MONTHYEARIR 05000244/20243012024-10-22022 October 2024 Initial Operator Licensing Examination Report 05000244/2024301 ML24286A0022024-10-11011 October 2024 Core Operating Limits Report Cycle 45, Revision 0 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing RS-24-092, Revised Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-09-25025 September 2024 Revised Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000244/20245012024-09-24024 September 2024 LLC - Emergency Preparedness Biennial Exercise Inspection Report 05000244/2024501 IR 05000244/20240052024-08-29029 August 2024 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant (Report 05000244/2024005) ML24234A0922024-08-21021 August 2024 Requalification Program Inspection IR 05000244/20240102024-08-19019 August 2024 Biennial Problem Identification and Resolution Inspection Report 05000244/2024010 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000244/20240022024-08-0505 August 2024 LLC - Integrated Inspection Report 05000244/2024002 and Independent Spent Fuel Storage Installation Report 07200067/2024001 ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) ML24170A3852024-07-16016 July 2024 R. E. Ginna Nuclear Power Plant - Alternative Associated with Inservice Testing of B Auxiliary Feedwater Pump - PR-03 ML24197A0302024-07-15015 July 2024 LLC - Operator Licensing Examination Approval RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions IR 05000244/20244022024-06-20020 June 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000244/2024402 RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24143A0752024-05-22022 May 2024 Re. Ginna Nuclear Power Plant and Independent Spent Fuel Storage Installation (ISFSI) Registration for Use of General License ISFSI Casks ML24136A1692024-05-14014 May 2024 And Independent Spent Fuel Storage Installation (ISFSI) - 2023 Annual Radioactive Effluent Release Report and 2023 Annual Radiological Environmental Operating Report ML24134A0042024-05-13013 May 2024 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000244/2024010 RS-24-049, Updated Notice of Intent to Pursue Subsequent License Renewal Applications2024-05-0909 May 2024 Updated Notice of Intent to Pursue Subsequent License Renewal Applications RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests IR 05000244/20240012024-04-24024 April 2024 LLC - Integrated Inspection Report 05000244/2024001 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24101A0432024-04-10010 April 2024 2024 10 CFR 50.46 Annual Report IR 05000244/20240112024-04-10010 April 2024 LLC - Fire Protection Team Inspection Report 05000244/2024011 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24088A2042024-03-28028 March 2024 R. E. Ginna Nuclear Power Plant - Response to NRC Request for Additional Information Regarding Relief Request Associated with Inservice Testing of ‘B’ Auxiliary Feedwater Pump ML24110A0122024-03-28028 March 2024 2023 Report of Individual Monitoring for R.E. Ginna Nuclear Power Plant LLC, License DPR-18 05000244/LER-2023-003-01, Re. Ginna Nuclear Power Plant, Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam2024-03-0707 March 2024 Re. Ginna Nuclear Power Plant, Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam IR 05000244/20230062024-02-28028 February 2024 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC, (Report 05000244/2023006) IR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 ML24026A0112024-01-26026 January 2024 R. E. Ginna Nuclear Power Plant, Relief Request Associated with Inservice Testing of ‘B’ Auxiliary Feedwater Pump IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 ML23348A0992023-12-15015 December 2023 R. E. Ginna Nuclear Power Plant – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0029 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23347A0092023-12-13013 December 2023 Annual Commitment Change Notification ML23346A0142023-12-12012 December 2023 LLC - Senior Reactor and Reactor Operator Initial License Examinations 05000244/LER-2023-003, Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam Generator Level2023-12-11011 December 2023 Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam Generator Level ML23341A1252023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements ML23321A1392023-11-17017 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information and Request for Additional Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums 05000244/LER-2023-002, Overtemperature Delta Temperature Reactor Protection System and Auxiliary Feedwater System Actuations on Due to 100% Load Rejection Caused by Turbine Overspeed Circuit Card Failure2023-11-0808 November 2023 Overtemperature Delta Temperature Reactor Protection System and Auxiliary Feedwater System Actuations on Due to 100% Load Rejection Caused by Turbine Overspeed Circuit Card Failure. IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 ML23292A0282023-10-19019 October 2023 LLC - Notification of Conduct of a Fire Protection Team Inspection RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23258A1382023-09-18018 September 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000244/2023010 IR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) 2024-09-25
[Table view] |
Text
200 Exelon Way Kennett Square, PA 19348
www.constellation.com
10 CFR 50.90
June 9, 2022
U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555- 0001
R. E. Ginna Nuclear Power Plant Renewed Facility Operating License No. DPR-18 NRC Docket No. 50-244
Subject:
Supplemental Information for R.E. Ginna Nuclear Power Plant to Adopt TSTF-5 05, "Provide Risk-I nformed Extended Completion Times - RITSTF Initiative 4b," Revision 2
References:
- 1. Letter from D. Gudger (Exelon Generation Company, LLC) to U.S. Nuclear Regulatory Commission, "License Amendment Request to Revise Technical Specific ations to Adopt Risk-I nformed Completion Times TSTF-505, Revision 2, 'Provide Risk-I nformed Extended Completion Times -
RITSTF Initiative 4b,' " dated May 20, 2021 (ML2 1140A3 24)
- 2. Letter from D. Gudger (Exelon Generation Company, LLC) to U.S. Nuclear Regulatory Commission, Supplemental Information No. 1 for R.E. Ginna Nuclear Power Plant to Adopt TSTF-5 05, "Provide Risk -Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 and 10 CFR 5 0.69,
'Risk-I nformed categoriz ation and treatment of structures, systems and components for nuclear power reactors.' " dated October 14, 2021 (ML21287A006)
This le tter is a supplement t o Reference 1. Exelon Generation Company, LLC ( Exelon) proposed an am endment to ch ange the R. E. Ginna Nuclear P ower P lant (Ginna) Tech nical Specification (TS). The proposed amendment would modify TS requirements to permit the use of Risk Informed Completion Times in accordance with TSTF-5 05, Revision 2, "Provide Risk-I nformed Extended Completion Times - RITSTF Initiative 4b," (ADAMS Ac cession No.
ML21140A 324). By l etter da ted October 14, 2021 ( Reference 2), Exel on provided supplemental informatio n to the proposed a mendment (Reference 1). Attachment 3 of Reference 2 provides a s uggest ed license condition. This letter provides clarification on t he proposed license condition and supersedes w hat w as p rovided in Attachment 3 o f Reference 2.
U.S. Nuclear Regulatory Comm ission Supplemental Information for TSTF-5 05 Docket No. 50-2 44 June 9, 2022 Page 2
Constellation Energy Generation, LLC (CEG) has reviewed the information supporting a finding of no significant hazards consideration and the environmental consideration provided to the NRC in Reference 1. The responses provided in this letter do not affect the bases for concluding that the proposed license amendment does not involve a significant hazards consideration. Furthermore, the re sponses provided in this l etter do not affect the bases for concluding that neither an environmental impact statement nor an environmental assessment needs to be prepared in connection with the proposed amendment.
CEG also requests ADAMS for immediate release marked as a publicly available document.
There are no commitments contained in this response.
In accordance with 10 CFR 50.91, " Notice for public comment; State consultation,"
paragraph (b), EGC is notifying the State of New York of this application for license amendment by transmitting a copy of this letter and its attachments to the designated State Official.
Should you have any questions concerning this letter, please contact Jessie Hodge at (610) 765-55 32.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 9 th day of June 2022.
Respectfully,
David T. Gudger Senior Manager - Licensing Constellation Energy Generation, LLC
Attachments: 1. License C ondition Information
cc: USNRC Region I, Regional Administrator w/ attachments USNRC Senior Resident Inspector, Ginna "
USNRC Project Manager, Ginna "
A. L. Peterson, NYSERDA "
ATTACHMENT 1
License Amendment Request
R. E. Ginna Nuclear Power Plant
Renewed Facility Operating License No. DPR-18
Docket No. 50- 244
License Condition Information Supplemental Attachment 1 Information for Page 1 of 1 TSTF-5 05 Docket No. 50-2 44
Constellation proposes the addition of the following condition to the renewed operating license of Ginna to document the NRCs approval of the use of Risk -Informed Completion Times TSTF 505, Revision 2, Provide Risk Informed Extended Completion Times RITSTF Initiative 4b
Constellation Energy Generation, LLC is approved to implement TSTF-505, Revision 2, modifying the Technical Specification requirements related to Completion Times (CT) for Required Actions to provide the option to calculate a longer, R isk-Informed CT (RICT). The methodology for using the new Risk-Informed Completion Time Program is described in NEI 06- 09-A, Risk -Informed Technical Specifications Initiative 4b, Risk-Managed Technical Specifications (RMTS) Guidelines, Revision 0, which was approved by the NRC on May 17, 2007.
Constellation Energy Generation, LLC will complete the implementation items listed in Attachment 6 of Exelon Letter to the NRC dated May 20, 2021, prior to implementation of the RICT Program. All issues identified in the attachment will be addressed and any associated changes will be made, focused-scope peer reviews will be performed on changes that are PRA upgrades as defined in the PRA standard (ASME/ANS RA-Sa-2009, as endorsed by RG 1.200, Revision 2), and any findings will be resolved and reflected in the PRA of record prior to the implementation of the RICT Program.