--- Entergy.
PNP 2017-041 June 20, 2017 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Entergy Nuclear Operations, Inc.
Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530 Tel 269 7642000 Charles F. Arnone Site Vice President
SUBJECT:
Biennial Update - Big Rock Point License Termination Plan Big Rock Point Dockets 50-155 and 72-043 Facility Operating License No. DPR-6
References:
- 1. Entergy Nuclear Operations, Inc. letter, PNP 2013-030, "Big Rock Point, 'Big Rock Point License Termination Plan,'" Revision 3, dated July 17, 2013 (ADAMS Accession No. ML13204A012)
Dear Sir or Madam:
In accordance with 10 CFR 50.71 (e), "Maintenance of records, making of reports," Entergy Nuclear Operations, Inc. (ENO) hereby submits the results of its biennial review, of the Big Rock Point (BRP) License Termination Plan (LTP).
The review concluded that there were no changes to the BRP L TP during the preceding two years and that Revision 3 of the L TP as submitted in Reference 1 is the latest revision of the LTP.
This letter contains no new commitments and no revisions to existing commitments.
I declare under penalty of perjury that the foregoing is true and correct. Executed on June 20, 2017.
Sincerely, CFA/jse CC Administrator, Region III, USNRC BRP Decommissioning Inspector, USNRC NMSS Project Manager, USNRC Michigan Department of Environmental Quality