Entergy Entergy Nuclear Operations, Inc.
Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043 269-764-2000 Otto W. Gustafson Licensing Manager SAFEGUARDS INFORMATION PNP 2012-053 June 5, 2012 10 CFR 50.54(p)
U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
SUBJECT:
Big Rock Point ISFSI Security Plan Revision 6 (U)
Big Rock Point Dockets 50-155 and 72-043 License No. DPR-6
Dear Sir or Madam:
Enclosed is Revision 6 of the Big Rock Point (BRP) Independent Spent Fuel Storage Installation (ISFSI) Security Plan. Attachment 1 contains a description of, and justification for, the changes included in Revision 6. Attachment 2 contains the revised Plan.
Entergy Nuclear Operations, Inc. (ENO) has determined that the changes contained in Revision 6 do not decrease the safeguards effectiveness of the BRP Security Plan.
Accordingly, this revision is submitted under the provisions of 10 CFR 50.5 4 (p)(2).
Information contained in the attachments to this document has been classified as Safeguards Information. Therefore, ENO requests that this information be withheld from public disclosure in accordance with 10 CFR 73.22.
NOTE: THE ENCLOSURES TO THIS LETTER CONTAIN SAFEGUARDS INFORMATION AND MUST BE PROTECTED ACCORDINGLY. UPON REMOVAL OF THE ENCLOSURES, THIS LETTER IS DECONTROLLED.
SAFEGUARDS INFORMATION
SAFEGUARDS INFORMATION Document Control Desk Page 2 This letter contains no new commitments and no revisions to existing commitments.
Sincerely, OWG/bed : Big Rock Point ISFSI Security Plan Change Matrix : Big Rock Point ISFSI Security Plan, Revision 6 CC Administrator, Region III, USNRC BRP ISFSI Project Manager, USNRC w/o enclosures NOTE: THE ENCLOSURES TO THIS LETTER CONTAIN SAFEGUARDS INFORMATION AND MUST BE PROTECTED ACCORDINGLY. UPON REMOVAL OF THE ENCLOSURES, THIS LETTER IS DECONTROLLED.