05000461/FIN-2011004-01
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Failure to Perform Code Required Cause and Effect Failure Evaluations for Diesel Starting Air and Fuel Oil System Relief Valves |
Description | The inspectors identified a finding of very low safety significance with an associated non-cited violation of 10 CFR 50.55a. The licensee failed to perform American Society of Mechanical Engineers (ASME) Code required cause and effect failure evaluations for set pressure test failures of diesel generator (DG) starting air and fuel oil system relief valves. The licensee entered this issue into its corrective action program for evaluation and subsequently completed an engineering evaluation to address past operability of the associated DG starting air and fuel oil systems due to the relief valve test failures. The licensee also moved up its schedule to test the remaining relief valves. The finding was of more than minor significance because it could lead to a more significant safety concern if left uncorrected. Specifically, the failure to perform Code required cause and effect evaluations for relief valve set pressure test failures could lead to a generic problem with valves in the same or other valve groups remaining uncorrected with a potential impact on operability of safety significant mitigating systems. Because the DG starting air and fuel oil systems are relied upon to support DG operability, the inspectors concluded that this issue was associated with the Mitigating Systems Cornerstone. The finding was determined to be a licensee performance deficiency of very low safety significance because the finding: (1) was not a design or qualification deficiency; (2) did not represent an actual loss of safety function of a system; (3) did not represent an actual loss of safety function of a single train for greater than its Technical Specification (TS) allowed outage time; (4) did not represent an actual loss of safety function of one or more non-TS trains of equipment designated as risk significant; and (5) did not screen as potentially risk significant due to a seismic, flooding, or severe weather initiating event. The inspectors concluded that the finding affected the cross-cutting area of human performance in that the licensees work practices did not ensure adequate supervisory and management oversight of work activities, such that nuclear safety was supported. Specifically, the relief valve test failures were left unresolved and were not evaluated as required by the Code for an extended period of time with several failed tests. |
Site: | Clinton |
---|---|
Report | IR 05000461/2011004 Section 1R12 |
Date counted | Sep 30, 2011 (2011Q3) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.12 |
Inspectors (proximate) | B Kemker D Lords J Cassidy J Draper M Ring R Langstaff S Bell S Mischke V Myers |
CCA | H.2, Field Presence |
INPO aspect | LA.2 |
' | |
Finding - Clinton - IR 05000461/2011004 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Clinton) @ 2011Q3
Self-Identified List (Clinton)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||