EPID:L-2017-FPR-0074, Yankee Atomic Electric Company - Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan (Open) |
|
MONTHYEARML22010A0122022-01-10010 January 2022 Yankee Atomic Electric Company - Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan Project stage: Request ML22237A0632022-08-0303 August 2022 Yankee Atomic Electric Company - Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan Project stage: Request ML22340A4752023-02-24024 February 2023 Closeout Letter to Yankee Atomic Electric Company Regarding 2018 and 2021 Updated DFPs for Yankee Nuclear Power Station ISFSI Project stage: Other 2022-08-03
[Table View] |
|
---|
Category:Decommissioning Funding Plan DKTs 30
MONTHYEARML23080A1072023-03-0606 March 2023 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML22237A0632022-08-0303 August 2022 Yankee Atomic Electric Company - Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML22082A1232022-03-14014 March 2022 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML22010A0122022-01-10010 January 2022 Yankee Atomic Electric Company - Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML21105A7382021-03-0202 March 2021 Yankee Nuclear Power Station Independent Sperit Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML19116A0502019-03-12012 March 2019 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation Decommissioning Funding Assurance Status Report ML18354A7382018-12-10010 December 2018 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Three-Year Update to the Decommissioning Funding Plan ML18075A3252018-03-0505 March 2018 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML16076A2742016-03-0909 March 2016 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML16020A0162015-12-14014 December 2015 Yankee ISFSI - Three-Year Update to the Decommissioning Funding Plan ML15131A0252015-03-0303 March 2015 Yankee and Independent Spent Fuel Storage Installation (ISFSI) - Decommissioning Funding Assurance Status Report ML13094A1162013-03-25025 March 2013 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML12363A1062012-12-17017 December 2012 Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML1210706332012-03-27027 March 2012 Redacted - Yankee, Decommissioning Funding Assurance Status Report - 10CFR 50.75 ML1007504532010-03-0909 March 2010 Yankee Atomic, Decommissioning Funding Assurance Status Report - 1OCFR 50.75 ML0409704532004-03-31031 March 2004 Yankee, Decommissioning Funding Assurance - 10CFR50.75(f) ML0210200492002-03-29029 March 2002 Submittal of Decommissioning Funding Assurance for the Yankee Nuclear Power Station 2023-03-06
[Table view] Category:40
MONTHYEARML23080A1072023-03-0606 March 2023 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML22237A0632022-08-0303 August 2022 Yankee Atomic Electric Company - Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML22082A1232022-03-14014 March 2022 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML22010A0122022-01-10010 January 2022 Yankee Atomic Electric Company - Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML21287A1012021-10-0404 October 2021 Yankee Atomic Electric Company - Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Biennial Update to the Yankee Nuclear Power Station License Termination Plan ML21105A7382021-03-0202 March 2021 Yankee Nuclear Power Station Independent Sperit Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML20108F5362020-03-12012 March 2020 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML19116A0502019-03-12012 March 2019 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation Decommissioning Funding Assurance Status Report ML18354A7382018-12-10010 December 2018 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Three-Year Update to the Decommissioning Funding Plan ML18075A3252018-03-0505 March 2018 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML17054C4592017-01-26026 January 2017 Yankee Atomic Electric Company - Yankee Rowe Independent Spent Fuel Storage Installation - Notification of Changes in Accordance with 10 CFR 50.82(a)(7) ML16076A2742016-03-0909 March 2016 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML16020A0162015-12-14014 December 2015 Yankee ISFSI - Three-Year Update to the Decommissioning Funding Plan ML15131A0252015-03-0303 March 2015 Yankee and Independent Spent Fuel Storage Installation (ISFSI) - Decommissioning Funding Assurance Status Report ML13094A1162013-03-25025 March 2013 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML12363A1072012-12-31031 December 2012 Independent Spent Fuel Storage Installation Decommissioning Study Plan ML12363A1062012-12-17017 December 2012 Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML1210706332012-03-27027 March 2012 Redacted - Yankee, Decommissioning Funding Assurance Status Report - 10CFR 50.75 ML1007504532010-03-0909 March 2010 Yankee Atomic, Decommissioning Funding Assurance Status Report - 1OCFR 50.75 ML0504703012005-02-0707 February 2005 Supplement to the Request for Proposed Procedures in Accordance with 1OCFR20.2002 ML0436305462004-12-22022 December 2004 Yankee Nuclear Power Station - Request for Approval of Proposed Procedures in Accordance with 10 CFR 20.2002 ML0409704532004-03-31031 March 2004 Yankee, Decommissioning Funding Assurance - 10CFR50.75(f) ML0411006392004-02-10010 February 2004 Yankee Atomic Electric Company (Rowe) License Termination Plan Update - Section 6 Appendices (A-N) ML0426700862003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Appendix 2C: Impacted Area Assessments Buildings, Structures and Open Land Areas Outside of the RCA ML0426701242003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 5 ML0426701152003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Appendix 4A: ALARA Evaluations ML0426701292003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 8 ML0426701272003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 7 ML0426701262003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 6 ML0426701072003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 4 ML0426700702003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Table of Contents ML0426700722003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 1 ML0426700782003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 2 ML0426700812003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Appendix 2A: Summaries of the Significant Events Leading to Long-Term Contamination of the Ynps Site (Presented in Ltp Table 2-3.) ML0426700842003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Appendix 2B: Impacted Area Assessments Buildings, Structures and Open Land Areas Inside of the RCA ML0426700912003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 3 ML0409600532003-10-28028 October 2003 Decommissioning Project Status, Goals and Challenges with Handwritten Notes ML0704301762003-10-20020 October 2003 Yankee Nuclear Power Station Site Closure Project Plan, Revision 1 ML0309805862003-03-31031 March 2003 Decommissioning Funding Assurance - 10CFR50.75 ML0210200492002-03-29029 March 2002 Submittal of Decommissioning Funding Assurance for the Yankee Nuclear Power Station ML0716700101993-12-20020 December 1993 Yankee Nuclear Power Station Decommissioning Plan Revision 0.0, Dated December 20, 1993 2023-03-06
[Table view] Category:50
MONTHYEARML23080A1072023-03-0606 March 2023 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML22237A0632022-08-0303 August 2022 Yankee Atomic Electric Company - Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML22082A1232022-03-14014 March 2022 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML22010A0122022-01-10010 January 2022 Yankee Atomic Electric Company - Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML21287A1012021-10-0404 October 2021 Yankee Atomic Electric Company - Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Biennial Update to the Yankee Nuclear Power Station License Termination Plan ML21105A7382021-03-0202 March 2021 Yankee Nuclear Power Station Independent Sperit Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML20108F5362020-03-12012 March 2020 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML19116A0502019-03-12012 March 2019 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation Decommissioning Funding Assurance Status Report ML18354A7382018-12-10010 December 2018 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Three-Year Update to the Decommissioning Funding Plan ML18075A3252018-03-0505 March 2018 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML17054C4592017-01-26026 January 2017 Yankee Atomic Electric Company - Yankee Rowe Independent Spent Fuel Storage Installation - Notification of Changes in Accordance with 10 CFR 50.82(a)(7) ML16076A2742016-03-0909 March 2016 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML16020A0162015-12-14014 December 2015 Yankee ISFSI - Three-Year Update to the Decommissioning Funding Plan ML15131A0252015-03-0303 March 2015 Yankee and Independent Spent Fuel Storage Installation (ISFSI) - Decommissioning Funding Assurance Status Report ML13094A1162013-03-25025 March 2013 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML12363A1072012-12-31031 December 2012 Independent Spent Fuel Storage Installation Decommissioning Study Plan ML12363A1062012-12-17017 December 2012 Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML1210706332012-03-27027 March 2012 Redacted - Yankee, Decommissioning Funding Assurance Status Report - 10CFR 50.75 ML1007504532010-03-0909 March 2010 Yankee Atomic, Decommissioning Funding Assurance Status Report - 1OCFR 50.75 ML0504703012005-02-0707 February 2005 Supplement to the Request for Proposed Procedures in Accordance with 1OCFR20.2002 ML0436305462004-12-22022 December 2004 Yankee Nuclear Power Station - Request for Approval of Proposed Procedures in Accordance with 10 CFR 20.2002 ML0409704532004-03-31031 March 2004 Yankee, Decommissioning Funding Assurance - 10CFR50.75(f) ML0411006392004-02-10010 February 2004 Yankee Atomic Electric Company (Rowe) License Termination Plan Update - Section 6 Appendices (A-N) ML0426700862003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Appendix 2C: Impacted Area Assessments Buildings, Structures and Open Land Areas Outside of the RCA ML0426701242003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 5 ML0426701152003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Appendix 4A: ALARA Evaluations ML0426701292003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 8 ML0426701272003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 7 ML0426701262003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 6 ML0426701072003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 4 ML0426700702003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Table of Contents ML0426700722003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 1 ML0426700782003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 2 ML0426700812003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Appendix 2A: Summaries of the Significant Events Leading to Long-Term Contamination of the Ynps Site (Presented in Ltp Table 2-3.) ML0426700842003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Appendix 2B: Impacted Area Assessments Buildings, Structures and Open Land Areas Inside of the RCA ML0426700912003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 3 ML0409600532003-10-28028 October 2003 Decommissioning Project Status, Goals and Challenges with Handwritten Notes ML0704301762003-10-20020 October 2003 Yankee Nuclear Power Station Site Closure Project Plan, Revision 1 ML0309805862003-03-31031 March 2003 Decommissioning Funding Assurance - 10CFR50.75 ML0210200492002-03-29029 March 2002 Submittal of Decommissioning Funding Assurance for the Yankee Nuclear Power Station ML0716700101993-12-20020 December 1993 Yankee Nuclear Power Station Decommissioning Plan Revision 0.0, Dated December 20, 1993 2023-03-06
[Table view] Category:70
MONTHYEARML23080A1072023-03-0606 March 2023 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML22237A0632022-08-0303 August 2022 Yankee Atomic Electric Company - Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML22082A1232022-03-14014 March 2022 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML22010A0122022-01-10010 January 2022 Yankee Atomic Electric Company - Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML21287A1012021-10-0404 October 2021 Yankee Atomic Electric Company - Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Biennial Update to the Yankee Nuclear Power Station License Termination Plan ML21105A7382021-03-0202 March 2021 Yankee Nuclear Power Station Independent Sperit Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML20108F5362020-03-12012 March 2020 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML19116A0502019-03-12012 March 2019 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation Decommissioning Funding Assurance Status Report ML18354A7382018-12-10010 December 2018 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Three-Year Update to the Decommissioning Funding Plan ML18075A3252018-03-0505 March 2018 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML17054C4592017-01-26026 January 2017 Yankee Atomic Electric Company - Yankee Rowe Independent Spent Fuel Storage Installation - Notification of Changes in Accordance with 10 CFR 50.82(a)(7) ML16076A2742016-03-0909 March 2016 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML16020A0162015-12-14014 December 2015 Yankee ISFSI - Three-Year Update to the Decommissioning Funding Plan ML15131A0252015-03-0303 March 2015 Yankee and Independent Spent Fuel Storage Installation (ISFSI) - Decommissioning Funding Assurance Status Report ML13094A1162013-03-25025 March 2013 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML12363A1072012-12-31031 December 2012 Independent Spent Fuel Storage Installation Decommissioning Study Plan ML12363A1062012-12-17017 December 2012 Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML1210706332012-03-27027 March 2012 Redacted - Yankee, Decommissioning Funding Assurance Status Report - 10CFR 50.75 ML1007504532010-03-0909 March 2010 Yankee Atomic, Decommissioning Funding Assurance Status Report - 1OCFR 50.75 ML0504703012005-02-0707 February 2005 Supplement to the Request for Proposed Procedures in Accordance with 1OCFR20.2002 ML0436305462004-12-22022 December 2004 Yankee Nuclear Power Station - Request for Approval of Proposed Procedures in Accordance with 10 CFR 20.2002 ML0409704532004-03-31031 March 2004 Yankee, Decommissioning Funding Assurance - 10CFR50.75(f) ML0411006392004-02-10010 February 2004 Yankee Atomic Electric Company (Rowe) License Termination Plan Update - Section 6 Appendices (A-N) ML0426700862003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Appendix 2C: Impacted Area Assessments Buildings, Structures and Open Land Areas Outside of the RCA ML0426701242003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 5 ML0426701152003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Appendix 4A: ALARA Evaluations ML0426701292003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 8 ML0426701272003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 7 ML0426701262003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 6 ML0426701072003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 4 ML0426700702003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Table of Contents ML0426700722003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 1 ML0426700782003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 2 ML0426700812003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Appendix 2A: Summaries of the Significant Events Leading to Long-Term Contamination of the Ynps Site (Presented in Ltp Table 2-3.) ML0426700842003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Appendix 2B: Impacted Area Assessments Buildings, Structures and Open Land Areas Inside of the RCA ML0426700912003-11-24024 November 2003 License Termination Plan for the Yankee Nuclear Power Station - Section 3 ML0409600532003-10-28028 October 2003 Decommissioning Project Status, Goals and Challenges with Handwritten Notes ML0704301762003-10-20020 October 2003 Yankee Nuclear Power Station Site Closure Project Plan, Revision 1 ML0309805862003-03-31031 March 2003 Decommissioning Funding Assurance - 10CFR50.75 ML0210200492002-03-29029 March 2002 Submittal of Decommissioning Funding Assurance for the Yankee Nuclear Power Station ML0716700101993-12-20020 December 1993 Yankee Nuclear Power Station Decommissioning Plan Revision 0.0, Dated December 20, 1993 2023-03-06
[Table view] Category:Letter
MONTHYEARIR 07200031/20234012023-10-0404 October 2023 Yankee Atomic Electric Company - Independent Spent Fuel Storage Security Inspection Report 07200031/2023401 ML23157A1012023-05-0404 May 2023 Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(2) for the Yankee Nuclear Power Station Independent Spent Fuel Storage Installation ML23130A1562023-04-24024 April 2023 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2022 ML23080A1072023-03-0606 March 2023 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML23080A1112023-03-0606 March 2023 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML22340A4752023-02-24024 February 2023 Closeout Letter to Yankee Atomic Electric Company Regarding 2018 and 2021 Updated DFPs for Yankee Nuclear Power Station ISFSI ML23041A1132023-01-0505 January 2023 Yankee Atomic Electric Company - Report of 10 CFR 72.48 Changes, Tests, and Experiments ML23041A1122023-01-0505 January 2023 Independent Spent Fuel Storage Installation, 10 CFR 50.59 Changes, Tests, and Experiments Report ML22347A2802022-12-21021 December 2022 Yankee Atomic Electric Company - Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 ML22237A0632022-08-0303 August 2022 Yankee Atomic Electric Company - Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML22136A1562022-04-28028 April 2022 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2021 ML22119A2112022-04-18018 April 2022 Independent Spent Fuel Storage Installation - Yankee Atomic Electric Company Adoption of NAC-MPC System, Amendment 8 Certificate of Compliance and Canister Registration ML22082A1232022-03-14014 March 2022 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML22089A1002022-03-14014 March 2022 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML22011A1292022-01-31031 January 2022 Yankee Atomic Electric Company- Independent Spent Fuel Storage Installation Security Inspection Plan ML22038A2062022-01-20020 January 2022 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Nuclear Liability Insurance Coverage ML22038A1982022-01-20020 January 2022 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Property Insurance Coverage ML22010A0122022-01-10010 January 2022 Yankee Atomic Electric Company - Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan IR 05000029/20210012021-10-29029 October 2021 Yankee Atomic Electric Company - NRC Independent Spent Fuel Storage Installation Inspection Report 07200031/2021001 and 0500029/2021001 ML21287A1012021-10-0404 October 2021 Yankee Atomic Electric Company - Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Biennial Update to the Yankee Nuclear Power Station License Termination Plan ML21287A0362021-10-0404 October 2021 Biennial Update to the Yankee Nuclear Power Station Final Safety Analysis Report ML21291A1602021-10-0404 October 2021 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Biennial Update of the Yaec Quality Assurance Program ML21189A0502021-06-0101 June 2021 Independent Spent Fuel Storage Installation, Formal Announcement of Change in ISFSI Manager ML21062A2472021-04-0707 April 2021 Close-out Letter - Yankee Rowe ISFSI DFP ML21077A1682021-03-0202 March 2021 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML21105A7382021-03-0202 March 2021 Yankee Nuclear Power Station Independent Sperit Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML21042A1452021-01-27027 January 2021 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Property Insurance Coverage ML21042A9812021-01-27027 January 2021 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Nuclear Liability Insurance Coverage ML21028A0632021-01-26026 January 2021 M210211: Welcome Letter to W. Norton ML20167A3032020-07-10010 July 2020 Letter - Ynps Exemption 190502, Rev 0 ML20167A3022020-07-0202 July 2020 FRN - Ynps Exemption 190502, Rev 0 ML20162A1282020-06-23023 June 2020 Issuance of Temporary Exemption from 10 CFR Part 73, Appendix B, for Yankee Rowe ISFSI (COVID-19) ML20160A0402020-05-20020 May 2020 BYR 2020-014 - Yaec Letter BYR 2020-014 Temporary Exemption - Annual Physical Requirement ML20087J6642020-03-16016 March 2020 Yankee Nuclear Power Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML20108F5362020-03-12012 March 2020 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML20054B6392020-02-0606 February 2020 Independent Spent Fuel Storage Installation - Formal Announcement of Change in ISFSI Manager ML20015A4942020-01-15015 January 2020 Yankee Atomic Power Company - Independent Spent Fuel Storage Installation Security Inspection Plan ML20013F6882019-12-17017 December 2019 Independent Spent Fuel Storage Installation - Formal Announcement of Change in Isfsj Manager ML19295E1062019-10-0202 October 2019 Biennial Update of the Yankee Atomic Electric Company Quality Assurance Program (Rev. 39) for the Yankee Rowe ISFSI ML19165A0262019-06-0505 June 2019 Independent Spent Fuel Storage Installation - Formal Announcement of Change in ISFSI Manager ML19176A0752019-05-0202 May 2019 Independent Spent Fuel Storage Installation - Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 ML19121A4202019-04-23023 April 2019 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2018 ML18354A7382018-12-10010 December 2018 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Three-Year Update to the Decommissioning Funding Plan IR 05000029/20180012018-05-30030 May 2018 Yankee Atomic Electric Company, Rowe, Massachusetts Site - NRC Independent Spent Fuel Storage Installation Report Nos. 07200031/2018001 and 05000029/2018001 IR 07200031/20184012018-05-17017 May 2018 Inspection Report 07200031/2018401, on May 17, 2018, Yankee Atomic Electric Company - ISFSI Security Inspection Report 07200031/2018401 - (Cover Letter Only) ML18136A5552018-04-10010 April 2018 Yankee Nuclear Power Station, and Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2017 ML18078A3012018-03-0505 March 2018 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML18075A3252018-03-0505 March 2018 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML17108A8282017-04-0303 April 2017 Yankee Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2016 ML17090A5292017-03-31031 March 2017 Independent Spent Fuel Storage Installation (ISFSI) - Transmittal of 10 CFR 50.59, 10 CFR 72.48, and Commitment Change Annual Reports and Notifications 2023-05-04
[Table view] |
Text
YANKEE ATOMIC ELECTRIC COMPANY 49 Yankee Road, Rowe, Massachusetts 01367 August 3, 2022 BYR 2022-018 Re: 10 CPR 72.4 and 10 CPR 72.30 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555 - 0001 Yankee Atomic Electric Company Yankee Nuclear Power Station Independent Spent Fuel Storage Installation NRC License No. DPR-3 (NRC Docket No.50-029)
Subject:
Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan On December 10, 2021, pursuant to the requirements of 10 CFR 72.30(c) and 10 CFR 72.4, Yankee Atomic Electric Company (YAEC) provided the three-year update to the Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan (DFP) (Reference 1). It included a modified assumption that significantly reduced the amount of material that would be shipped offsite as low-level radioactive waste. This letter provides supplemental information to define the basis for the modified assumption.
Y AEC utilized TLG Services, LLC a~ the i~dependent contractor to perfomi the Decommissioning Cost Estimates (DCEs) provided on December 10; 2018 and December JO, 2021 (References 2 and 1, respectively). Attachment 1 provides TLG Services, LLC's bases for the reduction in the volume of radioactive waste from that assumed in the previous DCE.
In addition, the volume oflow-level radioactive waste that is assumed to require remediation and shipment to an offsite facility is consistent with other licensees' DCEs that the NRC has previously reviewed. In References 3 and 4, South Carolina Electric & Gas and Santee Cooper submitted their initial decommissioning cost estimates for the Virgil C. Summer Nuclear Station Unit 1 ISFSI.
These documents state:
"The dry storage vendor, Holtec International, does not expect the overpacks to have any interior or exterior radioactive surface contamination. Any neutron activation of the steel and concrete is expected to be extremely small. The decommissioning estimate is based on the premise that some of the inner steel liners and concrete overpacks will contain low levels of neutron-induced residual radioactivity that would necessitate remediation at the time of decommissioning. As an allowance, 5 of the 75 Holtec overpacks are assumed to be affected, i.e., contain residual radioactivity. The aHowance quantity is based upon the number of casks
- required for the final core off-load (i.e., 157 off-loaded assemblies, 37 assemblies pet cask which results in 5 overpacks). It is assumed that these* are.the final casks offloaded; **
consequently they have the least time for radioactive decay of the neutron activation products."
Yankee Atomic Electric Company BYR 2022-018/August 3, 2022/Page 2 In Reference 5, the NRC provided their analysis of the decommissioning cost estimates for the Virgil C. Summer Nuclear Station Unit 1 ISFSI. The NRC states:
"Based on its financial analysis of SCE&G's and Authority's submittals, the NRC staff finds that the DCEs submitted for 2016: (1) are based on reasonable costs of a third party contractor; (2) include an adequate contingency factor; (3) reflect the cost of meeting the 10 CFR 20.1402 criteria for unrestricted use; and (4) are based on reasonable and documented assumptions.
Therefore, the NRC finds that the 2016 DCEs adequately estimate the cost, to carry out required ISFSI decommissioning activities prior.to license termination, and that the 2016 DCEs are acceptable."
In conclusion, the TLG Services, LLC bases provided in Attachment 1 and the precedent identified above justify the reduction in the volume of material that is assumed to be required to be remediated and shipped offsite in the DCE provided in December 2021 (Reference 1).
If you have any questions regarding this submittal, please do not hesitate to contact me at (508)-612-3322.
Respectfully,
~
Treasurer
Attachment:
- 1. TLG Services, LLC Bases for Low-Level Radioactive Waste Volume Assumption in December 2021 Decommissioning Cost Estimate
References:
- 1. Letter from T. Conry (YAEC) to Document Control Desk (NRC), Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated December 10, 2021 (BYR 2021-019) (ADAMS Accession Number: ML22010A012)
- 2. Letter from C. Pizzella (YAEC) to Document Control Desk (NRC), Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated December 10, 2018 (BYR 2018-025) (ADAMS Accession Number: ML18354A738)
- 3. Letter from South Carolina Electric & Gas to Document Control Desk (NRC), Virgil C.
Summer Nuclear Station, Unit 1, Decommissioning Funding Plan for Independent Spent Fuel Storage Installations (ISFSis), dated March 15, 2016 (ADAMS Accession Number:
ML16081A168)
Yankee Atomic Electric Company BYR 2022-018/August 3, 2022/Page 3
- 4. Letter from Santee Cooper to Document Control Desk (NRC) Virgil C. Summer Nuclear Station, Unit 1, Decommissioning Funding Plan for Independent Spent Fuel Storage Installation (ISFSis), dated March 18, 2016 (ADAMS Accession Number: ML16081Al36)
- 5. NRC Letter to V. C. Summer Nuclear Station, U.S. Nuclear Regulatory Commission Analysis of South Carolina Electric & Gas Company's and South Carolina Public Service Authority's Initial Decommissioning Funding Plans for Virgil C. Summer Independent Spent Fuel Storage Installation, dated May 26, 2021 (ADAMS Accession Number: ML21140A214) cc: D. Lew, NRC Region I Administrator T. Dimitriadis, Chief, Decommissioning Branch, NRC, Region 1 Y. Diaz-Sanabria, Chief, Storage and Transportation Licensing Branch, Division of Fuel Management, Office of Nuclear Material Safety and Safeguards J. Viveiros, Senior Nuclear Planner, MEMA J. Cope-Flanagan, Assistant General Counsel, MDPU J. Rogers, State of Massachusetts Office of the Attorney General
ATTACHMENT 1 TO BYR 2022-018 TLG Services, LLC Bases for Low-Level Radioactive Waste Volume Assumption in December 2021 Decommissioning Cost Estimate Prior to 2021, the Yankee Atomic Electric Company (YAEC) ISFSI decommissioning cost estimate was based on the general assumption that all of the overpacks and storage pads would be contaminated and require disposal as low-level waste. For the 2021 estimate, it was discussed that this assumption was overly conservative. YAEC engaged TLG to change this assumption to the standard that TLG assumes for the majority of their clients. Specifically, the number of storage canisters is based upon the number of canisters required for the final core off-load. It is assumed that these are the final casks offloaded; consequently, they have the least time for radioactive decay of the neutron activation products. The remaining overpacks and storage pad are assumed to be surveyed and free released.
While there is no generic guideline available for the quantity of activated material present in different designs for Dry Cask Storage Systems, the Final Safety Analysis Report (FSAR) for
-several storage systems references activation as a characteristic that must be assessed during decommissioning; however, the amount of neutron activation is expected to be small. For reference several documents are listed below:
Holtec Hi-Storm FSAR 3/31/16 ADAMS Accession Number: ML16138Al00 Section 2.4, Decommissioning Considerations. This document states that the overpack would have no interior or exterior surface contamination and that any neutron activation is expected to be extremely small. It is also stated that the overpack could be decontaminated to allow recycle
. or reuse options. In addition, no residual contamination is expected to be found on the storage pad.
NUHOLMS HD Horizontal Modular Storage System for Irradiated Nuclear Fuel, Safety Analysis Report, Rev. 0, April, 2004 ADAMS Accession Number: ML041540170 Section 2.4 Decommissioning Considerations. This document states that because of minimal contamination of the outer surface of the Dry Shielded Canister (DSC), no contamination is expected inside the Horizontal Storage Module (HSM). It is further stated that the HSMs can be dismantled and disposed of using commercial techniques.
NAC-MPC Final Safety Analysis Report, Revision 12, April 2019 ADAMS Accession Number: ML19113A211 Section 2.4 Decommissioning Considerations. This document states that activation of the carbon steel liner, concrete, support plates, and reinforcing bar could occur due to neutron flux from the stored fuel. Since the neutron flux rate is low, only minimal activation of carbon steel in the concrete cask is expected to occur. It is expected that the concrete will be broken up, and steel Page I of 3
ATTACHMENT 1 TO BYR 2022-018 TLG Services, LLC Bases for Low-Level Radioactive Waste Volume Assumption in December 2021 Decommissioning Cost Estimate components segmented, to reduce volume. Any contaminated or activated items are expected to qualify for near-surface disposal as low specific activity material. In addition, the storage pad, fence, and supporting utility fixtures are not expected to require decontamination as a result of use of the Universal Storage System.
NUREG-2215, Standard Review Plan for Spent Fuel Dry Cask Storage Systems and Facilities, April 2020 ADAMS Accession Number: ML20121A190 Section 14 Decommissioning Evaluation. This document describes the NRC's objective to ensure that the applicant's provisions for eventual decontamination and decommissioning of the ISFSI provide reasonable assurance that:
(1) the proposed provisions for eventual decontamination and decommissioning of the ISFSI will provide adequate protection of public health and safety (2) funds will be available to decommission the ISFSI (3) the design and operational features of the ISFSI facilitate eventual decontamination and decommissioning.
IAEA Technical Document -1081 Spent fuel storage and transport cask decontamination and modification, April 1999 URL: https://www-pub.iaea.org/MTCD/publications/PDF/te_ 1081 _prn.pdf Section 2.3 Neutron Activation of Cask Structure: While this publication states that in 8 to 10 years after fuel removal, the activated casks and concrete should decay to acceptable levels, currently there is no Below Regulatory Concern (BRC) for US licensees.
Discussion and Conclusions A MARSSIM-type survey on the over-pack steel and concrete using the most sensitive and appropriate detection instrument available (per MARSSIM) would determine if the subject containers are free releasable. Note that with evolving technologies it is expected that the level of detection for key radionuclides will improve over time.
In terms of the TLG "Class A" thumb rule: Using the volume of the cask systems for the last full core off-load is reasonable as these are likely to have the highest neutron flux/residual activation products with the least amount of decay time. Ultimately, a MARS SIM-type survey and characterization should be performed on the remaining site components post-DOE pickup to determine if contamination/activation products are present. In the case of a SAFSTOR scenario where the DOE removes the stored spent fuel 10+ years prior to site demolition (assumes that ISFSI and Power Block decommissioning and dismantlement is occurring in the same time period), the probability of free release is much improved.
Page 2 of 3
ATTACHMENT 1 TO BYR 2022-018 TLG Services, LLC Bases for Low-Level Radioactive Waste Volume Assumption in December 2021 Decommissioning Cost Estimate Making the above-described change to the YAEC Yankee Rowe ISFSI decommissioning cost estimates results in a significant reduction in waste volume and disposal costs. TLG believes this change is reasonable and is consistent with the DCEs developed by TLG for other utilities.