MONTHYEARML24250A1132024-09-0303 September 2024 Inspection Report 2024004 Radiation Safety Baseline Inspection Information Request IR 05000424/20240052024-08-26026 August 2024 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 and 2 - Report 05000424/2024005 and 05000425/2024005 ML24235A1952024-08-22022 August 2024 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 3 and 4 - Report 05200025/2024005 and 05200026/2024005 ML24163A0632024-06-12012 June 2024 2024 Licensed Operator Re-qualification Inspection Notification Letter Vogtle, Units 3 & 4 ML24107A7292024-04-15015 April 2024 Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection - Inspection Report 2024-02 ML24053A3562024-02-28028 February 2024 Annual Assessment Letter for Vogtle Electric Generating Plant, Unit 3 & 4 (Report 05200025/2023006 & 05200026/2023006) IR 05000424/20230062024-02-28028 February 2024 Annual Assessment Letter for Vogtle Electric Generating Plant Units 1 and 2 - NRC Inspection Report 05000424-2023006 and 05000425-2023006 ML23291A1512023-10-18018 October 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 0520026/2024401 ML23243A0092023-08-31031 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 3 & 4 (Report 05200025 2023005 & 05200026 2023005) IR 05000424/20230052023-08-29029 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 & 2 - Report 05000424/2023005 and 05000425/2023005 ML23220A0572023-07-26026 July 2023 Document Request for Vogtle Units 1 and 2 - Radiation Protection Inspection - Inspection Report 2023-03 ML23199A1472023-07-19019 July 2023 (Vegp), Unit 4 - Transition to the Operating Reactor Assessment Program (NRC Report 05200026/2023010) IR 05000424/20220062023-03-0101 March 2023 Annual Assessment Letter for Vogtle Electric Generating Plant Units 1 and 2, NRC Inspection Reports 05000424/2022006 and 05000425/2022006 ML23053A1342023-03-0101 March 2023 Annual Assessment Letter for Vogtle Electric Generating Plant, Unit 4 NRC Report 05200026/2022009 ML23058A2292023-03-0101 March 2023 Annual Assessment Letter for Vogtle Electric Generating Plant, Unit 3 (Report 05200025/2022012) ML23003A1682022-11-10010 November 2022 Notification of Vogtle Commercial Grade Dedication Inspection IR 05000424/20220052022-08-24024 August 2022 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 & 2 - Report 05000424/2022005 and 05000425/2022005 ML22188A1712022-07-29029 July 2022 (VEGP) Unit 3 - Transition to the Operating Reactor Assessment Program (NRC Report 05200025/2022009) IR 05000424/20210062022-03-0202 March 2022 Annual Assessment Letter for Vogtle Electric Generating Plant Units 1 and 2 (Report No 05000424/2021006 and 05000425/2021006) ML22054A3232022-03-0202 March 2022 Annual Assessment Letter for Vogtle Electric Generating Plant Units 3 and 4 - NRC Report 05200025/2021012 and 05200026/2021012 ML21120A0082021-04-29029 April 2021 Requalification Program Inspection Vogtle Nuclear Plant IR 05000424/20190112021-04-0707 April 2021 Biennial Problem Identification and Resolution Inspection Report 05000424/2019011 and 05000425/2021010 ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 IR 05000424/20200062021-03-0303 March 2021 Annual Assessment Letter for Vogtle Electric Generating Plant, Units 1 & 2 - Report 05000424/2020006 and 05000425/2020006 IR 05000424/20200112020-10-26026 October 2020 NRC Triennial Fire Protection Inspection Report 05000424/2020011 and 05000425/2020011 ML20063L6052020-03-0303 March 2020 Annual Assessment Letter for Vogtle Electric Generating Plant Units 3&4 (NRC Report 05200025/2019-006 and 05200025/2019-006) IR 05000424/20190062020-03-0303 March 2020 Annual Assessment Letter for Vogtle Electric Generating Plant, Units 1 & 2 - Report 05000424/2019006 and 05000425/2019006 IR 05000424/20190052019-08-27027 August 2019 Updated Inspection Plan for Vogtle Electric Generating Plant Reports 05000424/2019005 and 05000425/2019005 ML19123A1382019-05-0303 May 2019 Occupational Radiation Safety Baseline Inspection 2019002 Document Request ML19065A3072019-03-0606 March 2019 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000424/20180062019-03-0404 March 2019 Annual Assessment Letter for Vogtle Electric Generating Plant - Report 05000424/2018006 and 05000425/2018006 ML19063D3462019-03-0404 March 2019 Annual Assessment Letter for Vogtle Electric Generating Plant Units 3 & 4 (NRC Report 05200025/2018006 and 05200026/2018006) ML19030A7392019-01-28028 January 2019 RFI IR 05000424/20180052018-08-23023 August 2018 Updated Inspection Plan for Vogtle Electric Generating Plant Units 1 and 2 - NRC Inspection Reports 05000424/2018005 and 05000425/2018005 ML18215A1242018-08-0303 August 2018 Radiation Safety Baseline Inspection RFI 2018004 (Public) ML18082A0612018-03-20020 March 2018 Emergency Preparedness Inspection and Request for Information ML18059A7212018-03-0202 March 2018 Annual Assessment Letter for Vogtle Electric Generating Plant Units 2 and 3 (NRC Report 05200025/2017005 and 05200026/2017005 ML18059A1672018-02-28028 February 2018 EOC Assessment Letter IR 05000424/20170052017-08-28028 August 2017 Updated Inspection Plan NRC Inspection Report 05000424/2017005 and 05000425/2017005 ML17233A2492017-08-17017 August 2017 Notification of Inspection Report and Request for Information ML17143A3262017-05-19019 May 2017 Requalification Program Inspection 05000424/2017002 and 05000425/2017002 IR 05000424/20160062017-03-0101 March 2017 Annual Assessment Letter for Vogtle Electric Generating Plant, Units 1 and 2 (Report 05000424/2016006 and 05000425/2016006) IR 05000424/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Vogtle Electric Generating Plant Units 1 and 2 - NRC Inspection Report 05000424/2016005 and 05000425/2016005 IR 05000424/20150062016-03-0202 March 2016 Annual Assessment Letter for Vogtle Electric Generating Plant Unit 1 and Unit 2 (Report 05000424/2015006 and 05000425/2015006) ML16032A0382016-01-29029 January 2016 Vogtle Electric Generating Plant, Unit 2, Notification Of Inspection and Request for Information ML16008A1462016-01-0808 January 2016 Vogtle Electric Generating Plant Emergency Preparedness Inspection and Request for Information ML16008A1202016-01-0808 January 2016 Vogtle Electric Generating Plant - Notification of Inspection and Request for Information IR 05000424/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Vogtle Electric Generating Plant Units 1 and 2 (Inspection Report No. 05000424/2015005 and 05000425/2015005 ML15110A0332015-04-17017 April 2015 Notification of Conduct of a Triennial Fire Protection Baseline Inspection, U. S. Nuclear Regulatory Commission Inspection Report Nos. 05000424/2015007 and 05000425/2015007 IR 05000424/20140012015-03-0404 March 2015 Annual Assessment Letter for Vogtle Electric Generating Plant Unit 1 and Unit 2 (NRC Inspection Report 05000424/2014001 and 05000425/2014001) 2024-09-03
[Table view] Category:Letter
MONTHYEARML24297A6482024-10-23023 October 2024 5 to the Updated Final Safety Analysis Report, Technical Specification Bases Changes, Technical Requirements Manual Changes, Summary Report and Revised NRC Commitments Report ML24269A2502024-09-26026 September 2024 Acknowledgement of the Withdrawal of the Requested Exemption and License Amendment Request to Remove Tier 1 and Tier 2* Requirements NL-24-0350, Core Operating Limits Report, Cycle 24, Version 22024-09-25025 September 2024 Core Operating Limits Report, Cycle 24, Version 2 NL-24-0369, Withdrawal of License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2 Requirements2024-09-25025 September 2024 Withdrawal of License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2 Requirements ML24243A0072024-09-10010 September 2024 – Correction of Amendment Nos. 223 and 206 Regarding Revision to Technical Specifications to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-14483 NL-24-0337, Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program2024-09-0909 September 2024 Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program ML24102A2642024-09-0909 September 2024 – Exemption Request Regarding Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0013) - Letter ML24249A2942024-09-0606 September 2024 Correction of Amendment Nos. 218 and 201 Regarding Revision to Technical Specifications to Use Online Monitoring Methodology 05200025/LER-2024-002, Manual Reactor Protection System and Automatic Safeguards Actuation Due to an Unexpected Change in Position of a Main Feedwater Pump Minimum Flow Control Valve2024-09-0505 September 2024 Manual Reactor Protection System and Automatic Safeguards Actuation Due to an Unexpected Change in Position of a Main Feedwater Pump Minimum Flow Control Valve IR 05000424/20240052024-08-26026 August 2024 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 and 2 - Report 05000424/2024005 and 05000425/2024005 ML24235A1952024-08-22022 August 2024 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 3 and 4 - Report 05200025/2024005 and 05200026/2024005 IR 05000424/20244012024-08-15015 August 2024 4 - Security Baseline Inspection Report 05000424-2024401, 05000425-2024401, 05200025-2024402, and 05200026-2024403 - Cover Letter NL-24-0299, Exemption Request: Final Safety Analysis Report Update Schedule, Response to Request for Additional Information2024-08-14014 August 2024 Exemption Request: Final Safety Analysis Report Update Schedule, Response to Request for Additional Information 05000425/LER-2024-001, Manual Actuation of the Reactor Protection System Due to a Rod Control Fuse Opening Causing a Misaligned Shutdown Rod2024-08-0909 August 2024 Manual Actuation of the Reactor Protection System Due to a Rod Control Fuse Opening Causing a Misaligned Shutdown Rod ML24218A1842024-08-0707 August 2024 Examination Report and Cover Letter 05200026/LER-2024-001, Manual Reactor Protection System Actuation Due to Procedure Not Optimally Sequenced to Reset the Rapid Power Reduction Signal2024-08-0606 August 2024 Manual Reactor Protection System Actuation Due to Procedure Not Optimally Sequenced to Reset the Rapid Power Reduction Signal ML24212A1442024-08-0101 August 2024 Integrated Inspection Report 05200025/2024002 and 05200026/2024002 IR 05000424/20240022024-07-29029 July 2024 Integrated Inspection Report 05000424/2024002 and 05000425/2024002 IR 05000424/20244042024-07-26026 July 2024 Material Control and Accounting Program Inspection Report 05000424/2024404 and 05000425/2024404 (Cover Letter) NL-24-0282, License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2* Requirements2024-07-25025 July 2024 License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2* Requirements NL-24-0126, – Units 3 and 4, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Action a and SR 3.7.6.62024-07-25025 July 2024 – Units 3 and 4, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Action a and SR 3.7.6.6 ML24204A0722024-07-23023 July 2024 Issuance of Amendment No. 225, Regarding LAR to Revise TS 3.7.9 for a one-time Change to Support Nuclear Service Cooling Water Transfer Pump Repairs - Emergency Circumstances NL-24-0286, Emergency Request to Revise Technical Specification 3.7.9 for a One-Time Change to Support a Unit 1 Nuclear Service Cooling Water Transfer Pump Repair2024-07-20020 July 2024 Emergency Request to Revise Technical Specification 3.7.9 for a One-Time Change to Support a Unit 1 Nuclear Service Cooling Water Transfer Pump Repair ML24191A4562024-07-19019 July 2024 Request for Relief and Alternative Requirements for Squib (Explosively Actuated) Valves First Test Interval NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 ML24194A0342024-07-12012 July 2024 Review of the Refueling Outage 1R24 Steam Generator Tube Inspection Report ML24191A3792024-07-10010 July 2024 – Initial Test Program and Operational Programs Inspection Report 05200026/2024011 NL-24-0227, Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2024-07-0303 July 2024 Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) NL-24-0234, Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown2024-06-28028 June 2024 Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in NL-24-0087, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks2024-06-21021 June 2024 License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks NL-24-0201, Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2024-06-18018 June 2024 Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) NL-24-0243, Registration of Spent Fuel Cask Use2024-06-18018 June 2024 Registration of Spent Fuel Cask Use ML24163A0632024-06-12012 June 2024 2024 Licensed Operator Re-qualification Inspection Notification Letter Vogtle, Units 3 & 4 ML24155A1772024-06-0505 June 2024 Regulatory Audit in Support of Review of the LAR to Revise Emergency Diesel Generator Frequency and Voltage Ranges for Technical Specification 3.8.1, Surveillance Requirements NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24094A1402024-05-16016 May 2024 Staff Response to Request for Revision to NRC Staff Assessment of Updated Seismic Hazard Information and Latest Understanding of Seismic Hazards at the Vogtle Plant Site Following the NRC Process for the Ongoing Assessment of Natural Hazard ML24130A2412024-05-13013 May 2024 Integrated Inspection Report 05200025/2024001 and 05200026/2024001 ML24120A1812024-05-13013 May 2024 Request for Withholding Information from Public Disclosure Responses to NRC Request for Additional Information for Refueling Outage IR24 Steam Generator Tube Inspection Report – Enclosure 2 ML24101A2112024-05-11011 May 2024 Expedited Issuance of Amendment No. 198 Change to Technical Specification 5.5.13, Ventilation Filter Testing Program (VFTP) NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 ML24127A2372024-05-0909 May 2024 Initial Test Program and Operational Programs Inspection Report 05200026/2024010 NL-24-0194, Revised Request for Relief and Alternative Requirements for Squib Valves First Test Interval (V34-IST-ALT-03-R1)2024-05-0707 May 2024 Revised Request for Relief and Alternative Requirements for Squib Valves First Test Interval (V34-IST-ALT-03-R1) IR 05000424/20244032024-05-0101 May 2024 Cyber Security Inspection Report 05000424/2024403 and 05000425/2024403 Public ML24120A2832024-04-30030 April 2024 Project Manager Reassignment NL-24-0170, Responses to Second Round NRC Request for Additional Information for Refueling Outage 1 R24 Steam Generator Tube Inspection Report2024-04-25025 April 2024 Responses to Second Round NRC Request for Additional Information for Refueling Outage 1 R24 Steam Generator Tube Inspection Report NL-24-0165, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20232024-04-25025 April 2024 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2023 IR 05000424/20240012024-04-23023 April 2024 –Integrated Inspection Report 05000424/2024001 and 05000425/2024001 NL-24-0154, Preservice Inspection Progam Owners Activity Report2024-04-16016 April 2024 Preservice Inspection Progam Owners Activity Report 2024-09-09
[Table view] |
Text
March 1, 2023 Jamie Coleman Regulatory Affairs Director Southern Nuclear Company 7825 River Road, BIN 63031 Waynesboro, GA 30830
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR VOGTLE ELECTRIC GENERATING PLANT, UNIT 3 (REPORT 05200025/2022012)
Dear Ms. Coleman:
The NRC has completed its end-of-cycle performance assessment of Vogtle Electric Generating Plant, Unit 3, reviewing performance indicators (PIs), inspection results, and enforcement actions from August 3, 2022, through December 31, 2022. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC concluded that overall performance at your facility preserved public health and safety.
The baseline inspection program was completed at your facility in accordance with Section IV.B of the Transition to the Reactor Oversight Process for Vogtle Electric Generating Plant, Units 3
& 4 memo (ML20191A383).
The NRC determined the performance at Vogtle Electric Generating Plant, Unit 3 during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2024.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In response to the COVID-19 public health emergency (PHE), the NRC adjusted inspection plans and schedules to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. While the PHE continues, overall conditions throughout the country support performance of our inspection and oversight activities returning to normal onsite presence by our resident and region-based inspectors and completion of nominal baseline inspection samples.
J. Coleman 2 We continue to monitor site-specific conditions and, as discussed in our November 2, 2021, memo, Implementation of Inspection Programs Following Re-Entry from the Public Health Emergency for the Reactor Safety Program (ML21295A302), it may be necessary to alter how and when we perform our inspection and oversight activities as we balance the importance of protecting the health and safety of our staff with the need to conduct effective oversight that supports the NRCs critical safety mission.
For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.
Beginning on January 1, 2023, the engineering inspection frequency will transition from a triennial (3-year) to a quadrennial (4-year) cycle. The new engineering inspection program will consist of a Comprehensive Engineering Team Inspection (CETI)1 and three Focused Engineering Inspections (FEIs) that will be performed in each quadrennial cycle. For the cycle beginning in 2023, the FEIs will be: Fire Protection Team Inspection, Commercial Grade Dedication and an engineering inspection that reviews age-related degradation and management2.
1 Aspects of the Design Basis Assurance Inspection (DBAI), Evaluations of Changes, Tests, & Experiments, and Heat Sink inspections will be included in the new CETI inspection. Previously scheduled Evaluation of Changes, Tests, & Experiments and Heat Sink inspections have been cancelled and removed from attached Report 22.
2 The Age-Related Degradation procedure is publicly, and the NRC plans to implement the first inspection of this type beginning in July 2023.
J. Coleman 3 In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 404-997-4428 with any questions you have regarding this letter.
Sincerely, Signed by Davis, Bradley on 03/01/23 Bradley J. Davis, Chief Construction Inspection Branch 2 Division of Construction Oversight Docket No. 05200025 License No. NPF-92
Enclosure:
Vogtle Unit 3 Inspection/Activity Plan cc w/ encl: Distribution via LISTSERV
ML23058A229 X SUNSI Review X Non-Sensitive X Publicly Available Sensitive Non-Publicly Available OFFICE RII/DCO RII/DCO NAME C. Even B. Davis DATE 02/27/23 03/01/23 Site Inspection Activity Plan Vogtle 3 03/01/2023 - 12/31/2024 Unit Start End Activity CAC Title Staff Count CYBER SECURITY INSPECTION 4 3 3/13/2023 3/17/2023 IP 81000.09 001465 Cyber Security Inspection for Construction EMERGENCY PREPAREDNESS PROGRAM INSPECTION 2 3 4/10/2023 4/14/2023 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 3 4/10/2023 4/14/2023 IP 71151 001397 Performance Indicator Verification BASELINE SECURITY INSPECTION 1 3 5/15/2023 8/18/2023 IP 71130.02 000734 Access Control 3 5/15/2023 8/18/2023 IP 71130.09 001656 Security Plan Changes 3 5/15/2023 8/18/2023 IP 71151 001338 Performance Indicator Verification TARGET SET INSPECTION 2 3 6/5/2023 6/9/2023 IP 71130.14 000743 Review of Power Reactor Target Sets RP OCCUPATIONAL RADIATION SAFETY BASELINE INSPECTION 2 3 8/14/2023 8/18/2023 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 3 8/14/2023 8/18/2023 IP 71124.05 000729 Radiation Monitoring Instrumentation SECURITY BASELINE INSPECTION 2 3 10/23/2023 10/27/2023 IP 71130.01 000733 Access Authorization 3 10/23/2023 10/27/2023 IP 71130.06 000738 Protection of Safeguards Information 3 10/23/2023 10/27/2023 IP 71130.08 000740 Fitness For Duty Program FOCUSED ENGINEERING INSPECTION (FIRE PROTECTION) 4 3 1/22/2024 1/26/2024 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI) 3 2/5/2024 2/9/2024 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
PROBLEM IDENTIFICATION & RESOLUTION 3 3 2/26/2024 3/1/2024 IP 71152B 000747 Problem Identification and Resolution CYBER SECURITY INSPECTION 2 3 3/25/2024 3/29/2024 IP 71130.10 000741 Cybersecurity UNIT 3 IN-SERVICE INSPECTION +SG 2 3 5/20/2024 5/24/2024 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
EMERGENCY PREPAREDNESS EXERCISE INSPECTION 5 3 5/20/2024 5/24/2024 IP 71114.01 000716 Exercise Evaluation 3 5/20/2024 5/24/2024 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes SECURITY BASELINE INSPECTION 2 3 5/20/2024 5/24/2024 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 3 5/20/2024 5/24/2024 IP 71130.07 000739 Security Training Enclosure
Site Inspection Activity Plan RP RAD SAFETY PUBLIC BASELINE INSPECTION 3 3 6/10/2024 6/14/2024 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 3 6/10/2024 6/14/2024 IP 71124.07 000731 Radiological Environmental Monitoring Program 3 6/10/2024 6/14/2024 IP 71151 000746 Performance Indicator Verification SECURITY BASELINE INSPECTION 2 3 7/29/2024 8/8/2024 IP 71130.02 000734 Access Control 3 7/29/2024 8/8/2024 IP 71130.09 001656 Security Plan Changes SECURITY BASELINE INSPECTION 3 3 10/21/2024 10/25/2024 IP 71130.05 000737 Protective Strategy Evaluation 2