PNP 2019-008, Report of Changes, Tests and Experiments and Summary of Commitment Changes

From kanterella
Jump to navigation Jump to search
Report of Changes, Tests and Experiments and Summary of Commitment Changes
ML19099A008
Person / Time
Site: Big Rock Point  File:Consumers Energy icon.png
Issue date: 04/08/2019
From: Hardy J
Entergy Nuclear Operations
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
PNP 2019-008
Download: ML19099A008 (1)


Text

  • ~ Entergy Entergy Nuclear Operations, Inc.

Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043 Tel 269 764 2000 Jeffery A. Hardy Regulatory Assurance Manager PNP 2019-008 April 8, 2019 10 CFR 50.74 ATTN: Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555-0001

Subject:

Report of Changes, Tests and Experiments and Summary of Commitment Changes Big Rock Point Dockets 50-155 and 72-043 License No. DPR-6

Dear Sir or Madam:

Entergy Nuclear Operations, Inc. is providing notification that there were no facility changes, tests or experiments performed at Big Rock Point for the period from April 1, 2017, through March 31, 2019. This notification is being submitted in accordance with the requirements of 10 CFR 72.48 and 10 CFR 50.59. In addition, there were no commitment changes made during the period.

This letter contains no new commitments and no revision to existing commitments.

Respectfully, JAH/bed CC Administrator, Region III, USNRC Project Manager, Palisades, USNRC Resident Inspector, Palisades, USNRC