05000269/FIN-2011004-01
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Failure to Promptly Identify and Correct an Adverse Condition Affecting Operability of Letdown Line Containment Isolation Valves |
Description | An NRC-identified non-cited violation of 10 CFR 50, Appendix B, Criterion XVI, Corrective Action, was identified for the licensees failure to promptly identify and correct a condition adverse to quality. The licensee failed to identify and correct a degraded condition associated with containment isolation valves 1HP-5, 2HP-5 and 3HP-5 following the identification of a degraded condition on valve 1HP-5. The licensee restored closing margin to the Unit 1 valve during its refueling outage which began April 2, 2011, by installing a permanent modification on the valve actuator. An interim modification was installed on June 11, 2011, for Unit 2, and on June 10, 2011, for Unit 3 to restore closing margin to those valves. The licensees failure to promptly identify the degraded condition of 2HP-5 and 3HP-5 and adequately correct the condition on 1HP-5 as required by 10 CFR 50, Appendix B, Criterion XVI, was a performance deficiency (PD). The PD was more than minor because it was associated with the Barrier Integrity cornerstone attribute of Design Control and adversely impacted the cornerstone objective because the degraded condition had the potential to result in a containment bypass pathway. The inspectors determined a Phase 3 analysis was required because the finding represented a potential containment bypass pathway that would not be isolable following certain events analyzed in Chapter 15 of the Updated Final Safety Analysis Report. A Phase 3 analysis was performed by a regional Senior Reactor Analyst (SRA) who determined that the finding was of very low safety significance (Green) because the line break Large Early Release Frequency (LERF), and the Station Blackout (SBO)/Standby Shutdown Facility (SSF) core damage frequency (CDF) results were less than 1X10-6. The finding directly involved the cross-cutting area of Human Performance under the Conservative Assumptions and Safe Actions aspect of the Decision Making component, in that the licensee failed to demonstrate conservative decision making in their evaluation of the operability of the Units 1, 2, and 3 letdown line containment isolation valves. |
Site: | Oconee |
---|---|
Report | IR 05000269/2011004 Section 1R15 |
Date counted | Sep 30, 2011 (2011Q3) |
Type: | NCV: Green |
cornerstone | Barrier Integrity |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.15 |
Inspectors (proximate) | A Sabisch G Ottenberg J Bartley J Hamman K Ellis R Russell |
CCA | H.14, Conservative Bias |
INPO aspect | DM.2 |
' | |
Finding - Oconee - IR 05000269/2011004 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Oconee) @ 2011Q3
Self-Identified List (Oconee)
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||