Traditional Enforcement Violation
A Traditional Enforcement Violation (TEV) is a type of NRC finding used in lieu of using the normal Reactor Oversight Process; most typically for not performing a regulatory process properly (eg. Reportabilities).
Compare the violation with examples in the Enforcement Policy to determine if the violation rises to SL-IV or above and thus constitutes a non-minor traditional enforcement violation.
NoteNote: In addition, Traditional enforcement violations are not assessed for cross-cutting aspects.
impacted the regulatory process
Examples:
- Failure to provide complete and accurate information
- Failure to receive prior NRC approval for changes in licensed activities
- Failure to notify the NRC of changes in licensed activities
- Failure to perform 10 CFR 50.59 analyses
- Reporting failure, etc.
actual safety consequences
Examples:
- Actual onsite or offsite releases of radiation exceeding regulatory limits
- Onsite or offsite radiation exposures exceeding regulatory limits
- Accidental criticalities
- Core damage
- Loss of significant safety barriers
- Loss of control of radiological material exceeding regulatory limits for public dose
- Radiological emergencies
SL-IV or greater violation with no associated performance deficiency
Circumstances may arise where enforcement discretion should be considered or exercised to either escalate or mitigate enforcement sanctions or otherwise refrain from taking enforcement action for a particular violation. The Enforcement Policy and Enforcement Manual describe situations where this may apply. Specific circumstances may include:
- Specific cases for which temporary Enforcement Guidance Memoranda prescribes enforcement discretion
- Non-minor violations absent a performance deficiency
- Violations identified during extended shutdowns or work stoppages
- Violations involving old design issues
- Violations identified because of previous enforcement action
- Violations involving certain discrimination issues
For example: ISFSI facilities are not subject to the SDP and are not subject to the Reactor Oversight Process, so violations identified at ISFSIs are assessed using traditional enforcement.
Additional Inspection
A TEV falls under three categories: actual consequences, willfulness, or the potential for impacting the regulatory process.
IP 92723, 3 Level IV TEV
This procedure provides the follow up for three or more Severity Level (SL) IV violations when all occur within a single traditional enforcement area of willfulness, impeding the regulatory process or actual consequence during any 12-month period.
IP 92722, 2 Level III or a I or II TEV
This procedure provides the follow up response for the following:
- Any Severity Level I and II violation in the traditional enforcement areas of willfulness, impeding the regulatory process or actual consequence.
- Two or more Severity Level III violations in the traditional enforcement areas of willfulness, impeding the regulatory process or actual consequence in any 12 month period.
List
Significance | Site | Title | |
---|---|---|---|
05000275/FIN-2018404-03 | Severity level IV | Diablo Canyon | Licensee-Identified Violation |
05000528/FIN-2018008-03 | Severity level IV | Palo Verde | Licensee-Identified Violation |
05000390/FIN-2018003-06 | Severity level IV | Watts Bar | Licensee-Identified Violation |
05000313/FIN-2018003-03 | Severity level IV | Arkansas Nuclear | Failure to Provide Complete and Accurate Information in a License Amendment Request to Change Emergency Action Level Requirements |
05000287/FIN-2018003-03 | Severity level IV | Oconee | Main Steam Relief Valve As-Found Lift Pressure Prohibited by Technical Specifications |
05000482/FIN-2018003-02 | Severity level IV | Wolf Creek | Failure to Submit a Licensee Event Report for a Condition Prohibited by Technical Specifications |
05000269/FIN-2018003-02 | Severity level IV | Oconee | Failure to Make a 60 Day Notification of an Actuation of an Emergency AC Power Source |
05000237/FIN-2018003-02 | Severity level IV | Dresden | Licensee-Identified Violation |
05000298/FIN-2018003-01 | Severity level IV | Cooper | Failure to Provide Complete and Accurate Information in a License Amendment Request |
05000369/FIN-2018003-01 | Severity level IV | Mcguire McGuire | Failure to Adequately Document the Basis for a Change to the Emergency Plan |
05000269/FIN-2018003-01 | Severity level IV | Oconee | Failure to Maintain the Effectiveness of the Emergency Plan |
05000348/FIN-2018003-01 | Severity level IV | Farley | Unit 1 Pressurizer Safety Valve Lift Pressure Outside of Technical Specification Tolerance Band |
05000296/FIN-2018003-01 | Severity level IV | Browns Ferry | Main Steam Relief Valves Lift Settings Outside of Technical Specifications Required Setpoints |
05000443/FIN-2018003-01 | Severity level IV | Seabrook | Pressurizer Safety Valve Outside of Technical Specification Limits |
05000446/FIN-2018011-01 | Severity level III | Comanche Peak | Failure to Maintain a Quality Record Complete and Accurate in All Material Respects |
05000266/FIN-2018003-01 | Severity level IV | Point Beach | Failure to Perform Evaluations to Ensure that the Fabrication of Dry Cask Storage Systems Meets the Requirements of the Loading Certificate of Compliance |
05000254/FIN-2018003-02 | Severity level IV | Quad Cities | Failure to Follow Procedures for Forced Helium Dehydration of a Multipurpose Canister |
05000333/FIN-2018411-02 | Severity level IV | FitzPatrick | Security |
05000348/FIN-2018014-02 | Severity level IV | Farley | Failure to Provide Complete and Accurate Information Related to System Operator Rounds |
05000348/FIN-2018014-01 | Severity level IV | Farley | Failure to Complete System Operator Rounds as Required per Procedures |
05000296/FIN-2018002-02 | Severity level IV | Browns Ferry | Inoperable Residual Heat Removal (RHR) Pump Results in Condition Prohibited by Technical Specifications |
05000269/FIN-2018002-02 | Severity level IV | Oconee | Failure to Coordinate a No-later-than Arrival Time for the Shipment of a Category 2 Quantity of Radioactive Material |
05000390/FIN-2018002-02 | Severity level IV | Watts Bar | Licensee-Identified Violation |
05000286/FIN-2018002-01 | Severity level IV | Indian Point | Reactor Pressure Boundary Leakage Due to Weld Failure in Reactor Vessel Head Penetration #3 |
05000369/FIN-2018002-01 | Severity level IV | McGuire | Licensee-Identified Violation |
05000400/FIN-2018002-03 | Severity level IV | Harris | Failure to Adequately Document Changes to the Emergency Plan |
05000293/FIN-2018002-03 | Severity level IV | Pilgrim | 480V Bus B6 Auto Transfer Function Degraded Due to Time Delay Relay Failure |
05000482/FIN-2018002-01 | Severity level IV | Wolf Creek | Announcement of an NRC Inspectors Presence by Station Personnel |
05000458/FIN-2018002-01 | Severity level IV | River Bend | Failure to Correct Inadequate Technical Specification Pressure Temperature Curves |
05000458/FIN-2018012-04 | Severity level IV | River Bend | Failure to Submit a Licensee Event Report for a Manual Scram |
05000458/FIN-2018012-07 | Severity level IV | River Bend | Failure to Perform 10 CFR 50.59 Evaluation for Main Feedwater System Sparger Nozzle Damage |
05000397/FIN-2018401-01 | Severity level IV | Columbia | Security |
05000254/FIN-2018001-01 | Severity level IV | Quad Cities | Repeat Use of Written Exams During Licensed Operator Requalification Examinations |
05000440/FIN-2018001-01 | Severity level IV | Perry | Failure to Notify the NRC within 60 Days of a Condition Prohibited by Technical Specifications |
05000219/FIN-2018001-01 | Severity level IV | Oyster Creek | Untimely Licensee Event Report for Reportable Conditions Associated with the No. 2 Emergency Diesel Generator |
05000382/FIN-2018001-01 | Severity level IV | Waterford | Failure to Obtain NRC Staff Authorization Prior to Changing a Procedure that Impacts Implementation of Technical Specifications |
05000498/FIN-2018001-04 | Severity level IV | South Texas | Licensee-Identified Violation |
05000397/FIN-2018401-02 | Severity level IV | Columbia | Security |
05000498/FIN-2018001-03 | Severity level IV | South Texas | Licensee-Identified Violation |
05000461/FIN-2017004-04 | Severity level IV | Clinton | Failure to Perform an Evaluation in Accordance with 10 CFR 72.48 for Changes Made to the Time-to-Boil Calculation |
05000331/FIN-2017004-02 | Severity level IV | Duane Arnold | Failure to Evaluate Site Fire and Explosion Hazards in Accordance with 10 CFR 72.212(b) (6) |
05000348/FIN-2017009-01 | Severity level IV | Farley | Failure to Report a Condition Which was Prohibited by Technical Specifications |
05000416/FIN-2017007-04 | Severity level IV | Grand Gulf | Failure to Update the Final Safety Analys is Report |
05000382/FIN-2017008-03 | Severity level IV | Waterford | Two Examples of Failure to Submit and Receive Prior Authorization of Alternatives to ASME OM Code Leak Testing Requirements |
05000341/FIN-2017003-01 | Severity level IV | Fermi | Failure to Satisfy 10 CFR 50.73 Reporting Requirements for Primary Containment Isolation Valve Actuations |
05000382/FIN-2017010-01 | Severity level IV | Waterford | Failure to Evaluate Departures from Approved Methodologies for Reactor Vessel Fluence |
05000498/FIN-2017010-02 | Severity level IV | South Texas | Failure to Perform Required 50.54(q) Evaluations prior to Implementing Changes to the Emergency Plan |
05000272/FIN-2017003-01 | Severity level IV | Salem | Expiration of Periodic Inservice Testing of 14 Service Water Pump |
05000346/FIN-2017003-04 | Severity level IV | Davis Besse | Failure to Perform 10 CFR 50.59 Evaluation |
05000397/FIN-2017003-02 | Severity level IV | Columbia | Failure to Report Unplanned Valid Reactor Protection System Actuation |
... further results |