05000259/FIN-2011004-01
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Failure to Control Transient Combustible Materials in the Unit 1 Reactor Building |
Description | A NRC-identified non-cited violation of the Technical Specifications 5.4.1.d, Fire Protection Program Implementation, was identified for the licensees failure to control transient combustible materials in a designated exclusion area between Fire Zones 1-1 and 1-2 in the Unit 1 reactor building. Specifically, on August 12, 2011, the inspectors identified transient combustible materials left unattended in the designated exclusion area between Loops I and II of the low pressure coolant injection (LPCI) system following LPCI injection valve maintenance activities. Upon notification by the inspectors, the licensee promptly removed the materials. This issue was entered into the licensees corrective action program as problem evaluation report (PER) 418101. The finding was determined to be greater than minor because it was similar to example 4.k. of Inspection Manual Chapter (IMC) 0612, Appendix E, for an issue of concern involving transient combustibles in a designated combustible free area required for separation of redundant safe shutdown trains. The safety significance of the finding was characterized using IMC 0609, Significance Determination Process (SDP), Appendix F, Attachment 1, Fire Protection SDP Phase 1 Worksheet, and determined to be of very low safety significance because of a low degradation rating since a roving fire watch was already established in this same area for an another fire impairment while the transient combustibles were left unattended. The cause of this finding was directly related to the cross cutting aspect of effectively communicating expectations regarding procedural compliance in the Work Practices component of the Human Performance area, because the expectations for the removal of combustible materials from this area were not effectively communicated to the night shift personnel |
Site: | Browns Ferry |
---|---|
Report | IR 05000259/2011004 Section 1R05 |
Date counted | Sep 30, 2011 (2011Q3) |
Type: | NCV: Green |
cornerstone | Initiating Events |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.05 |
Inspectors (proximate) | C Stancil E Guthrie L Pressley P Niebaum T Ross |
CCA | H.8, Procedure Adherence |
INPO aspect | WP.4 |
' | |