Entergy Presentation Slides for Pre-Submittal Meeting on 10/24/23, Mtc LAR
ML23296A100
Person / Time
Site: Arkansas Nuclear, Waterford  Entergy icon.png
Issue date: 10/24/2023
From:
Entergy Operations
To: Lingham S
NRC/NRR/DORL/LPL4
Wengert T
References
EPID L-2023-LRM-0081
Download: ML23296A100 (1)


Text

Arkansas Nuclear One Unit 2 Waterford 3 Pre-Submittal Meeting to Adopt Moderator Temperature Coefficient Tech Spec Change October 24, 2023

Agenda

  • Background
  • Current Requirements
  • Proposed Changes
  • Discussion of the Change
  • Precedent
  • Timeline for Submittal
  • Open Discussion 2

Background

  • Arkansas Nuclear One Unit 2 (ANO2) and Waterford 3 (WF3) have Technical Specifications (TS) based on NUREG-0212.
  • The NUREG-0212 Technical Specifications provide more information than is generally contained in the Improved Standard Technical Specification (ISTS).
  • The TS typically do not specify how a surveillance should be performed, only that a parameter should be within limits.
  • The TS do not specify references to specific topical reports that are used.
  • The proposed License Amendment Request (LAR) will more closely align the ANO2 and WF3 Moderator Temperature Coefficient (MTC) TSs with the structure in NUREG-1432.

3

Current Requirements - ANO2 ANO2 MTC Technical Specification is documented in TS 3.1.1.4

  • The Limiting Condition for Operation (LCO) for ANO2 is similar to the ISTS in function with some minor wording differences.
  • The current applicability includes a footnote (*) for Keff 1.0 in MODE 2.
  • The current end state mode in the Action statement is referred to by name.

4

Current Requirements - ANO2 ANO2 MTC Technical Specification is documented in TS 3.1.1.4.

  • The surveillance requirement (SR) states that MTC shall be confirmed by measurement.
  • SR 4.1.1.4.2 specifies that the surveillance is performed prior to and above 5% rated thermal power (RTP).

5

Current Requirements - ANO2 ANO2 MTC Technical Specification is documented in TS 3.1.1.4.

6

Current Requirements - WF3 WF3 MTC Technical Specification is documented in TS 3.1.1.3.

  • The LCO for WF3 is similar to the ISTS in function with some minor wording differences.
  • The current applicability includes a footnote (1) for Keff 1.0 in MODE 2.
  • The current end state mode in the Action statement is referred to by name.

7

Current Requirements - WF3 WF3 MTC Technical Specification is documented in TS 3.1.1.3.

  • The SR states that MTC shall be confirmed by measurement.
  • SR 4.1.1.3.2 specifies that the surveillance is performed prior to 5% RTP, greater than 15%,

and at any power.

8

Current Requirements - WF3 WF3 MTC Technical Specification is documented in TS 3.1.1.3.

9

Proposed Changes ANO2 and WF3 will adopt the structure of the ISTS (ANO2 example is shown).

10

Discussion of the Change

  • Current SRs are structured using NUREG-0212. This structure specifies a specific surveillance procedure will be used to verify the MTC.
  • Current SRs contain the word measured, which precludes using another procedure to verify that the surveillances are met.
  • Revising the wording in SRs from measured to verified is consistent with the ISTS.
  • Using the word verified will allow the use of other procedures to verify the surveillances are met.

11

Discussion of the Change

  • The industry has worked on several initiatives to reduce the number of times that MTC is measured in the plant.
  • The STP LAR provided a specific procedure that would be used to verify MTC.
  • Entergy is not requesting approval of a new procedure that will be used to verify MTC.
  • At this time, Entergy is not making any change to the procedure that is used to verify the MTC.
  • Future changes to the surveillance procedures will be assessed in accordance with 10 CFR 50.59.

12

Precedent NUREG-1432, Standard Technical Specifications for Combustion Engineering Plants.

13

Timeline for Submittal

  • Submittal to NRC - 1st quarter 2024
  • Requesting normal NRC approval schedule 14

CLOSING REMARKS 15