Revision 26 to the Updated Final Safety Analysis Report, Chapter 14, Initial Test Program, Figure 134.2-1, Initial Plant Organization
ML16180A181
Person / Time
Site: Ginna Constellation icon.png
Issue date: 05/05/2016
From:
Exelon Generation Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML16180A174 List:
References
Download: ML16180A181 (43)


Text

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.2-1 Initial Plant Organization Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-1 Sheet 1 - Original Safety Injection System Functional Test Data Sheet (Typical)

Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-1 Sheet 2 - Original Safety Injection System Functional Test Data Sheet (Typical)

Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-2 Sheet 1 - Rod Cluster Control Assembly Drop Time Test Results (Typical)

Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-2 Sheet 2 - Rod Cluster Control Assembly Drop Time Test Results (Typical)

Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-2 Sheet 3 - Rod Cluster Control Assembly Drop Time Test Results (Typical)

Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-2 Sheet 4 - Rod Cluster Control Assembly Drop Time Test Results (Typical)

Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-3 Partial-Length Rods Operation Test Results (Typical)

Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-4 Sheet 1 - Radiation Monitoring System Operational Test Data Sheet (Typical)

Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-4 Sheet 2 - Radiation Monitoring System Operational Test Data Sheet (Typical)

Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-5 Pressurizer Safety Valve Test Data Sheet Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-6 Reactor Vessel Internals Displacement Indicators Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-7 Sheet 1 - Reactor Vessel Accelerometers Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-7 Sheet 2 - Reactor Vessel Accelerometers Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-7 Sheet 3 - Reactor Vessel Accelerometers Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-7 Sheet 4 - Reactor Vessel Accelerometers Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-8 Sheet 1 - Reactor Coolant System Vibration Test Data Sheet Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-8 Sheet 2 - Reactor Coolant System Vibration Test Data Sheet Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-9 Sheet 1 - Reactor Coolant Pump Flow Coastdown Test Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-9 Sheet 2 - Reactor Coolant Pump Flow Coastdown Test Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-9 Sheet 3 - Reactor Coolant Pump Flow Coastdown Test Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-9 Sheet 4 - Reactor Coolant Pump Flow Coastdown Test Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-9 Sheet 5 - Reactor Coolant Pump Flow Coastdown Test Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-10 Sheet 1 - Natural Circulation Test Data Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-10 Sheet 2 - Natural Circulation Test Data Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-11 Preoperational Containment Leak Rate Test Data Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-12 Preoperational Containment Leak Rate Test, Pressurization System Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-13 Sheet 1 - 50% Load Reduction From 75% Power Level Test, Recorded Process Variables Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-13 Sheet 2 - 50% Load Reduction From 75% Power Level Test, Recorded Process Variables Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-13 Sheet 3 - 50% Load Reduction From 75% Power Level Test, Recorded Process Variables Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-13 Sheet 4 - 50% Load Reduction From 75% Power Level Test, Recorded Process Variables Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-13 Sheet 5 - 50% Load Reduction From 75% Power Level Test, Recorded Process Variables Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-14 Operational Dynamic Rod Drop Test, Nuclear Power Channel Signals Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-15 Ginna 1520 Megawatts Power Test Program, March 1 Through April 15, 1972 Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-16 Ginna Uprating, Control Bank D Differential and Integral Worth, Cycle 1B 7800 MWd/MTU, Hot Zero Power Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-17 Ginna Uprating, Control Bank C Differential and Integral Worth, Cycle 1B 7800 MWd/MTU, Hot Zero Power Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-18 Ginna Uprating, Boron Concentration Versus Reactivity Insertion, Cycle 1B 7800 MWd/MTU, Hot Zero Power Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-19 Ginna Uprating, Isothermal Temperature Coefficient Versus Boron Concentra-tion, Cycle 1B 7800 MWd/MTU, Hot Zero Power Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-20 Relative Power During Uprating: 1300, 1380, 1455 MWt Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-21 Relative Power During Uprating: 1455 MWt Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-22 Ginna Uprating, Power Range Output Versus Core Power, Channel NE41 Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-23 Ginna Uprating, Axial Offset Calibration, Channel 41 Output Normalized to 1520 MWt Revision 26 5/2016

GINNA/UFSAR CHAPTER 14 INITIAL TEST PROGRAM Figure 14.6-24 Relative Power at 1520 MWt, April 12, 1972 Revision 26 5/2016