Finding | |
---|---|
Title | Inadequate 50.59 Evaluation for Steam Generator Tube Rupture Analysis |
Description | The inspectors identified a Severity Level IV noncited violation of 10 CFR 50.59 after Pacific Gas and Electric failed to perform an adequate evaluation of a change to the facility as described in the Final Safety Analysis Report Update. In 1992, the licensee identified that auxiliary feedwater and steam generator power-operated relief valve flow rates assumed in the steam generator tube rupture accident analysis were non-conservative. To address the non-conforming condition, Pacific Gas and Electric changed the accident analysis to include a new time critical operator action to terminate turbine-driven auxiliary feedwater flow 5.54 minutes after the reactor trip and credit motor driven auxiliary feedwater automatic level control to the ruptured steam generator. The licensee did not perform a 10 CFR 50.59 safety evaluation of these changes. The NRC basis of approval of the accident analysis include four time critical operator actions, each assumed to occur after the first 10 minutes following the accident. The inspectors concluded that NRC approval was required before the licensee added the new time critical manual action under the 10 CFR 50.59 Rule in effect at the time because the change reduced the margin to safety to the basis of Technical Specification 3.7.4, 10% Atmospheric Dump Valves. The inspectors also concluded that prior NRC approval was required under the current 50.59 Rule because the change result in a departure from a method of evaluation described in the Final Safety Analysis Report Update. The performance deficiency, a less than adequate 50.59 evaluation, was the result of a latent issue. However, the inspectors concluded that the licensee had reasonable recent opportunities to identify the problem. The inspectors also concluded that plant programs, processes or organizations have not changed such that the problem would not reasonably occur today and that the most significant contributor to the performance deficiency was reflective of current plant performance. The licensee entered this issue into their corrective action program as Notification 50270786. The failure of Pacific Gas and Electric to perform a 10 CFR 50.59 evaluation of the changes to the steam generator tube rupture accident analysis was a performance deficiency. The inspectors evaluated this issue using traditional enforcement because the performance deficiency had the potential for impacting the NRCs ability to perform its regulatory function. The issue was more than minor because of reasonable likelihood the change to the facility would require Commission review and approval prior to implementation. The inspectors also evaluated the significance of this issue under the Significance Determination Process using Inspection Manual Chapter 0609.04, Phase 1 - Initial Screening and Characterization of Findings. The finding affected the Mitigating Systems Cornerstone because the change described the operator actions required to mitigate steam generator tube rupture accident. The inspectors concluded the finding screened Green because the finding was a design deficiency that did not result in the loss of operability or functionality. The inspectors concluded that the violation was a Severity Level IV because the issue screened Green under the Significance Determination Process. The inspectors concluded that this finding had a crosscutting aspect in the area of problem identification and resolution associated with the corrective action program component because the licensee did not thoroughly evaluate the steam generator tube rupture analysis such that the resolutions addressed causes and extent of condition P.1(c |
Site: | Diablo Canyon |
---|---|
Report | IR 05000275/2009005 Section 4OA2 |
Date counted | Dec 31, 2009 (2009Q4) |
Type: | TEV: Severity level IV |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71152 |
Inspectors (proximate) | G Guerra M Brown M Peck G George G Miller S Makor D Graves N Greene |
CCA | P.2, Evaluation |
INPO aspect | PI.2 |
' | |