ML16180A173
From kanterella
Revision as of 15:37, 14 May 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
ML16180A173 | |
Person / Time | |
---|---|
Site: | Ginna |
Issue date: | 05/05/2016 |
From: | Exelon Generation Co |
To: | Office of Nuclear Reactor Regulation |
Shared Package | |
ML16180A174 | List:
|
References | |
Download: ML16180A173 (9) | |
Similar Documents at Ginna | |
---|---|
Category:Updated Final Safety Analysis Report (UFSAR)
MONTHYEARML20339A0532020-11-20020 November 2020
[Table view]9 to Updated Final Safety Analysis Report, Chapter 3, Appendix 3E Thru 3F ML20339A0232020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 2, Appendices ML20339A0582020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 2, Site Characteristics, Table of Contents ML20339A0652020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 6, Engineered Safety Features, Sections 6.1 Through 6.6 ML20339A0552020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 3, Design of Structures, Components, Equipment, and Systems, Section 3.8, Design of Seismic Category I Structures ML20339A0472020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 11, Figures ML20339A1782020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 14, Initial Test Program, Sections 14.1 Thru 14.6 ML20339A0542020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 17, Quality Assurance, Table of Contents ML20339A0992020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Fire Protection Program (FPP) Revision 18, Technical Specification Bases Changes, Revision 101, Summary of 50.59 Evaluations and 72.48 Evaluations ML20339A0422020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 17, Quality Assurance, Sections 17.1 Thru 17.2 ML20339A0412020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 15, Accident Analysis, Figures ML20339A0452020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 11, Radioactive Waste Management, Sections 11.1 Through 11.5 ML20339A0372020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 2, Appendix 2A, Probable Maximum Flood and Low Water Conditions, Figures ML20339A0292020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 2, Appendix C Report, Figures ML20339A0162020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 10, Steam and Power Conversion System, Figures ML20339A0382020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 13, Conduct of Operations, Table of Contents ML20339A0512020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 3, Appendix 3C, Containment Shell Stress Calculation Results ML20339A0692020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 4, Reactor, Table of Contents ML20339A0282020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 6, Engineered Safety Features, Table of Contents ML20339A0272020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 7, Instrumentation and Controls, Sections 7.1 Through 7.7 ML20339A2972020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 15, Accident Analyses, Table of Contents ML20339A0682020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 3, Design of Structures, Components, Equipment and Systems, Table of Contents ML20339A0312020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 3, Appendix 3D, Containment Tendon Anchorage Hardware Capacity Tests ML20339A0322020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 12, Radiation Protection, Figure 12.5-1 ML20339A0252020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 9, Auxiliary Systems, Sections 9.1 Through 9.5 ML20339A0212020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 8, Figure 8.1-1 Electrical Distribution System & Figure 8.2-1 Transmission Connections ML20339A0202020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 3, Design of Structures, Components, Equipment, and Systems, Sections 3.1 Through 3.7 ML20339A0142020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 17, Figure 17.1-1, Quality Control Relationships During Construction ML20339A0502020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 13, Conduct of Operations, Sections 13.1 Through 13.6 ML20339A0332020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 2, Site Characteristics, Sections 2.1 Through 2.5 ML20339A0462020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 9, Auxiliary Systems, Table of Contents ML20339A0572020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 3, Design of Structures, Components, Equipment, and Systems, Sections 3.9 Through 3.11 ML20339A0602020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 18, Updated Final Safety Analysis Report Supplement for License Renewal, Sections 18.1 Through 18.4 ML20339A0342020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 2, Site Characteristics, Figures ML20339A0562020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 11, Radioactive Waste Management, Table of Contents ML20339A0392020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 8, Electric Power, Table of Contents ML20339A0402020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 10, Steam and Power Conversion System, Sections 10.1 Thru 10.7 ML20339A1012020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 15, Accident Analyses ML20339A0262020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 18, Table of Contents ML20339A0352020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 5, Reactor Coolant System and Connected Systems, Figures ML20339A0132020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 5, Reactor Coolant System and Connected Systems, Section 5.1 Thru 5.8 ML20339A0302020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 12, Radiation Protection, Table of Contents ML20339A0642020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 10, Steam and Power Conversion System, Table of Contents ML20339A0612020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 5, Reactor Coolant System and Connected Systems, Table of Contents ML20339A0632020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 13, Conduct of Operations, Figures ML20339A0522020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 2, Appendix 2B, Drift and Dispersion Characteristics of Lake Ontario Near Shore Waters, Figures ML20339A2402020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 14, Initial Test Program, Table of Contents ML20339A0432020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 9, Auxiliary Systems, Figures ML20339A0442020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 1, Table of Content ML20339A0622020-11-20020 November 2020 9 to Updated Final Safety Analysis Report, Chapter 8, Electric Power, Sections 8.1 Through 8.3 2020-11-20 |
Text
Retrieved from "https://kanterella.com/w/index.php?title=ML16180A173&oldid=638875"