Finding | |
|---|---|
| Title | Failure to Control Temporary Equipment Resulted in a Fire |
| Description | A self-revealing non-cited violation of 10 CFR 50 Appendix B, Criterion V, Instructions, Procedures and Drawings was identified for the licensees failure to install and maintain adequate control of temporary lighting in the intake cable tunnel as required by the Tennessee Valley Authority (TVA) Safety Manual and NPG-SPP- 09.17, Temporary Equipment Control. Consequently, a temporary light string was left improperly installed, without ground fault circuit interrupt (GFCI) device(s), for over two years until it faulted electrically and caused a fire in the intake cable tunnel on October 12, 2011. The fire brigade extinguished the fire in approximately 10 minutes and removed the temporary light string from the cable tunnel. The licensee entered this event into their corrective action program as PER 445331. The finding was determined to be more than minor because it was considered sufficiently similar to example 4.f of Inspection Manual Chapter (IMC) 0612, Appendix E, for an issue of concern that resulted in a fire hazard in a safety-related area of the plant. The finding was associated with the Initiating Events Cornerstone and characterized according to IMC 0609, Significance Determination Process (SDP), Attachment 04, Phase 1 - Initial Screening and Characterization of Findings. The results of this analysis required an evaluation in accordance with IMC 0609, Appendix F, Attachment 01, Part 1, Fire Protection SDP Phase 1 Worksheet. For the SDP Phase 1 evaluation a high degradation rating was assigned for this fire event with a duration factor greater than 30 days. When compared against the SDP Phase 1 screening criteria, this resulted in a SDP Phase 2 evaluation. The inspectors concluded that this finding screened to Green in the Appendix F Phase 2 analysis using Appendix F Attachment 01, Part 2, Fire Protection SDP Phase 2 Worksheet. Specifically, it was determined that the fire could not reach the temperature threshold for fire-induced cable failure and would not spread to other combustible materials in the area. The cause of this finding was directly related to the cross cutting aspect of Long-Standing Equipment Issues in the Resources component of the Human Performance area, because the deficiencies with the permanently installed lighting system in the intake cable necessitated the use of the temporary light stringer for more than two years H.2(a) |
| Site: | Browns Ferry |
|---|---|
| Report | IR 05000259/2011005 Section 4OA3 |
| Date counted | Dec 31, 2011 (2011Q4) |
| Type: | NCV: Green |
| cornerstone | Initiating Events |
| Identified by: | Self-revealing |
| Inspection Procedure: | IP 71153 |
| Inspectors (proximate) | C Kontz C Stancil E Guthrie L Pressley P Niebaum R Baldwin T Ross |
| CCA | H.6, Design Margins |
| INPO aspect | WP.2 |
| ' | |