05000499/LER-2008-003

From kanterella
Jump to navigation Jump to search
LER-2008-003, Inoperable Component Cooling Water Train
Docket Number
Event date:
Report date:
Reporting criterion: 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications

10 CFR 50.73(a)(2)(i)
4992008003R00 - NRC Website

DESCRIPTION OF EVENT

A. REPORTABLE EVENT CLASSIFICATION

This event is reportable pursuant to 10 CFR 50.73(a)(2)(i)(B). South Texas Project (STP) Technical Specification 3.7.3 allows one train of Component Cooling Water (CCW) to be inoperable in Modes 1 through 4 for seven days before taking action to begin shutdown without extending the allowed outage time using the Configuration Risk Management Program. However, STP Unit 2 CCW Train A was determiried to have been inoperable longer than the allowed outage time. Consequently, STP Unit 2 was in a condition prohibited by Technical Specifications.

B. PLANT OPERATING CONDITIONS PRIOR TO EVENT

STP Unit 2 was in Mode 6 at 0% power.

C. STATUS OF STRUCTURES, SYSTEMS, AND COMPONENTS THAT WERE INOPERABLE

AT THE START OF THE EVENT AND THAT CONTRIBUTED TO THE EVENT

� No other inoperable structures, systems, or components contributed to the event.

D. NARRATIVE SUMMARY OF THE EVENT

At 20:59 on October 14, 2008, during a surveillance test, STP Unit 2 CCW Train A was found to be inoperable due to failure of system valves to actuate to their designated positions. This occurred during the component 18-month surveillance test conducted during the Unit 2 2RE13 refueling outage. This test is conducted in plant operating modes 5 or 6, or when the core is offloaded. The test was conducted on CCW surge tank low-low level switch A2CC-LSL-4503C which actuates valves required to mitigate a CCW system leak. Troubleshooting determined that a. loose wire on switch terminal 6 was the reason for the event. The wire was secured in place and Train A was returned to operable status at 01:58 on October 16, 2008.

The most recent maintenance performed on the switch occurred during a calibration procedure on January 22, 2008. The internal switch contacts were not functionally checked after restoration following calibration.

Initially, the condition was identified as being not reportable based on "time of discovery" as delineated in NUREG-1022. The condition would not have prevented fulfillment of a safety function. However, subsequent review determined that a functional check was not performed following restoration after the calibration on January 22, 2008. Because Train A was inoperable longer than the Technical Specification allowed outage time, a formal determination was made November 12, 2008, that the condition is reportable under 10 CFR 50.73(a)(2)(i)(B).

discovery. The instrumentation was confirmed to be operable.

E. METHOD 'OF DISCOVERY OF EACH COMPONENT FAILURE, SYSTEM FAILURE, OR

PROCEDURAL ERROR

This condition was identified during the 18-month surveillance of the Unit 2 Train A CCW surge tank low level actuation system.

IL EVENT-DRIVEN INFORMATION

A. SAFETY SYSTEMS THAT RESPONDED

No safety systems were required to respond during this event.

B. DURATION OF SAFETY SYSTEM INOPERABILITY

The CCW surge tank low-low level switch-was most recently calibrated on January 22, 2008.

The loose wire is presumed to have occurred at that time. Train A was declared inoperable October 14, 2008, and restored to operability October 16, 2008. The train was inoperable for 237 days.

Of the three trains of CCW, Trains B and C were unaffected by this condition. Low and low-low surge tank level monitors for Train B and Train C were confirmed as being operable.

At least one of the two remaining trains was operable while Train A was inoperable.

C. SAFETY CONSEQUENCES AND IMPLICATIONS OF THE EVENT

Technical Specification Requirements:

Technical Specification 3/.3 requires at least three independent CCW loops to be operable in Modes 1, 2, 3, and 4. With only two CCW loops operable, the inoperable loop is to be restored to operable status within seven days or the Configuration Risk Management Program applied to justify an extension. Otherwise, the unit is to be in at least hot standby within the next six hours and in cold shutdown within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

In addition to Technical Specification 3.7.3, Technical Specifications also include requirements for Residual Heat Removal System (RHR) operability. Some of these technical specifications are applicable in modes 5 and 6. CCW operability is required to support RHR operability; therefore, CCW must be operable during modes 5 and 6 in addition to modes 1 through 4 as required above.

Because Unit 2 CCW Train A was inoperable longer than allowed under the Technical Specifications without entering the appropriate action statements, this event is reportable pursuant to 10 CFR 50.73(a)(2)(i)(B).

Design Description:

The CCW surge tank is partitioned into three equal volumes by internal baffles. Each compartment is connected to the inlet piping of one of the CCW pumps. The internal baffles provide separation between redundant CCW trains, so that leakage from a pipe break in one train does not affect the operability of the other trains. Makeup to the CCW surge tank is added automatically from the Demineralized Water System (DWS). As a backup by manual valve alignment, makeup water can be obtained from the Reactor Makeup Water System (RMWS) which is a safety-related and seismic Category I makeup source. An alarm is indicated in the control room if the level in the surge tank decreases due to inadequate makeup. If the level in the surge tank continues to decrease, the non-safety header is isolated, followed by automatic isolation of each CCW train from the other trains by closing the motor-operated supply and return valves located upstream and downstream of the common supply and the return headers, respectively. Simultaneously, pneumatic cross-connect valves (FV-4656 and FV-4657) in the centrifugal charging pump and positive displacement pump coolers supply and return headers (CCW train A and CCW train B from CCW train C) and motor-operated valves MOV-0768 and MOV-0772 are closed to prevent loss of more than one CCW train at a time. As soon as the CCW common header is isolated, the low pressure switch located in the common header automatically starts the standby CCW pump(s).

Makeup to the system is automatic. The main plant computer and the Qualified Display Processing System monitor the surge tank level. When the valve providing tank makeup opens, the computer alarms to give an indication of system leakage. If the normal source of makeup (the Demineralized Water System) fails or is inadequate, it is alarmed in the control room by the surge tank level instrumentation. Surge tank level indication is displayed in the control room through indicators and the QDPS.

Risk Assessment:

This event resulted in no personnel injuries, no offsite radiological releases, and no damage to other safety-related equipment. The extended outage of CCW Train A was not risk significant and did not result in a net increase in the radiological risk to the public. Train A was still functional.� ; III' CAUSE OF THE EVENT , The root cause of the event was an inadequate calibration probedure. The procedure did not require a functionality check of the internal switch contacts after switch calibration restoration.

IV. CORRECTIVE ACTIONS

The surveillance procedure will be revised to require functional checks of switch contact actuation.

  • Expected completion: 01/31/2009 Maintenance surveillance procedures will be reviewed to identify and correct as necessary those that do not have a functionality check prior to return-to-service.
  • Expected completion: 04/09/2009

V. PREVIOUS SIMILAR EVENTS

On April 13, 2008, CCW surge tank for Train A low level switch LSL-4503B failed to actuate a non­ safety isolation valve during performance of the low level actuation surveillance procedure. A valve was found to be stuck, and Train A was returned to service after it was corrected.

VI. ADDITIONAL INFORMATION

None.