|
---|
Category:Inspection Plan
MONTHYEARML24262A1502024-09-24024 September 2024 Requalification Program Inspection - Browns Ferry Nuclear Plant IR 05000259/20240052024-08-26026 August 2024 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2024005, 05000260/2024005 and 05000296/2024005 ML24225A1682024-08-16016 August 2024 – Notification of Inspection and Request ML24087A1822024-03-28028 March 2024 Notification of Target Set Inspection and Request for Information NRC Inspection Report 05000259/2024403 and 05000260/2024403 and 05000296/2024403 ML24052A1472024-02-28028 February 2024 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2023006, 05000260/2023006 and 05000296/2023006 IR 05000259/20230052023-08-29029 August 2023 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2023005, 05000260/2023005 and 05000296/2023005 IR 05000259/20220062023-03-0101 March 2023 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 Report 05000259/2022006, 05000260/2022006 and 05000296/2022006 ML23020A0602023-01-20020 January 2023 Long Term Steam Dryer Inspection Plan IR 05000259/20220052022-08-30030 August 2022 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 Report 05000259/2022005, 05000260/2022005 and 05000296/2022005 ML22210A1342022-07-20020 July 2022 Requalification Inspection Notification Letter ML22174A2722022-06-24024 June 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000259/20224012022-03-0808 March 2022 Information Request for the Cyber-Security Baseline Inspection Notification to Perform Inspection 05000259/2022401; 05000260/2022401; 05000296/2022401 ML22091A1942022-03-0808 March 2022 2022 BFN POV Inspection Information Request IR 05000259/20210062022-03-0202 March 2022 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 (Report No. 05000259/2021006, 05000260/2021006 and 05000296/2021006 ML22025A4132022-01-25025 January 2022 RP Inspection Doc Request ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections ML21343A4232021-12-0909 December 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000259/2022010, 05000260/2022010, and 05000296/2022010) and Request for Information (RFI) IR 05000259/20210052021-08-23023 August 2021 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2, and 3- Report Nos. 05000259/2021005, 05000260/2021005 and 5000296/2021005 IR 05000259/20200062021-03-0303 March 2021 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2020006, 05000260/2020006 and 05000296/2020006 ML21047A4732021-02-16016 February 2021 Notification of Browns Ferry Nuclear Power Plant Design Bases Assurance Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000259/2021010, 05000260/2021010, and 05000296/2021010 ML20338A3682020-12-0303 December 2020 Notification of Inspection and Request for Information ML20266G4472020-09-22022 September 2020 Notification of Inspection and Request for Information IR 05000259/20200052020-08-18018 August 2020 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2020005, 05000260/2020005, and 05000296/2020005 ML20191A2232020-07-0909 July 2020 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000259/20190062020-03-0303 March 2020 Annual Assessment Letter for Browns Ferry Nuclear Plant Units 1,2,and 3 - NRC Report 05000259/2019006, 05000260/2019006, and 05000296/2019006 ML19108A1682019-04-18018 April 2019 EP Exercise Inspection RFI IR 05000259/20180062019-03-0404 March 2019 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2018006, 05000260/2018006 and 05000328/2018006 ML19030A6712019-01-25025 January 2019 U2 ISI RFI ML19024A4112019-01-24024 January 2019 Transmittal of RP Baseline Inspection Document Request 2019 ML18264A2052018-09-21021 September 2018 U1 ISI Emailed RFI Notification ML18059A1052018-02-28028 February 2018 EOC Assessment Letter ML18029A4672018-01-29029 January 2018 Notification of Browns Ferry Nuclear Plant Design Bases Assurance Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000259/2018010, 05000260/2018010, and 05000296/2018010 ML18029A2552018-01-29029 January 2018 U3 RFI Email Request ML17236A1972017-08-24024 August 2017 Updated Inspection Plan ML17156A1612017-06-0202 June 2017 Notification of Inspection and Request for Information IR 05000259/20160062017-03-0101 March 2017 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2, and 3 (Report 05000259/2016006, 05000260/2016006 and 05000296/2016006) IR 05000259/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3, NRC Inspection Reports 05000259/2016005, 05000260/2016005 and 05000296/2016005 ML16243A2242016-08-30030 August 2016 Notification of Inspection and Request for Information ML16120A1182016-04-27027 April 2016 Notification of Conduct of a Triennial Fire Protection Baseline Inspection - U.S. Nuclear Regulatory Commission Inspection Report Nos. 05000259/2016011, 05000260/2016011 and 05000296/2016011 IR 05000259/20150062016-03-0202 March 2016 Annual Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3 NRC Inspection Reports 05000259/2015006, 05000260/2015006 and 05000296/2015006 ML16013A0812016-01-12012 January 2016 Browns Ferry Nuclear Plant, Unit 3 - Notification of Inspection and Request for Information ML15348A1802015-12-14014 December 2015 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000259/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for the Browns Ferry Nuclear Plant Units 1, 2 and 3, NRC Inspection Report 005000259/2015005, 005000260/2015005, and 005000296/2015005 IR 05000259/20140012015-03-0404 March 2015 Annual Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3 - NRC Inspection Reports 05000259/2014001, 05000260/2014001 and 05000296/2014001 IR 05000259/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3 (NRC Inspection Reports 05000259/2014006, 05000260/2014006 and 05000296/2014006) ML14063A1092014-03-0404 March 2014 2013 Annual Assessment Letter for Browns Ferry ML14031A4122014-01-31031 January 2014 U3 2014002 ISI RFI Final - Copy ML13353A5852013-12-19019 December 2013 PIR Notification Letter 2014 ML13246A1842013-09-0303 September 2013 Mid Cycle Assessment Letter ML13084A0052013-03-25025 March 2013 Emergency Preparedness Inspection Notification and Request for Information 2024-09-24
[Table view] Category:Letter
MONTHYEARIR 05000259/20240032024-11-0404 November 2024 Integrated Inspection Report 05000259/2024003 and 05000260/2024003 and 05000296/2024003 CNL-24-043, Application for Subsequent Renewed Operating Licenses, Second Safety Supplement2024-11-0101 November 2024 Application for Subsequent Renewed Operating Licenses, Second Safety Supplement ML24305A1692024-10-31031 October 2024 Site Emergency Plan Implementing Procedure Revision 05000259/LER-2024-003, Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators2024-10-29029 October 2024 Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators 05000259/LER-2024-001-02, Secondary Containment Isolation Valve Inoperable Due to Mechanical Failure2024-10-28028 October 2024 Secondary Containment Isolation Valve Inoperable Due to Mechanical Failure ML24299A2632024-10-25025 October 2024 Response to Apparent Violation in NRC Inspection Report 05000260/2024090, EA-24-075 ML24289A1232024-10-24024 October 2024 Letter to James Barstow Re Environmental Scoping Summary Report for Browns Ferry CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24308A0042024-10-16016 October 2024 Ahc 24-1578 Environmental Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3 Subsequent License Renewal Application Limestone County CNL-24-077, Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 12024-10-0909 October 2024 Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 1 ML24270A2162024-09-27027 September 2024 Notice of Intentions Regarding Preliminary Finding from NRC Inspection Report 05000260/2024090, EA-24-075 CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description ML24262A1502024-09-24024 September 2024 Requalification Program Inspection - Browns Ferry Nuclear Plant ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24263A2952024-09-19019 September 2024 Site Emergency Plan Implementing Procedure Revision CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000260/20240902024-09-17017 September 2024 NRC Inspection Report 05000260/2024090 and Preliminary White Finding and Apparent Violation - 1 CNL-24-062, Cycle 16 Reload Analysis Report2024-09-16016 September 2024 Cycle 16 Reload Analysis Report ML24255A8862024-09-10010 September 2024 Core Operating Limits Report for Cycle 16 Operation, Revision 0 ML24239A3332024-09-0303 September 2024 Full Audit Plan IR 05000259/20244042024-09-0303 September 2024 Cyber Security Inspection Report 05000259/2024404 and 05000260-2024404 and 05000296/2024404-Cover Letter IR 05000259/20240052024-08-26026 August 2024 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2024005, 05000260/2024005 and 05000296/2024005 ML24225A1682024-08-16016 August 2024 – Notification of Inspection and Request IR 05000259/20244022024-08-0606 August 2024 Security Baseline Inspection Report 05000259/2024402 and 05000260/2024402 and 05000296/2024402 ML24219A0272024-08-0606 August 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000259/20240022024-08-0202 August 2024 Brown Ferry Nuclear Plant – Integrated Inspection Report05000259/2024002 and 05000260/2024002 and 05000296/2024002 ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter ML24183A4142024-07-10010 July 2024 – License Renewal Regulatory Limited Scope Audit Regarding the Environmental Review of the License Renewal Application (EPID Number: L-2024-SLE-0000) (Docket Numbers: 50-259, 50-260, and 50-296) 05000296/LER-2024-003, Main Steam Relief Valves Lift Settings Outside of Technical Specifications Required Setpoints2024-07-0808 July 2024 Main Steam Relief Valves Lift Settings Outside of Technical Specifications Required Setpoints 05000259/LER-2024-001-01, Inoperability of Unit 3 Diesel Generator Due to Relay Failure2024-07-0303 July 2024 Inoperability of Unit 3 Diesel Generator Due to Relay Failure ML24184A1142024-07-0202 July 2024 Site Emergency Plan Implementing Procedure Revision ML24183A3842024-07-0101 July 2024 Registration of Use of Cask to Store Spent Fuel (MPC-364, -365) ML24179A0282024-06-26026 June 2024 Evaluation of Effects of Out-of-Limits Condition as Described in IWB-3720(a) 05000259/LER-2024-002, Reactor Scram Due to Generator Step-Up Transformer Failure2024-06-24024 June 2024 Reactor Scram Due to Generator Step-Up Transformer Failure ML24175A0042024-06-23023 June 2024 Interim Report of a Deviation or Failure to Comply Associated with a Valve in the Unit 3 High Pressure Coolant Injection System ML24176A1132024-06-23023 June 2024 American Society of Mechanical Engineers, Section XI, Fourth 10 Year Inspection Interval, Inservice Inspection, System Pressure Test, Containment Inspection, and Repair and Replacement Programs, Owner’S Activity Report Cycle 21 Oper ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24155A0042024-06-18018 June 2024 Proposed Alternative to the Requirements of the ASME Code (Revised Alternative Request 0-ISI-47) ML24158A5312024-06-0606 June 2024 Registration of Use of Cask to Store Spent Fuel (MPC-361, -362, -363) ML24071A0292024-06-0505 June 2024 Subsequent License Renewal Application Enclosure 3 - Proprietary Determination Letter ML24068A2612024-06-0505 June 2024 SLRA Fluence Methodology Report - Proprietary Determination Letter IR 05000259/20244032024-05-22022 May 2024 – Security Baseline Report 05000259/2024403 and 05000260/2024403 and 05000296/2024403 05000260/LER-2024-002, High Pressure Coolant Injection Inoperable Due to Rupture Disc Failure and Resulting System Isolation2024-05-20020 May 2024 High Pressure Coolant Injection Inoperable Due to Rupture Disc Failure and Resulting System Isolation ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24136A0702024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000259/20240012024-05-14014 May 2024 Integrated Inspection Report 05000259/2024001, 05000260/2024001, and 05000296/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24123A2012024-05-0202 May 2024 NRC Cybersecurity Baseline Inspection (NRC Inspection Report 05000259/2024404, 05000260-2024404, 05000296/2024404) and Request for Information ML24122A6852024-05-0101 May 2024 2023 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual 2024-09-03
[Table view] |
Text
March 2, 2016
Mr. Joseph Vice President, Nuclear Licensing Tennessee Valley Authority 1101 Market Street, LP 3D-C Chattanooga, TN 37402-2801
SUBJECT: ANNUAL ASSESSMENT LETTER FOR BROWNS FERRY NUCLEAR PLANT UNITS 1, 2 AND 3 - NRC INSPECTION REPORTS 05000259/2015006, 05000260/2015006 AND 05000296/2015006
Dear Mr. Shea:
On February 11, 2016, the NRC completed its end-of-cycle performance review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2015, through December 31, 2015. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility. The NRC determined that overall, Browns Ferry Units 1, 2, and 3 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Browns Ferry Units 1, 2, and 3 during the most recent quarter was within the Licensee Response Column of the NRC's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility. The enclosed inspection plan lists the inspections scheduled through December 31, 2017. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence. In addition to the ROP baseline inspections at your facility, we also plan on conducting infrequently performed inspections which include: Inspection Procedure (IP) 43004, Inspection of Commercial-Grade Dedication Programs, IP 92702 Followup on Corrective Actions for Violations and Deviations and Operator Licensing Examinations. In response to the accident at Fukushima, the Commission issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design- Basis External Events." This Order requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation." This Order requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. The audit was completed for Browns Ferry Units 1, 2, and 3, and the information gathered will aid staff in development of the Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Final Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above by performing TI 191, "Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans." In accordance with 10 CFR 2.390 of the NRC's "Agency Rules of Practice and Procedure," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at (404) 997-4415 with any questions you may have regarding this letter.
Sincerely,/RA/ Alan Blamey, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket Nos.: 50-259, 50-260, 50-296 License Nos.: DPR-33, DPR-52, DPR-68
Enclosure:
Browns Ferry Inspection/Activity Plan (03/01/2016 - 12/31/2017) cc: Distribution via ListServ
________________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP SIGNATURE CRK1 AJB3 NAME C. Kontz A. Blamey DATE 2/26/2016 3/1/2016 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO Letter to Joseph from Alan Blamey dated March 2, 2016
SUBJECT: ANNUAL ASSESSMENT LETTER FOR BROWNS FERRY NUCLEAR PLANT UNITS 1, 2 AND 3 - NRC INSPECTION REPORTS 05000259/2015006, 05000260/2015006 AND 05000296/2015006 Distribution w/encl: D. Gamberoni, RII L. Gibson, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMBrownsFerry Resource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)
Page 1 of 203/02/201608:14:40Report 22UnitNumberPlanned DatesStart EndInspection ActivityTitleNo. of Staffon SiteBrowns FerryInspection / Activity Plan03/01/2016-12/31/2017RP-RAD HAZARDS ANALYSIS AND TRANSPORTATION21,2,3 IPRadiological Hazard Assessment and Exposure Controls71124.0102/29/201603/04/20161,2,3 IPRadioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.0802/29/201603/04/2016ISI-UNIT 3 IN-SERVICE INSPECTION1 3 IPInservice Inspection Activities - BWR7111108G03/07/201603/11/2016LR-UNIT 3 POST APPROVAL LR PHASE 12 3 IPPost-Approval Site Inspection for License Renewal7100303/07/201603/11/2016EQ-ENVIRONMENTAL QUALIFICATION INSPECTION41,2,3 IPComponent Design Bases Inspection711112103/21/201603/25/20161,2,3 IPComponent Design Bases Inspection711112104/11/201604/15/2016EP-EP PROGRAM INSPECTION61,2,3 IPAlert and Notification System Testing711140206/06/201606/10/20161,2,3 IPEmergency Preparedness Organization Staffing and Augmentation System711140306/06/201606/10/20161,2,3 IPEmergency Action Level and Emergency Plan Changes711140406/06/201606/10/20161,2,3 IPCorrection of Emergency Preparedness Weaknesses and Deficiencies711140506/06/201606/10/20161,2,3 IPPerformance Indicator Verification7115106/06/201606/10/2016RP-RP PUBLIC RAD SAFETY BASELINE21,2,3 IPRadioactive Gaseous and Liquid Effluent Treatment71124.0606/13/201606/17/20161,2,3 IPRadiological Environmental Monitoring Program71124.0706/13/201606/17/20161,2,3 IPPerformance Indicator Verification7115106/13/201606/17/2016TFPI-TRIENNIEL FIRE PROTECTION INSPECTION71,2,3 IPFire Protection [Triennial]7111105T07/25/201607/29/20161,2,3 IPFire Protection [Triennial]7111105T08/08/201608/12/2016OL RQ-REQUAL INSP21,2,3 IPLicensed Operator Requalification Program7111111B09/12/201609/16/2016ISI-UNIT 1 IN-SERVICE INSPECTION11 IPInservice Inspection Activities - BWR7111108G10/10/201610/14/2016ISI-UNIT 2 IN-SERVICE INSPECTION1 2 IPInservice Inspection Activities - BWR7111108G03/13/201703/17/2017OL EXAM-INITIAL LICENSE EXAM PREP31 BROWNS FERRY/APRIL 2017 INITIAL EXAM AT POWER FACILITIESV2349003/13/201703/17/2017RP-RP OCCUPATIONAL INSPECTION WEEK 131,2,3 IPRadiological Hazard Assessment and Exposure Controls71124.0103/13/201703/17/2017This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
Page 2 of 203/02/201608:14:40Report 22UnitNumberPlanned DatesStart EndInspection ActivityTitleNo. of Staffon SiteBrowns FerryInspection / Activity Plan03/01/2016-12/31/2017RP-RP OCCUPATIONAL INSPECTION WEEK 131,2,3 IPOccupational ALARA Planning and Controls71124.0203/13/201703/17/20171,2,3 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0303/13/201703/17/20171,2,3 IPOccupational Dose Assessment71124.0403/13/201703/17/20171,2,3 IPRadiation Monitoring Instrumentation71124.0503/13/201703/17/20171,2,3 IPPerformance Indicator Verification7115103/13/201703/17/2017RP-RP OCCUPATIONAL INSPECTION WEEK 221,2,3 IPRadiological Hazard Assessment and Exposure Controls71124.0104/03/201704/07/20171,2,3 IPOccupational ALARA Planning and Controls71124.0204/03/201704/07/20171,2,3 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0304/03/201704/07/20171,2,3 IPOccupational Dose Assessment71124.0404/03/201704/07/20171,2,3 IPRadiation Monitoring Instrumentation71124.0504/03/201704/07/20171,2,3 IPPerformance Indicator Verification7115104/03/201704/07/2017OL EXAM-INITIAL LICENSE EXAM31 BROWNS FERRY/APRIL 2017 INITIAL EXAM AT POWER FACILITIESV2349004/03/201704/21/2017EP-EP EXERCISE61,2,3 IPExercise Evaluation711140106/26/201706/30/20171,2,3 IPEmergency Action Level and Emergency Plan Changes711140406/26/201706/30/20171,2,3 IPExercise Evaluation - Scenario Review711140806/26/201706/30/20171,2,3 IPPerformance Indicator Verification7115106/26/201706/30/2017HS-TRIENNIAL HEAT SINK PERFORMANCE11,2,3 IPHeat Sink Performance7111107T07/24/201707/28/2017MODS-PLANT MODIFICATIONS INSPECTION31,2,3 IPEvaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T12/04/201712/08/20171,2,3 IPEvaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T12/18/201712/22/2017This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.