| Title | Failure to Update the Final Safety Analysis Report with the Current Plant Design Bases |
| Description | The inspectors identified a noncited violation of 10 CFR 50.71 after Pacific Gas and Electric failed to update the Final Safety Analysis Report Update with the current design basis. The inspectors identified that the current Final Safety Analysis Report Update, Revision 18, Sections 3.1, 6.4, 6.5, and 9.4 did not capture the current design basis for the control room, component cooling water, and auxiliary feedwater systems. The failure of the licensee to provide current design basis information in the Final Safety Analysis Report Update had an adverse impact on the plant modification process, the licensees ability to assess operability for degraded plant systems, and the NRCs ability to ensure that regulatory requirements were met. The licensee entered this violation into the corrective action program as Notifications 50308588, 50306131, 5030799, and 50307476. The inspectors evaluated this violation using the traditional enforcement process because the issue affected the NRCs ability to perform its regulatory function. The inspectors concluded that the violation is more than minor because the incorrect Final Safety Analysis Report Update information had a potential impact on safety and licensed activities. The inspectors concluded the violation is Severity Level IV because the erroneous information was not used to make an unacceptable change to the facility or procedures that would have resulted in greater than very low safety significance under the Significance Determination Process. Because the violation included a performance deficiency, the inspectors also concluded the issue was a finding under the Reactor Oversight Process. The finding had a crosscutting aspect in the area of problem identification and resolution associated with the corrective action program component because the licensee did not adequately evaluate the extent of condition of previous similar violation and take appropriate corrective actions P.1(c) |
| Site: | Diablo Canyon |
|---|---|
| Report | IR 05000275/2010002 Section 1R04 |
| Date counted | Mar 31, 2010 (2010Q1) |
| Type: | TEV: Severity level IV |
| cornerstone | Mitigating Systems |
| Identified by: | NRC identified |
| Inspection Procedure: | IP 71111.04 |
| Inspectors (proximate) | G Guerra M Brown M Peck G Miller |
| CCA | P.2, Evaluation |
| INPO aspect | PI.2 |
| ' | |