License Amendment Request #296, Revision 0, Measurement Uncertainty Recapture Uprate, Submittal Schedule Update
ML071710556
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 06/18/2007
From: Young D
Progress Energy Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
3F0607-04
Download: ML071710556 (5)


Text

Progress Energy Crystal River Nuclear Plant Docket No. 50-302 Operating License No. DPR-72 Ref: 10CFR50.90 June 18, 2007 3F0607-04 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

Subject:

Crystal River Unit 3 - License Amendment Request #296, Revision 0, Measurement Uncertainty Recapture Uprate, Submittal Schedule Update

Reference:

Crystal River Unit 3 - License Amendment Request #296, Revision 0, Measurement Uncertainty Recapture Uprate, dated April 25, 2007

Dear Sir:

Florida Power Corporation (FPC), doing business as Progress Energy Florida, Inc., hereby submits a revision to the schedule for supplemental submittals for License Amendment Request (LAR) #296, Revision 0. The proposed submittals will include the following information:

1) the results of a grid reliability analysis for the uprated conditions,
2) the conclusions of the FPC evaluation of impact of the uprated conditions on operator actions,
3) clarifications of the description of the proposed changes (Attachments A and D) relative to the proposed No Significant Hazards Consideration Determination, and
4) withdrawal of the revised containment response analysis (Attachment F) and corresponding changes to the CR-3 Improved Technical Specifications.

Regulatory Issue. Summary (RIS) 2002-03 provided guidance for submittals requesting power uprates involving feedwater flow measurement uncertainty recapture. The RIS stated that licensee's applications which follow this guidance will require less review time. FPC believes the additional information described above will fully comply with NRC expectations for meeting the guidance in the RIS. FPC will provide the above information by June 29, 2007.

Regulatory commitments are identified in the Attachment to this letter.

Progress Energy Florida, Inc.

Crystal River Nuclear Plant 15760 W. Powerline Street Crystal River, FL 34428

U.S. Nuclear Regulatory Commission Page 2 of 3 3F0607-04 If you have any questions regarding this submittal, please contact Mr. Paul Infanger, Supervisor, Licensing and Regulatory Programs at (352) 563-4796.

Sincerely, Dale E. Young Vice President Crystal River Nuclear Plant DEY/pei

Attachment:

List of Regulatory Commitments xc: NRR Project Manager Regional Administrator, Region II Senior Resident Inspector State Contact

U.S. Nuclear Regulatory Commission Page 3 of 3 3F0607-04 STATE OF FLORIDA COUNTY OF CITRUS Dale E. Young states that he is the Vice President, Crystal River Nuclear Plant for Florida Power Corporation, doing business as Progress Energy Florida, Inc.; that he is authorized on the part of said company to sign and file with the Nuclear Regulatory Commission the information attached hereto; and that all such statements made and matters set forth therein are true and correct to the best of his knowledge, information, and belief.

Dale E. Young Vice President Crystal River Nuclear Plant 4'k-The foregoing document was acknowledged before me this I day of 2007, by Dale E. Young.

Signature of Notary Pub --- -8 IM O.XI State of Florida MCMMSION#DD4 EXPIRES: July 8,20 B=WeThmuNo~aiyPd*IUOX (Print, type, or stamp Commissioned Name of Notary Public)

Personally/ Produced Known '/ -OR- Identification

FLORIDA POWER CORPORATION CRYSTAL RIVER UNIT 3 DOCKET NUMBER 50-302/LICENSE NUMBER DPR-72 LICENSE AMENDMENT REQUEST #296, REVISION 0, SUBMITTAL SCHEDULE UPDATE ATTACHMENT LIST OF REGULATORY COMMITMENTS

U.S. Nuclear Regulatory Commission Attachment 3F0607-04 Page 1 of 1 List of Regulatory Commitments The following table identifies those actions committed to by Florida Power Corporation (FPC) in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments. Please direct questions regarding these commitments to Mr. Paul Infanger, Supervisor, Licensing & Regulatory Programs at (352) 563-4796.

Regulatory Commitments Due Date FPC will submit the following information in support of License Amendment June 29, 2007 Request #296, Revision 0, Measurement Uncertainty Recapture Uprate:

1) the results of a grid reliability analysis for the uprated conditions,
2) the conclusions of the FPC evaluation of impact of the uprated conditions on operator actions,
3) clarifications of the description of the proposed changes (Attachments A and D) relative to the proposed No Significant Hazards Consideration Determination, and
4) withdrawal of the revised containment response analysis (Attachment F) and corresponding changes to the CR-3 Improved Technical Specifications.