05000286/FIN-2016001-03
From kanterella
Jump to navigation
Jump to search
Finding | |
|---|---|
| Title | Inadequate Screening of Reactor Protection System Test Method Change |
| Description | The inspectors identified that Entergy conducted testing on the Unit 3 RPS that was not described in the UFSAR without performing an adequate 50.59 evaluation, contrary to EN-LI-100, Process Applicability Determination. Specifically, Entergy made temporary changes to the Unit 3 reactor coolant temperature channel functional test procedures, pressurizer pressure loop functional test procedures, and nuclear power range channel axial offset calibration procedures to use jumpers to bypass RPS trip functions. As a result, the NRC opened an URI related to this concern. On October 21, 2014, Entergy implemented temporary procedure changes to three sets of reactor protection system surveillance procedures. These procedures were 3-PT-Q87A, B, and C, Channel Functional Test of Reactor Coolant Temperature Channel 411, 421, and 431; 3-PT-Q95A, B, and C, Pressurizer Pressure Loop P-455, 456, and 457 Functional Test; and 3-PT-Q109A, B, and C, Nuclear Power Range Channel N-41, 42, and 43 Axial Offset Calibrations. Entergy made the temporary procedures changes as an interim corrective action following a trip of Unit 3 on August 13, 2014, during reactor protection system surveillance testing when a spurious actuation signal occurred in the channel that was not being tested. Entergy was initially unable to identify and correct the cause of the spurious over-temperature delta temperature (OTDT) channel trip and, therefore, wanted to perform their TS required surveillances without risking another unit trip should another spurious actuation occur in the degraded channel not under test. In each case, the change was to install a jumper at the beginning of the testing to maintain the trip relay in an energized condition for the tested channel of the OTDT trip circuit thereby effectively bypassing the channel in test. Each quarterly test was performed three or four times over the course of approximately ten months. On July 1, 2015, Entergy determined that they had corrected the cause of the spurious OTDT channel trips and removed the temporary procedure changes from the controlled document system. Despite this, on August 12, 2015, Entergy performed the surveillances 3-PT-Q95A, B, and C, Pressurizer Pressure Loop P-455, 456, and 457 Functional Test, which incorporated the temporary procedure changes that had been discontinued. Operating experience has shown that human error has allowed jumpers to remain installed even after testing is over because there is no obvious indication that the channel is in bypass when a jumper is used. Indian Point is committed to IEEE Standard 279-1971, Criteria for Protective Systems for Nuclear Power Plants. Section 4.13, Indication of Bypass, requires that any channel placed in a bypass configuration for testing shall have continuous indication in the control room that the channel has been removed from service. These standards preclude the use of jumpers for routine testing. This commitment was further documented in the Safety Evaluation Report for TS Amendment 107 that approved the extension of surveillance testing intervals and approved the use of the bypass feature for testing. Although Unit 3 was not originally built with RPS bypass switches, New York Power Authority had planned to install bypass switches, which would comply with IPEEE 279-1971. Entergy terminated the WO for installation of these switches. Normally, during the course of RPS channel surveillance testing, the affected channel of the OTDT trip circuit would de-energize the trip relay. If one of the other three redundant RPS channels spuriously de-energized at the same time, the two of four signal RPS trip logic would be satisfied and Unit 3 would trip, as occurred on August 13, 2015. By putting the jumper in place, the affected channel trip relay would remain energized under all conditions, including actual conditions that would require a plant trip on OTDT. During testing, the use of the jumper did not increase the likelihood of a malfunction of an SSC over that previously evaluated in the UFSAR because Unit 3 had received a license amendment (Agencywide Documents Access and Management System (ADAMS) Accession No. ML003779650) that allowed testing a bypassed channel. However, the safety evaluation report for that license amendment stated that, The licensee further commits that only those instruments whose hardware capability does not require the lifting of leads or installing of jumpers will be routinely tested in bypass. When Unit 3 applied for the license amendment, the intent was to permanently install bypass switches that would allow bypassing a channel and would clearly indicate in the control room that a channel was bypassed. The risk of inadvertently leaving a jumper in place is greater than the risk of inadvertently leaving a channel bypassed using hardware that brings in an alarm in the control room, because the jumper can go unnoticed for a longer period of time since it does not result in clear indication in the control room. Per procedure EN-LI-100, Entergy performed a 50.59 screening review for these temporary procedure changes. In this screening, they incorrectly determined that the temporary procedure changes did not involve a test not described in the UFSAR, and as a result, did not perform a 50.59 evaluation. Although the UFSAR describes reactor protection system testing by bypassing channels, it specifically does not authorize the use of jumpers to do so. The UFSAR for Unit 3, chapter 7, states, Test procedures also allow the bistable output relays of the channel under test to be placed in the bypassed mode prior to proceeding with the analog channel test ... this may only be done for circuits whose hardware does not require the use of jumpers or lifted leads to be placed in bypass mode. Jumpering out the RPS trip relay in an RPS channel under test created an adverse condition because it removed the automatic trip signal from the RPS logic. Entergy was required to fully evaluate the adverse condition rather than authorize the change under an abbreviated 50.59 screening process. The inspectors concluded that not performing an adequate 50.59 evaluation was a performance deficiency that was reasonably within Entergys ability to foresee and correct and should have been prevented. Because Entergy was in the process of performing a retroactive 50.59 evaluation at the end of the inspection period, the inspectors were not able to evaluate if the performance deficiency was more than minor. The inspectors determined that the issues concerning the use of jumpers for RPS testing is an URI pending Entergy completion and NRC review of the 50.59 evaluation. |
| Site: | Indian Point |
|---|---|
| Report | IR 05000286/2016001 Section 1R18 |
| Date counted | Mar 31, 2016 (2016Q1) |
| Type: | URI: Green |
| cornerstone | Mitigating Systems |
| Identified by: | NRC identified |
| Inspection Procedure: | IP 71111.18 |
| Inspectors (proximate) | B Haagensen G Dentel G Newman H Gray J Furia J Patel P Ott S Richb Haagensenc Safouri E Dipaolo G Newman H Gray J D'Antonio J Deboer J Furia L Mckown M Henrion N Embert P Kaufman S Rich |
| CCA | H.14, Conservative Bias |
| INPO aspect | DM.2 |
| ' | |
Finding - Indian Point - IR 05000286/2016001 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Indian Point) @ 2016Q1
Self-Identified List (Indian Point)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||