Duane Arnold - Six Month Status Report in Response to 03/12/2012 Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation
ML16246A006
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 08/31/2016
From: Vehec T A
NextEra Energy Duane Arnold
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-12-051, NG-16-0168
Download: ML16246A006 (5)


Text

August 31, 2016 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Duane Arnold Energy Center Docket No. 50-331 Renewed Op. License No. DPR-49 NG-16-0168 10 CFR 2.202 NextEra Energy Duane Arnold Energy Center, LLC's Six Month Status Report in Response to March 12, 2012 Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)

References:

1) Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation" dated March 12. 2012 (ML 12054A682)
2) Letter, R. Anderson (NextEra Energy Duane Arnold, LLC) to U.S.* NRG, "NextEra Energy Duane Arnold, LLC's Overall Integrated Plan in Response to March 12, 2012 Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)," NG-13-0086 dated February 28, 2013 (ML 13063A014)

On March 12, 2012, the Nuclear Regulatory Commission (NRG) issued Reference 1, an immediately effective Order to all licensees including NextEra Energy Duane Arnold, LLC (hereafter NextEra Energy Duane Arnold). In Reference 2, NextEra Ener9-Y Duane Arnold submitted an Overall Integrated Plan *for the implementation of this Order. The Order required licensees to provide periodic status reports for the Overall Integrated Plan. The purpose of this letter is to provide the next six-month status report pursuant*

to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementing the requirements of Reference

1. The enclosure to this letter fooD I .

NextEra Energy Duane Arnold, LLC, 3277 DAEC Road, Palo, IA 52324 Document Control Desk NG-16-0168 Page 2 of 2 provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any. _If you have any questions or require additional information, contact Mike Matchinis at319-851-7756.

I declare under penalty of perjury that the foregoing is true and correct. (/;:_us! 31, 2016 T. A. Vehec Vice President, Duane Arnold Energy Center NextEra Energy Duane Arnold, LLC Enclosure cc: Regional Administrator, USNRC, Region Ill Resident Inspector, USNRC, Duane Arnold Energy Center Project Manager, USNRC, Duane Arnold Energy Center Enclosure to NG-16-0168 NextEra Energy Duane Arnold, LLC's Six Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation 2 pages follow NEXTERA ENERGY DUANE ARNOLD, LLC DUANE ARNOLD ENERGY CENTER Six Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool lnstrun::ientation

1. Introduction NextEra Energy Duane Arnold, LLC (hereafter, NextEra Energy Duane Arnold) developed an Overall Integrated Plan (Reference 1), documenting the planned modification with regard to Reliable Spent Fuel Pool Instrumentation (SFPI) in response to Reference
2. This enclosure provides an update of milestone accomplishments since submittal of the Overall Integrated Plan and the last status update, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any. 2. Milestone Accomplishments The following milestone has.been completed since the submittal of the last status update (Reference 7), and is current as of August 19, 2016.
  • Complete Installation of SFP Instruments
3. Milestone Schedule Status The dates are planning dates subject to change as design and implementation details are developed.

Target Revised Activity Target Milestone Completion Status Completion Date Date Commence Engineering and Design -In Progress Completed N/A Comple_te Design 4Q 2015 Completed N/A Complete Procurement of SFP 2Q 2016 Completed N/A Instruments Complete Installation of SFP 4Q 2016 Completed N/A Instruments Instruments Operational and Training 4Q 2016 Started N/A Complete 4. Changes to Compliance Method There are no changes to the compliance method as documented in the Overall Integrated Plan and past status updates. Page 1 of 2

5. Need for Relief/Relaxation and Basis for the Relief/Relaxation Duane Arnold is not requesting relief from the requirements of Order EA-12-051 (Reference
2) at this time.
  • 6. Requests for Additional Information The NRC staff determined that additional information was required to enable the continued technical review of the NextEra Energy Duane Arnold's Overall Integrated Plan (OIP). Requests for Information (RAls) were provided in Reference 4 as corrected by Reference
5. Per a letter to all licensees, (Reference 6), the NRG notified licensees to not formally submit responses to RAls on the docket, but instead provide their responses and supporting information on their ePortals.

The DAEC RAI responses and supporting information were uploaded to the CERTREC ePortal in December of 2015. 7. References

-1) Letter, R. Anderson (NextEra Energy Duane Arnold, LLC) to U.S. NRC, "NextEra Energy Duane Arnold, LLC's Overall lntE;?grated Pla_n in Response to March 12, 2012 Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)," NG-13-0086 dated February 28, 2013(ML13063A014)

2) Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation" dated March 12, 2012 (ML 12054A682)
3) Letter, T.A. Vehec (NextEra Energy Duane Arnold, LLC) to U.S. NRG, "NextEra Energy Duane Arnold Energy Center, LLC's Six-Month Status Report in
4) NRG Letter, "Duane Arnold Energy Center-Interim Staff Evaluation and Request For Additional Information Regarding the Overall Integrated Plan for . Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation," dated November 26, 2013 (ML 133238443)
5) NRG Letter, "Correction Letter-Duane Arnold Energy Center Regarding Interim Staff Evaluation and Request for Additional Information for Reliable Spent Fuel Pool Instrumentation (Order EA-12-051);" dated January 17, 2014(ML14007A215)
6) NRG Letter dated March 26, 2014, Nuclear Regulatory Commission Audits of Licensee Responses to Reliable Spent Fuel Pool Instrumentation Order EA-12-051 (ML 14083A620)
7) Letter, T.A. Vehec (NextEra Energy Duane Arnold, LLC) to U.S. NRG, "NextEra Energy Duane Arnold Energy Center, LLC's Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)," NG-16-* 0047 dated February 29, 2016(ML16064A022)

Page 2 of 2