NG-07-0301, Decommissioning Funding Status Report
ML071000221 | |
Person / Time | |
---|---|
Site: | Duane Arnold |
Issue date: | 03/29/2007 |
From: | Vanmiddlesworth G Duane Arnold |
To: | Document Control Desk, NRC/NRR/ADRO |
References | |
NG-07-0301 | |
Download: ML071000221 (3) | |
Similar Documents at Duane Arnold | |
---|---|
Category:Decommissioning Funding Plan DKTs 30
MONTHYEARNG-24-0001, 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update2024-03-0606 March 2024
[Table view]2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update NG-23-0001, 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report2023-03-27027 March 2023 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-22-0041, And Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report2022-03-31031 March 2022 And Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-21-0006, 2021 Annual Decommissioning and Spent Fuel Management Funding Status Report2021-03-31031 March 2021 2021 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-20-0023, Decommissioning Funding Status Report2020-03-26026 March 2020 Decommissioning Funding Status Report NG-20-0007, Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50. 75(h)(1 )(Iv)2020-02-25025 February 2020 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50. 75(h)(1 )(Iv) L-2019-045, NextEra Energy Duane Arnold, Ilc - Independent Spent Fuel Storage Installation (ISFSI) - Decommissioning Funding Status Reports, Financial Assurance Update2019-03-25025 March 2019 NextEra Energy Duane Arnold, Ilc - Independent Spent Fuel Storage Installation (ISFSI) - Decommissioning Funding Status Reports, Financial Assurance Update L-2015-064, Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2015-03-27027 March 2015 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update L-2013-103, Decommissioning Funding Status Reports2013-03-25025 March 2013 Decommissioning Funding Status Reports L-2012-442, Units 1 & 2 - ISFSI Decommissioning Funding Plans2012-12-17017 December 2012 Units 1 & 2 - ISFSI Decommissioning Funding Plans L-2011-209, Duane Arnold Energy Center, & Point Beach, Units 1 and 2, Response to Request for Additional Information Related to Decommissioning Funding Status Report2011-06-0808 June 2011 Duane Arnold Energy Center, & Point Beach, Units 1 and 2, Response to Request for Additional Information Related to Decommissioning Funding Status Report NG-10-0105, Decommissioning Funding Status Report2010-03-25025 March 2010 Decommissioning Funding Status Report NG-10-0067, Document 82A9634, Revision 1, Decommissioning Cost Estimate Study for the Duane Arnold Energy Center, Enclosure 32010-01-27027 January 2010 Document 82A9634, Revision 1, Decommissioning Cost Estimate Study for the Duane Arnold Energy Center, Enclosure 3 L-2009-207, Units 1 & 2, Update to Decommissioning Funding Status and Financial Assurance Plan2009-09-11011 September 2009 Units 1 & 2, Update to Decommissioning Funding Status and Financial Assurance Plan L-2009-172, and Point Beach Nuclear Plant, Units 1 and 2 - Decommissioning Funding Status and Financial Assurance Plan2009-07-27027 July 2009 and Point Beach Nuclear Plant, Units 1 and 2 - Decommissioning Funding Status and Financial Assurance Plan L-2009-055, Units 1 and 2, Decommissioning Funding Status Reports2009-03-27027 March 2009 Units 1 and 2, Decommissioning Funding Status Reports NG-07-0481, Revised Decommissioning Funding Status Report2007-06-28028 June 2007 Revised Decommissioning Funding Status Report NG-07-0301, Decommissioning Funding Status Report2007-03-29029 March 2007 Decommissioning Funding Status Report NG-06-0282, Decommissioning Funding Status Report2006-03-31031 March 2006 Decommissioning Funding Status Report L-HU-05-008, Decommissioning Funding Status Reports2005-03-31031 March 2005 Decommissioning Funding Status Reports ML0329009652003-10-16016 October 2003 Decommissioning Funding Status Reports - Supplemental Response for Duane Arnold, Kewaunee, Monticello, Palisades, Point Beach, Units 1 and 2, and Prairie Island, Units 1 and 2 ML0309300582003-03-31031 March 2003 Decommissioning Funding Status Reports 2024-03-06 Category:40 MONTHYEARNG-24-0001, 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update2024-03-0606 March 2024
[Table view]2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update NG-23-0001, 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report2023-03-27027 March 2023 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-22-0041, And Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report2022-03-31031 March 2022 And Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-21-0006, 2021 Annual Decommissioning and Spent Fuel Management Funding Status Report2021-03-31031 March 2021 2021 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-20-0023, Decommissioning Funding Status Report2020-03-26026 March 2020 Decommissioning Funding Status Report NG-20-0007, Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50. 75(h)(1 )(Iv)2020-02-25025 February 2020 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50. 75(h)(1 )(Iv) L-2019-045, NextEra Energy Duane Arnold, Ilc - Independent Spent Fuel Storage Installation (ISFSI) - Decommissioning Funding Status Reports, Financial Assurance Update2019-03-25025 March 2019 NextEra Energy Duane Arnold, Ilc - Independent Spent Fuel Storage Installation (ISFSI) - Decommissioning Funding Status Reports, Financial Assurance Update NG-17-0220, License Amendment Request TSCR-177, Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements2017-11-10010 November 2017 License Amendment Request TSCR-177, Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements L-2015-064, Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2015-03-27027 March 2015 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update L-2013-103, Decommissioning Funding Status Reports2013-03-25025 March 2013 Decommissioning Funding Status Reports L-2012-442, Units 1 & 2 - ISFSI Decommissioning Funding Plans2012-12-17017 December 2012 Units 1 & 2 - ISFSI Decommissioning Funding Plans NG-12-0167, License Amendment Request (TSCR-135): Application for One-Time Technical Specification Change Regarding Core Spray Operability During Shutdown Section Affected: 3.3.5.12012-05-0101 May 2012 License Amendment Request (TSCR-135): Application for One-Time Technical Specification Change Regarding Core Spray Operability During Shutdown Section Affected: 3.3.5.1 L-2011-209, Duane Arnold Energy Center, & Point Beach, Units 1 and 2, Response to Request for Additional Information Related to Decommissioning Funding Status Report2011-06-0808 June 2011 Duane Arnold Energy Center, & Point Beach, Units 1 and 2, Response to Request for Additional Information Related to Decommissioning Funding Status Report NG-10-0105, Decommissioning Funding Status Report2010-03-25025 March 2010 Decommissioning Funding Status Report NG-10-0067, Document 82A9634, Revision 1, Decommissioning Cost Estimate Study for the Duane Arnold Energy Center, Enclosure 32010-01-27027 January 2010 Document 82A9634, Revision 1, Decommissioning Cost Estimate Study for the Duane Arnold Energy Center, Enclosure 3 L-2009-207, Units 1 & 2, Update to Decommissioning Funding Status and Financial Assurance Plan2009-09-11011 September 2009 Units 1 & 2, Update to Decommissioning Funding Status and Financial Assurance Plan L-2009-172, and Point Beach Nuclear Plant, Units 1 and 2 - Decommissioning Funding Status and Financial Assurance Plan2009-07-27027 July 2009 and Point Beach Nuclear Plant, Units 1 and 2 - Decommissioning Funding Status and Financial Assurance Plan L-2009-055, Units 1 and 2, Decommissioning Funding Status Reports2009-03-27027 March 2009 Units 1 and 2, Decommissioning Funding Status Reports NG-07-0481, Revised Decommissioning Funding Status Report2007-06-28028 June 2007 Revised Decommissioning Funding Status Report NG-07-0301, Decommissioning Funding Status Report2007-03-29029 March 2007 Decommissioning Funding Status Report NG-06-0282, Decommissioning Funding Status Report2006-03-31031 March 2006 Decommissioning Funding Status Report L-HU-05-008, Decommissioning Funding Status Reports2005-03-31031 March 2005 Decommissioning Funding Status Reports ML0329009652003-10-16016 October 2003 Decommissioning Funding Status Reports - Supplemental Response for Duane Arnold, Kewaunee, Monticello, Palisades, Point Beach, Units 1 and 2, and Prairie Island, Units 1 and 2 ML0309300582003-03-31031 March 2003 Decommissioning Funding Status Reports 2024-03-06 Category:50 MONTHYEARNG-24-0001, 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update2024-03-0606 March 2024
[Table view]2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update NG-23-0001, 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report2023-03-27027 March 2023 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-22-0041, And Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report2022-03-31031 March 2022 And Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-21-0006, 2021 Annual Decommissioning and Spent Fuel Management Funding Status Report2021-03-31031 March 2021 2021 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-20-0023, Decommissioning Funding Status Report2020-03-26026 March 2020 Decommissioning Funding Status Report NG-20-0007, Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50. 75(h)(1 )(Iv)2020-02-25025 February 2020 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50. 75(h)(1 )(Iv) L-2019-045, NextEra Energy Duane Arnold, Ilc - Independent Spent Fuel Storage Installation (ISFSI) - Decommissioning Funding Status Reports, Financial Assurance Update2019-03-25025 March 2019 NextEra Energy Duane Arnold, Ilc - Independent Spent Fuel Storage Installation (ISFSI) - Decommissioning Funding Status Reports, Financial Assurance Update L-2015-064, Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2015-03-27027 March 2015 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update L-2013-103, Decommissioning Funding Status Reports2013-03-25025 March 2013 Decommissioning Funding Status Reports L-2012-442, Units 1 & 2 - ISFSI Decommissioning Funding Plans2012-12-17017 December 2012 Units 1 & 2 - ISFSI Decommissioning Funding Plans L-2011-209, Duane Arnold Energy Center, & Point Beach, Units 1 and 2, Response to Request for Additional Information Related to Decommissioning Funding Status Report2011-06-0808 June 2011 Duane Arnold Energy Center, & Point Beach, Units 1 and 2, Response to Request for Additional Information Related to Decommissioning Funding Status Report NG-10-0105, Decommissioning Funding Status Report2010-03-25025 March 2010 Decommissioning Funding Status Report NG-10-0067, Document 82A9634, Revision 1, Decommissioning Cost Estimate Study for the Duane Arnold Energy Center, Enclosure 32010-01-27027 January 2010 Document 82A9634, Revision 1, Decommissioning Cost Estimate Study for the Duane Arnold Energy Center, Enclosure 3 L-2009-207, Units 1 & 2, Update to Decommissioning Funding Status and Financial Assurance Plan2009-09-11011 September 2009 Units 1 & 2, Update to Decommissioning Funding Status and Financial Assurance Plan L-2009-172, and Point Beach Nuclear Plant, Units 1 and 2 - Decommissioning Funding Status and Financial Assurance Plan2009-07-27027 July 2009 and Point Beach Nuclear Plant, Units 1 and 2 - Decommissioning Funding Status and Financial Assurance Plan L-2009-055, Units 1 and 2, Decommissioning Funding Status Reports2009-03-27027 March 2009 Units 1 and 2, Decommissioning Funding Status Reports NG-07-0481, Revised Decommissioning Funding Status Report2007-06-28028 June 2007 Revised Decommissioning Funding Status Report NG-07-0301, Decommissioning Funding Status Report2007-03-29029 March 2007 Decommissioning Funding Status Report NG-06-0282, Decommissioning Funding Status Report2006-03-31031 March 2006 Decommissioning Funding Status Report L-HU-05-008, Decommissioning Funding Status Reports2005-03-31031 March 2005 Decommissioning Funding Status Reports ML0329009652003-10-16016 October 2003 Decommissioning Funding Status Reports - Supplemental Response for Duane Arnold, Kewaunee, Monticello, Palisades, Point Beach, Units 1 and 2, and Prairie Island, Units 1 and 2 ML0309300582003-03-31031 March 2003 Decommissioning Funding Status Reports 2024-03-06 Category:70 MONTHYEARNG-24-0001, 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update2024-03-0606 March 2024
[Table view]2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update NG-23-0001, 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report2023-03-27027 March 2023 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-22-0041, And Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report2022-03-31031 March 2022 And Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-21-0006, 2021 Annual Decommissioning and Spent Fuel Management Funding Status Report2021-03-31031 March 2021 2021 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-20-0023, Decommissioning Funding Status Report2020-03-26026 March 2020 Decommissioning Funding Status Report NG-20-0007, Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50. 75(h)(1 )(Iv)2020-02-25025 February 2020 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50. 75(h)(1 )(Iv) L-2019-045, NextEra Energy Duane Arnold, Ilc - Independent Spent Fuel Storage Installation (ISFSI) - Decommissioning Funding Status Reports, Financial Assurance Update2019-03-25025 March 2019 NextEra Energy Duane Arnold, Ilc - Independent Spent Fuel Storage Installation (ISFSI) - Decommissioning Funding Status Reports, Financial Assurance Update NG-17-0220, License Amendment Request TSCR-177, Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements2017-11-10010 November 2017 License Amendment Request TSCR-177, Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements L-2015-064, Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2015-03-27027 March 2015 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update L-2013-103, Decommissioning Funding Status Reports2013-03-25025 March 2013 Decommissioning Funding Status Reports L-2012-442, Units 1 & 2 - ISFSI Decommissioning Funding Plans2012-12-17017 December 2012 Units 1 & 2 - ISFSI Decommissioning Funding Plans NG-12-0167, License Amendment Request (TSCR-135): Application for One-Time Technical Specification Change Regarding Core Spray Operability During Shutdown Section Affected: 3.3.5.12012-05-0101 May 2012 License Amendment Request (TSCR-135): Application for One-Time Technical Specification Change Regarding Core Spray Operability During Shutdown Section Affected: 3.3.5.1 L-2011-209, Duane Arnold Energy Center, & Point Beach, Units 1 and 2, Response to Request for Additional Information Related to Decommissioning Funding Status Report2011-06-0808 June 2011 Duane Arnold Energy Center, & Point Beach, Units 1 and 2, Response to Request for Additional Information Related to Decommissioning Funding Status Report NG-10-0105, Decommissioning Funding Status Report2010-03-25025 March 2010 Decommissioning Funding Status Report NG-10-0067, Document 82A9634, Revision 1, Decommissioning Cost Estimate Study for the Duane Arnold Energy Center, Enclosure 32010-01-27027 January 2010 Document 82A9634, Revision 1, Decommissioning Cost Estimate Study for the Duane Arnold Energy Center, Enclosure 3 L-2009-207, Units 1 & 2, Update to Decommissioning Funding Status and Financial Assurance Plan2009-09-11011 September 2009 Units 1 & 2, Update to Decommissioning Funding Status and Financial Assurance Plan L-2009-172, and Point Beach Nuclear Plant, Units 1 and 2 - Decommissioning Funding Status and Financial Assurance Plan2009-07-27027 July 2009 and Point Beach Nuclear Plant, Units 1 and 2 - Decommissioning Funding Status and Financial Assurance Plan L-2009-055, Units 1 and 2, Decommissioning Funding Status Reports2009-03-27027 March 2009 Units 1 and 2, Decommissioning Funding Status Reports NG-07-0481, Revised Decommissioning Funding Status Report2007-06-28028 June 2007 Revised Decommissioning Funding Status Report NG-07-0301, Decommissioning Funding Status Report2007-03-29029 March 2007 Decommissioning Funding Status Report NG-06-0282, Decommissioning Funding Status Report2006-03-31031 March 2006 Decommissioning Funding Status Report L-HU-05-008, Decommissioning Funding Status Reports2005-03-31031 March 2005 Decommissioning Funding Status Reports ML0329009652003-10-16016 October 2003 Decommissioning Funding Status Reports - Supplemental Response for Duane Arnold, Kewaunee, Monticello, Palisades, Point Beach, Units 1 and 2, and Prairie Island, Units 1 and 2 ML0309300582003-03-31031 March 2003 Decommissioning Funding Status Reports 2024-03-06 Category:Letter type:NG MONTHYEARNG-24-0004, 2023 Annual Radiological Environmental Operating Report2024-05-0808 May 2024
[Table view]2023 Annual Radiological Environmental Operating Report NG-24-0003, Submittal of 2023 Annual Radioactive Material Release Report2024-04-24024 April 2024 Submittal of 2023 Annual Radioactive Material Release Report NG-24-0001, 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update2024-03-0606 March 2024 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update NG-24-0002, 2023 Annual Exposure Report - Form 5s2024-03-0606 March 2024 2023 Annual Exposure Report - Form 5s NG-23-0010, Supplement to Duane Arnold Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-12-0606 December 2023 Supplement to Duane Arnold Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule NG-23-0009, Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule NG-23-0006, Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2023-05-23023 May 2023 Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update NG-23-0004, 2022 Annual Radioactive Material Release Report2023-04-25025 April 2023 2022 Annual Radioactive Material Release Report NG-23-0003, 2022 Annual Exposure Report - Form 5s2023-04-21021 April 2023 2022 Annual Exposure Report - Form 5s NG-23-0002, 10 CFR 50.59 Report, Commitment Changes, 10 CFR 72.48 Report, Quality Assurance Program Changes, Technical Specification Basis Changes, and Revision of the DAEC Defueled Safety Analysis Report2023-03-27027 March 2023 10 CFR 50.59 Report, Commitment Changes, 10 CFR 72.48 Report, Quality Assurance Program Changes, Technical Specification Basis Changes, and Revision of the DAEC Defueled Safety Analysis Report NG-23-0001, 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report2023-03-27027 March 2023 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-22-0055, Revision to Duane Arnold Energy Center (DAEC) ISFSI-Only Emergency Plan2022-05-20020 May 2022 Revision to Duane Arnold Energy Center (DAEC) ISFSI-Only Emergency Plan NG-22-0053, 2021 Annual Radiological Environmental Operating Report2022-05-0606 May 2022 2021 Annual Radiological Environmental Operating Report NG-22-0052, Regulatory Issue Summary 2000-11. NRC Emergency Telecommunications System, Statement of Intent to Implement the Proposed Voluntary Initiative2022-05-0404 May 2022 Regulatory Issue Summary 2000-11. NRC Emergency Telecommunications System, Statement of Intent to Implement the Proposed Voluntary Initiative NG-22-0050, Revised Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program, Revision 02022-04-26026 April 2022 Revised Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program, Revision 0 NG-22-0049, 2021 Annual Radioactive Material Release Report2022-04-26026 April 2022 2021 Annual Radioactive Material Release Report NG-22-0035, Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program. Revision 02022-04-13013 April 2022 Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program. Revision 0 NG-22-0047, Registration of Independent Spent Fuel Installation Storage Cask and Notification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool2022-04-11011 April 2022 Registration of Independent Spent Fuel Installation Storage Cask and Notification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool NG-22-0042, Registration of Independent Spent Fuel Installation Storage Casks2022-04-0808 April 2022 Registration of Independent Spent Fuel Installation Storage Casks NG-22-0041, And Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report2022-03-31031 March 2022 And Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-22-0030, Registration of Independent Spent Fuel Installation Storage Casks2022-03-23023 March 2022 Registration of Independent Spent Fuel Installation Storage Casks NG-22-0031, 2021 Annual Exposure Report - Form 5s2022-03-23023 March 2022 2021 Annual Exposure Report - Form 5s NG-22-0025, Registration of Independent Spent Fuel Installation Storage Casks2022-03-0808 March 2022 Registration of Independent Spent Fuel Installation Storage Casks NG-22-0021, Registration of Independent Spent Fuel Installation Storage Casks2022-02-24024 February 2022 Registration of Independent Spent Fuel Installation Storage Casks NG-22-0014, Registration of Independent Spent Fuel Installation Storage Casks2022-02-10010 February 2022 Registration of Independent Spent Fuel Installation Storage Casks NG-22-0009, Registration of Independent Spent Fuel Installation Storage Casks2022-01-20020 January 2022 Registration of Independent Spent Fuel Installation Storage Casks NG-22-0001, Supplement to Exemption Request for Failed Fuel Can Weight in a Certificate of Compliance 1004 Renewed Amendment 17 61BTH Type 2 Dry Shielded Canister2022-01-0606 January 2022 Supplement to Exemption Request for Failed Fuel Can Weight in a Certificate of Compliance 1004 Renewed Amendment 17 61BTH Type 2 Dry Shielded Canister NG-21-0038, Registration of Independent Spent Fuel Installation Storage Casks2021-12-22022 December 2021 Registration of Independent Spent Fuel Installation Storage Casks NG-21-0035, Supplement to Exemption Request for Failed Fuel Can Weight in a Certificate of Compliance 1004 Renewed Amendment 17 61 Bth Type 2 Dry Shielded Canister2021-12-10010 December 2021 Supplement to Exemption Request for Failed Fuel Can Weight in a Certificate of Compliance 1004 Renewed Amendment 17 61 Bth Type 2 Dry Shielded Canister NG-21-0030, Exemption Request for Failed Fuel Can Weight in a Certificate of Compliance 1004 Renewed Amendment 17 61 Bth Type 2 Dry Shielded Canister2021-10-21021 October 2021 Exemption Request for Failed Fuel Can Weight in a Certificate of Compliance 1004 Renewed Amendment 17 61 Bth Type 2 Dry Shielded Canister NG-21-0028, Request for Approval of NextEra Energy Duane Arnold, Llc'S Decommissioning Quality Assurance Program Revision 02021-07-30030 July 2021 Request for Approval of NextEra Energy Duane Arnold, Llc'S Decommissioning Quality Assurance Program Revision 0 NG-21-0010, License Amendment Request (TSCR-192): Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme2021-06-28028 June 2021 License Amendment Request (TSCR-192): Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme NG-21-0026, CFR 72.48 Report of Changes. Tests. and Experiments2021-06-16016 June 2021 CFR 72.48 Report of Changes. Tests. and Experiments NG-21-0011, Submittal of 2020 Annual Radiological Environmental Operating Report2021-05-0404 May 2021 Submittal of 2020 Annual Radiological Environmental Operating Report NG-21-0009, Report of Facility Changes. Tests and Experiments. and Commitment Changes2021-04-27027 April 2021 Report of Facility Changes. Tests and Experiments. and Commitment Changes NG-21-0021, Supplement to License Amendment Request (TSCR-185): Application to Revise Operating License to Remove Cyber Security Plan Requirements2021-04-22022 April 2021 Supplement to License Amendment Request (TSCR-185): Application to Revise Operating License to Remove Cyber Security Plan Requirements NG-21-0006, 2021 Annual Decommissioning and Spent Fuel Management Funding Status Report2021-03-31031 March 2021 2021 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-21-0005, NextEra Energy Duane Arnold, LLC - Transmittal of the DAEC Defueled Safety Analysis Report Revision 02021-03-29029 March 2021 NextEra Energy Duane Arnold, LLC - Transmittal of the DAEC Defueled Safety Analysis Report Revision 0 NG-20-0094, License Amendment Request (TSCR-189): Revision to Facility License and Technical Specifications to Reflect Permanent Removal of Spent Fuel from the Spent Fuel Pool2021-02-19019 February 2021 License Amendment Request (TSCR-189): Revision to Facility License and Technical Specifications to Reflect Permanent Removal of Spent Fuel from the Spent Fuel Pool NG-21-0004, Response to Request for Additional Information Related to Post Shutdown Decommissioning Activities Report2021-02-0505 February 2021 Response to Request for Additional Information Related to Post Shutdown Decommissioning Activities Report NG-20-0078, Update to Spent Fuel Management Plan Pursuant to 10 CFR 50.54(bb)2021-01-13013 January 2021 Update to Spent Fuel Management Plan Pursuant to 10 CFR 50.54(bb) NG-20-0101, Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to COVID-19 Pandemic2020-12-29029 December 2020 Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to COVID-19 Pandemic NG-20-0099, Response to Request for Additional Information Relating to License Amendment Request (TSCR-187): Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme2020-12-0101 December 2020 Response to Request for Additional Information Relating to License Amendment Request (TSCR-187): Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme NG-20-0093, Supplement to License Amendment Request (TSCR-187): Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme2020-10-29029 October 2020 Supplement to License Amendment Request (TSCR-187): Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme NG-20-0090, Certification of Permanent Removal of Fuel from the Reactor Vessel for Duane Arnold Energy Center2020-10-12012 October 2020 Certification of Permanent Removal of Fuel from the Reactor Vessel for Duane Arnold Energy Center NG-20-0083, Registration of Independent Spent Fuel Installation Storage Casks2020-10-12012 October 2020 Registration of Independent Spent Fuel Installation Storage Casks NG-20-0069, Response to Request for Additional Information Relating to Request for Exemption from Portions of 10 CFR 50.47 and 10 CFR 50, Appendix E2020-10-0707 October 2020 Response to Request for Additional Information Relating to Request for Exemption from Portions of 10 CFR 50.47 and 10 CFR 50, Appendix E NG-20-0082, Registration of Independent Spent Fuel Installation Storage Casks2020-09-28028 September 2020 Registration of Independent Spent Fuel Installation Storage Casks NG-20-0071, Request for One-Time Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Evaluated Exercise Requirements Due to COVID-19 Pandemic2020-09-22022 September 2020 Request for One-Time Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Evaluated Exercise Requirements Due to COVID-19 Pandemic NG-20-0077, Registration of Independent Spent Fuel Installation Storage Casks2020-09-10010 September 2020 Registration of Independent Spent Fuel Installation Storage Casks 2024-05-08 Category:Status Report MONTHYEARML24240A1692024-09-18018 September 2024
[Table view]Cy 2023 Summary of Decommissioning Trust Fund Status NG-24-0001, 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update2024-03-0606 March 2024 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update NG-23-0001, 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report2023-03-27027 March 2023 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-18-0138, NextEra Energy Duane Arnold, Llc'S Completion of Required Action for NRC Order Number EA-13-109, Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2018-12-19019 December 2018 NextEra Energy Duane Arnold, Llc'S Completion of Required Action for NRC Order Number EA-13-109, Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions NG-18-0066, Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2018-06-26026 June 2018 Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions NG-17-0250, Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (EA-13-109)2017-12-19019 December 2017 Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (EA-13-109) NG-17-0121, Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order EA-13-109)2017-06-29029 June 2017 Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order EA-13-109) L-2017-040, Decommissioning Funding Status Reports/Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2017-03-30030 March 2017 Decommissioning Funding Status Reports/Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update NG-16-0241, Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)2016-12-22022 December 2016 Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109) NG-16-0168, Six Month Status Report in Response to 03/12/2012 Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation2016-08-31031 August 2016 Six Month Status Report in Response to 03/12/2012 Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation NG-16-0169, Duane Arnold, Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2016-08-31031 August 2016 Duane Arnold, Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events NG-16-0130, Six-Month Status Report in Response to 06/06/2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)2016-06-30030 June 2016 Six-Month Status Report in Response to 06/06/2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109) ML16187A2612016-06-30030 June 2016 Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109) NG-15-0280, Six Month Status Report in Response to March 12, 2012 Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-08-27027 August 2015 Six Month Status Report in Response to March 12, 2012 Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) NG-15-0032, NextEra Energy Duane Arnold Energy Center, Llc'S Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard Response to March 12, 2012 Commission Order Modifying Licenses with Regard Events (Orde2015-02-19019 February 2015 NextEra Energy Duane Arnold Energy Center, Llc'S Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard Response to March 12, 2012 Commission Order Modifying Licenses with Regard Events (Order NG-15-0027, Six Month Status Report in Response to March 12, 2012 Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-16016 February 2015 Six Month Status Report in Response to March 12, 2012 Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) NG-14-0285, NextEra Energy Duane Arnold, Llc'S Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Num2014-12-10010 December 2014 NextEra Energy Duane Arnold, Llc'S Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Numbe NG-14-0061, NextEra Energy Duane Arnold Energy Center, Llc'S Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Orde2014-02-24024 February 2014 NextEra Energy Duane Arnold Energy Center, Llc'S Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order NG-14-0068, NextEra Energy Duane Arnold Energy Center, Llc'S Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-02-24024 February 2014 NextEra Energy Duane Arnold Energy Center, Llc'S Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) NG-13-0328, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)2013-08-27027 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049) NG-13-0324, First Six-Month Status Report in Response to Letter Dated March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation2013-08-27027 August 2013 First Six-Month Status Report in Response to Letter Dated March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation L-2013-103, Decommissioning Funding Status Reports2013-03-25025 March 2013 Decommissioning Funding Status Reports ML1214500142012-05-23023 May 2012 NFPA 805 LAR Status Matrix - May 2012 ML1029505682010-04-23023 April 2010 E-Mail from Burritt to Balian, Branch 3 Status - 4/23/10 NG-10-0105, Decommissioning Funding Status Report2010-03-25025 March 2010 Decommissioning Funding Status Report L-2009-055, Units 1 and 2, Decommissioning Funding Status Reports2009-03-27027 March 2009 Units 1 and 2, Decommissioning Funding Status Reports NG-07-0481, Revised Decommissioning Funding Status Report2007-06-28028 June 2007 Revised Decommissioning Funding Status Report NG-07-0301, Decommissioning Funding Status Report2007-03-29029 March 2007 Decommissioning Funding Status Report NG-06-0282, Decommissioning Funding Status Report2006-03-31031 March 2006 Decommissioning Funding Status Report L-HU-05-008, Decommissioning Funding Status Reports2005-03-31031 March 2005 Decommissioning Funding Status Reports L-HU-04-040, Nuclear Management Company, LLC, Implementation Status of Independent Spent Fuel Storage Installation Interim Compensatory Measures2004-09-24024 September 2004 Nuclear Management Company, LLC, Implementation Status of Independent Spent Fuel Storage Installation Interim Compensatory Measures ML0329009652003-10-16016 October 2003 Decommissioning Funding Status Reports - Supplemental Response for Duane Arnold, Kewaunee, Monticello, Palisades, Point Beach, Units 1 and 2, and Prairie Island, Units 1 and 2 2024-09-18 |
Text
FPL Energy Duane Arnold, LLC 3277 DAEC Road Palo, Iowa 52324 FPL [
Duane Arndd Energy Center March 29, 2007 NG-07-0301 10 CFR 50.75(f)(1)
U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Duane Arnold Energy Center Docket 50-331 License No. DPR-49
Subject:
Decommissioning Funding Status Report for the Duane Arnold Energy Center In accordance with the provisions of 10 CFR 50.75(f)(1), please find enclosed the decommissioning funding status report for the Duane Arnold Energy Center (DAEC).
FPL Energy, Duane Arnold, LLC submits this report on behalf of all the DAEC owners.
TheIfinancial information presented herein,' is current as of December 31,2006.
This letter contains no new commitments and no revisions to existing commitments.
If you have any questions concerning this matter, please contact Steven Catron, Manager, Nuclear Licensing at (319) 851-7234.
Sincerely, GaryVan Middlesworth Site Vice. President, Duane Arnold Energy Center Enclosure cc: Administrator, Region Ill, USNRC Project Manager, DAEC, USNRC Resident Inspector, DAEC, USNRC ooD(
Enclosure to NG-07-0301 March 29, 2007 FPL Energy Duane Arnold, LLC, Central Iowa Power Cooperative (CIPCO),
Corn Belt Power Cooperative (Corn Belt)
Decommissioning Funding Status Report The minimum decommissioning fund estimate pursuant to 10 CFR 50.75(b) a d (c).
Plant Owner (% Ownership) NRC Minimum FPL Energy Duane Arnold, LLC (70%) $329,633,641 CIPCO (20%) $94,181,040 Corn Belt (10%) $47,090,520 Total $470,905,201 The amount accumulated at the end of the calendar year preceding the date of the report.
Plant Owner (% Ownership) Internal External Total FPL Energy Duane Arnold, LLC (70%) $0 $205,876,043 $205,876,043 CIPCO (b) (20%) $27,422,178 $39,679,950 $67,102,128 Corn Belt (a) (10%) $9,562,460 $18,638,825 $28,201,285 Total $36,984,638 $264,194,818 $301,179,456 (a) Corn Belt is not relying on Internal Fund Reserve for purposes of meeting NRC decommissioning funding assurance requirements.
(b) These funds have been invested for purposes of funding decommissioning.
Schedule of the annual amounts remaining to be collected. (Beginning 2007 & Ending 2014)
Plant Owner (% Ownership) Annual Annuity Projected (a) Funds Ending 2014 FPL Energy Duane Arnold, LLC (70%) (b) $0 $312,275,149 CIPCO (20%) $1.0 mil to $3.2 mil $124,504,000 Corn Belt (10%) $500k to $700k $68,084,105 Total $1.5 to $3.9 mil $504,863,254 (a) Actual annual contributions to the external sinking fund will vary based upon reassessment of owner's decommissioning funding obligations in light of NRC requirements, actual inflation, actual fund earnings, and other factors.
(b) Projected funds include a $75 million parent guaranty from FPL Group Capital Inc.
Assumptions used regarding escalation in decommissioning costs, rate of earnings on decommissioning funds and rates of other factors used in funding projections.
Plant Owner (% Ownership) Rate of Earnings Escalation Real Rate of (Nominal Rate Of Factor Return Return) (Inflation) (Projected)
FPL Energy Duane Arnold, LLC (a) (70%) 7.1% 4.06% 2%
CIPCO (b) (20%) 8% 4% 4%
Corn Belt (c) (10%) 10% 5% 5%
Basis for Allowance:
(a) The real rate of return allowed by 10 CFR 50.75 is 2%.
Page 1 of 2
(b) Central Iowa Power Cooperative (CIPCO) is a tax-exempt cooperative under IRS section 501c(12). This exempt status allows for a higher rate of earnings that results in higher projected real rates of return. CIPCO's rates are not regulated by any state or federal agency. CIPCO's rates are determined annually based on a budget approved by the Board of Directors. If the cooperative does not obtain the projected earnings rates on the decommissioning fund, it has the ability to increase future funding to meet the decommissioning obligation.
(c) Corn Belt Power Cooperative is a tax-exempt cooperative under IRS section 501c(12).
This exempt status allows for higher rate of earnings that results in higher projected real rates of return. Corn Belt's rates are not regulated by any state or federal agency. Corn Belt's rates are determined annually based on a budget approved by the Board of Directors. If the cooperative does not obtain the projected earnings rates on the decommissioning fund, it has the ability to increase future funding to meet the decommissioning obligtion.
- 5. Any contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1 )(v). None FPL Energy Duane Arnold, LLC, CIPCO and Corn Belt are not relying upon any long term contract for purposes of providing decommissioning funding within the meaning of 10 CFR 50.75(e)(1)(v).
- 6. Any modifications to a licensee's method of providing financial assurance occurring since the last submitted report. See below FPL Energy Duane Arnold, LLC, CIPCO & Corn Belt continue to use the external sinking fund method of providing decommissioning funding assurance. FPL Group Capital Inc. is providing a parent guaranty in the amount of $75 million as an additional method of financial assurance for FPL Energy Duane Arnold, LLC.
- 7. Any material changes to trust agreements.
None Page 2 of 2