-34 Amendment No.