MONTHYEARML18352A7552018-12-14014 December 2018 Request for Rescission of Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) Project stage: Request ML19094A6802019-06-21021 June 2019 Withdrawal of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Withdrawal 2018-12-14
[Table View] |
|
---|
Category:Letter
MONTHYEARML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24129A1042024-05-26026 May 2024 Preapplication Readiness Assessment Plan for the Holtec Decommissioning International License Termination Plan ML24136A2382024-05-14014 May 2024 Annual Radiological Environmental Operating Report for 2023 ML24135A3212024-05-14014 May 2024 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2023 IR 05000293/20240012024-05-0707 May 2024 NRC Inspection Report No. 05000293/2024001 L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 L-24-010, Request for Preapplication Readiness Assessment of the Draft License Termination Plan2024-04-22022 April 2024 Request for Preapplication Readiness Assessment of the Draft License Termination Plan L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) IR 05000293/20230032024-02-29029 February 2024 NRC Inspection Report Nos. 05000293/2023003 and 05000293/2023004 L-24-002, Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G2024-02-0202 February 2024 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G ML23342A1182024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 ML23334A1822023-11-30030 November 2023 Biennial Report for the Defueled Safety Analysis Report Update, Technical Specification Bases Changes, 10 CFR 50.59 Evaluation Summary, and Regulatory Commitment Change Summary November 2021 Through October 2023 L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23306A0992023-11-0202 November 2023 and Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) L-23-011, 10 CFR 72.48 Biennial Change Summary Report2023-10-27027 October 2023 10 CFR 72.48 Biennial Change Summary Report IR 05000293/20234012023-08-31031 August 2023 NRC Inspection Report No. 05000293/2023401 & 2023001 (Cover Letter Only) IR 05000293/20230022023-08-0404 August 2023 NRC Inspection Report No. 05000293/2023002 L-23-008, Correction to Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations Holtec Decommissioning International, LLC (HDI)2023-05-23023 May 2023 Correction to Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations Holtec Decommissioning International, LLC (HDI) ML23135A2152023-05-15015 May 2023 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2022 ML23136A7792023-05-15015 May 2023 Annual Radiological Environmental Operating Report, January 1 Through December 31, 2022 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML23069A2782023-03-13013 March 2023 Request for Scoping Comments Concerning the Environmental Review of Monticello Nuclear Generating Plant, Unit 1 Subsequent License Renewal Application ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000293/20220042023-02-15015 February 2023 NRC Inspection Report No. 05000293/2022004 ML22356A0712023-01-31031 January 2023 Issuance of Exemption for Pilgrim Nuclear Power Station ISFSI Regarding Annual Radioactive Effluent Release Report - Cover Letter ML22347A2782022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 L-22-041, Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension2022-12-0909 December 2022 Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension IR 05000293/20220032022-11-18018 November 2022 NRC Inspection Report No. 05000293/2022003 L-22-036, Decommissioning Trust Fund Agreement2022-11-0808 November 2022 Decommissioning Trust Fund Agreement ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22266A1922022-09-23023 September 2022 and Pilgrim Nuclear Power Station - Request to Withdraw Prior Submissions from NRC Consideration ML22269A4202022-09-22022 September 2022 Citizen Lawsuit ML22272A0352022-09-22022 September 2022 S. Lynch-Benttinen Letter Regarding U.S. Citizen Intent to Sue U.S. Fish and Wildlife and NOAA Fisheries Representing the Endangered Species (Na Right Whale) Which Will Be Adversely Affected by Holtec International Potential Actions ML22241A1122022-08-29029 August 2022 Request for Exemption from 10 CFR 72.212(a)(2), (b)(2), (b)(3), (b)(4), (B)(5)(i), (b)(11), and 72.214 for Pilgrim ISFSI Annual Radioactive Effluent Release Report IR 05000293/20220022022-08-12012 August 2022 NRC Inspection Report No. 05000293/2022002 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22221A2592022-08-0101 August 2022 LTR-22-0217-1-NMSS - Town of Duxbury Letter Opposing the Irradiated Water Release from Pilgrim (Docket No. 05000293) ML22206A1512022-08-0101 August 2022 NRC Office of Investigations Case Nos. 1-2022-002 & 1-2022-006 ML22175A1732022-07-28028 July 2022 LTR-22-0153-1 - Response Letter to D. Turco, Cape Downwinders, from A. Roberts, NRC, Regarding Holtec-Pilgrim Plans to Dump One Million Gallons of Radioactive Waste Into Cape Cod Bay ML22193A1662022-07-28028 July 2022 LTR-22-0154-1 - Heather Govern, VP, Clean Air and Water Program, Et Al., Letter Regarding Radioactive Wastewater Disposal from the Pilgrim Nuclear Power Station (Docket No. 05000293) ML22154A4882022-06-0101 June 2022 Letter from Conservation Law Foundation Regarding Irradiated Water Release from Pilgrim ML22154A1622022-05-26026 May 2022 Letter and Email from Save Our Bay/Diane Turco Regarding Irradiated Water Release from Pilgrim ML22136A2602022-05-16016 May 2022 Submittal of Annual Radiological Environmental Operating Report for January 1 Through December 31, 2021 ML22136A2572022-05-16016 May 2022 Submittal of Annual Radioactive Effluent Release Report for January 1 Through December 31, 2021 ML22102A0932022-05-12012 May 2022 LTR-22-0067 Response to Matthew P. Levesque, President, Barnstable Town Council Regarding Irradiated Water Release from Pilgrim IR 05000293/20220012022-05-11011 May 2022 NRC Inspection Report No. 05000293/2022001 2024-06-03
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, O.C. 20555-0001 June 21, 2019 Mr. Brian R. Sullivan Site Vice President Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508
SUBJECT:
PILGRIM NUCLEAR POWER STATION -WITHDRAWAL OF ORDER EA-12-051, "ORDER MODIFYING LICENSES WITH REGARD TO RELIABLE SPENT FUEL POOL INSTRUMENTATION" (EPID NO. L-2018-JLD-0171)
Dear Mr. Sullivan:
This letter documents the withdrawal of Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,~ at Pilgrim Nuclear Power Station (Pilgrim),
as described below.
By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12054A679), the U.S. Nuclear Regulatory Commission (NRC, the Commission) issued Order EA-12-051 to Entergy Nuclear Operations, Inc. (Entergy, the licensee). This order requires certain actions at Pilgrim associated with the Fukushima Near-Term Task Force recommendations. Specifically, Order EA-12-051 requires that reliable spent fuel pool (SFP) instrumentation be installed and maintained in the event of a beyond-design-basis external event.
Section IV of Order EA-12-051 (the Order) required that Entergy submit to the Commission for review an overall integrated plan by February 28, 2013, describing how Pilgrim will achieve compliance with the requirements of the Order. The licensee responded to the Order by letter dated February 28, 2013 (ADAMS Accession No. ML13063A097). By letter dated July 17, 2015 (ADAMS Accession No. ML15209A606), the licensee notified the NRC that full compliance with the Order had been achieved at Pilgrim. The NRC staff issued a safety evaluation describing its review of the Pilgrim order compliance plan on March 3, 2016 (ADAMS Accession No. ML160088077), and documented a compliance inspection at the Pilgrim site by letter dated July 7, 2016 (ADAMS Accession No. ML16189A066).
Section IV of the Order also stipulates that the NRC's Director of the Office of Nuclear Reactor Regulation may, in writing, relax or rescind any of the conditions of the Order upon demonstration by the licensee of good cause.
By letter dated November 10, 2015 (ADAMS Accession No. ML15328A053), Entergy submitted to the NRC a certification of pem,anent cessation of operations for Pilgrim in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Section 50.82(a)(1 )(i). In this letter, Entergy provided notification to the NRC of its intent to permanently cease operations at Pilgrim
B. Sullivan no later than June 1, 2019. By letter dated June 10, 2019 (ADAMS Accession No. ML19161A033), Entergy certified to the NRC that it had permanently ceased operations at Pilgrim on May 31, 2019. In this letter, the licensee also provided notification to the NRC under 10 CFR 50.82(a)(1 )(ii) that, as of June 9, 2019, all fuel has been permanently removed from the Pilgrim reactor vessel and placed in the SFP. Further, Entergy confirmed its understanding that, under 10 CFR 50.82(a)(2), the Pilgrim 10 CFR Part 50 license no longer authorizes operation of the reactor or emplacement or retention of fuel into the reactor vessel.
By letter dated December 14, 2018 (ADAMS Accession No. ML18352A755), Entergy requested rescission of Order EA-12-051, to be effective upon the docketing of the 10 CFR 50.82(a)(1 )(i) and (ii) certifications for permanent cessation of operations and permanent removal of fuel from the reactor vessel.
The licensee's letter dated December 14, 2018, asserts that good cause exists to rescind the requirements of Order EA-12-051. The licensee's letter observes that Section Ill of the Order states that the Commission determined that all power reactor licensees and construction permit holders must have a reliable means of remotely monitoring wide-range SFP levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. According to the licensee, this statement forms the basis of the Order and reflects the need to effectively deploy limited resources to mitigate very low frequency events with the potential to challenge both the reactor and the SFP. The licensee further states that after Pilgrim is permanently shut down and defueled, plant staff would not have to prioritize event mitigation and recovery actions: the focus of the plant staff would be the SFP condition.
Because the licensee for Pilgrim has docketed the 10 CFR 50.82(a)(1 )(i) and (ii) certifications for permanent cessation of operations and permanent removal of fuel from the reactor vessel, and has acknowledged, consistent with 10 CFR 50.82(a)(2), that the Pilgrim 10 CFR Part 50 license no longer authorizes operation of the reactor or emplacement or retention of fuel into the reactor vessel, the NRC staff finds that the safety of the fuel in the SFP becomes the primary safety function for site personnel. In the event of a challenge to the safety of fuel stored in the SFP, the focus of the facility staff would be the SFP condition, without the possibility of a concurrent challenge to the reactor and primary containment safety functions. Thus, in the event of a beyond-design-basis external event, effective prioritization of event mitigation and recovery actions would be simplified, and the application of the Order requirements would no longer be necessary to serve the Order's underlying purpose.
B. Sullivan Based on the above, the NRG staff concludes that the licensee has demonstrated good cause for the withdrawal of Order EA-12-051. Accordingly, the NRG is withdrawing its March 12, 2012, Order EA-12-051 with respect to Pilgrim.
Sincerely, Ho K. Nieh, Director Office of Nuclear Reactor Regulation Docket No. 50-293 cc: Listserv
"
- ML19094A680 *via email OFFICE NRR/DLP/PBMB/PM NRR/DLP/PBMB/LA NRR/DLP/PBEB/BC(A)
NAME PBamford Slent BTitus DATE 3/29/2019 4/5/2019 4/26/2019 OFFICE NRR/DLP/PBMB/BC OE/D NRR/DLP/D NAME JBowen GWilson Llund DATE 4/29/2019 6/10/2019 6/14/2019 OFFICE OGC-NLO* NRR/D NAME RCarpenter HNieh (MEvans for) 6/14/2019 6/21/19