ML040960053
| ML040960053 | |
| Person / Time | |
|---|---|
| Site: | Yankee Rowe |
| Issue date: | 10/28/2003 |
| From: | Kacich R Yankee Atomic Electric Co |
| To: | NRC/FSME |
| References | |
| -RFPFR, FOIA/PA-2004-0057 | |
| Download: ML040960053 (17) | |
Text
I.
.1 I
Is
,R..
I I....
1 I
I I
acsloee Rone Decomrnrissioning roject Status, Goats and Challenges Richard M. Kacich, President October 28. 2003
- Ze
Recent successes and strategic direction have set the stage forpositive outcomes Completion of ftiel transfer enables the resumiption of demolition and disposal A focus on safety remains the key to Yankee's success Management is aggressively pursuing identified challenges Recent FERC settlement provides adequate funding 2HE
.t.,:-
,..t.
Thcn fulQs as de/Ot't.SP~~~l(10 The. 1 6thand fin~al storage.akImaded~wIth GTCmaeal waso rKv~dQtpIFSlpdol6gI
- A, '
- comp.
.a.-:a*.
er..
,,je:*A-Spent Fuel Pool Dran o L' WV.
FUEL TRANSFER AND SPF DRAIN DOWN ESafe Fuel and GTCC Transfer to the ISFSI Enabled Decommissioning/Demolition Resumption
- Extensive Stakeholder Interaction Facilitated a Timely NPDES Permit a SFP Drain Down was Uneventfully Completed Despite Significant Radiological Challenges
- Applying Lessons Learned From CY, MY and Big Rock Point Enhanced Outcomes
II 2003Site 'Dem mteils irWm ~app'ear ~Becm"~
0" io chee IcniePlnGal
.*W.:
4.
Ero 6i dion~6 Aeral wal applijear December 2003 Dmolitton j,
Activities' job
'Servrce.urtng Anne 8ervlc' B lnApnri.ex
..August 25.,2003
,..asbestos abatement rs s
oIn. compete abatement prepnratoiforo jg k
Avl.~
, * *; -I-:~, i MRw,
.g _
- g phds20.0demo tlon ca*mp ete-
.. ~ ~
~ u t. 3 2 0
'3
2003 SITE DEMOLITION INCENTIVE PLAN GOAL X Managing Available Real Estate Remains a Continuing Challenge X Time for Planning Dwarfs Time Required for Physical Demolition
- Photos Visually Depict 2003 Incentive Plan Goal Schedule
- Structures to be Demolished in 2003 Include:
Warehouse, Service Building Annex, Service Building, and Turbine Building (YA0 ro HIf
Consistent Physical Demolition Progress Achieves June 2005 Vision 5
JUNE 2005 DEMOLITION VISION
- Photo Series Illustrates Outcome Aligned With the FEIRC Settlement IDemolition Plan Aligned to Reduce Impact of Winter Weather Recurring Demolition Sequence Includes: "Cold &
Dark," Assess, Remediate, Demolish, Dispose
- June 2005 End State of "Physical Decommissioning" Sets the Stage for FSS and Property Transfer if45ijEl)
I !
,t FERC project settlement establishesbasisfor cost and schedulegoals a ALL waste shipped off-site 9 Physical decommissioning complete by June 2005 io Property ready for transfer January 2006 YA K) 6
The FER C settlement also includes requirement to engage interested parties..r..--a
- To cooperatively identify potentially viable alternatives for interim storage of SNF (including GTCC) outside of New England
- To identify the most viable alternative, and
- To develop an action plan to initiate the
,f selected alternative 7
KE.
Tihe cost to decommission is significant Cost Categories Totals ($ Millions)
Total Decommissioning Costs 636.4 1992-2002 Decommissioning (incurred) 347.9 "To-Go" Cost Estimate (2003-2022)*
288.5 Demolition/Disposal 97.1 Radioactive Waste 20.0 Long-Termn SNF Storage 129.2 Site Restoration 0.3 Final Status Survey 4.0 Contingency 37.9 i eITo-Go" cost estimate is stated in year 2003 dollars Q~-I 0ANK 8
Project Challenges Necessitate Strategic Focus Indenture Property Resolution PCB :Contamination
- 1. /,_
'-I,'
iIi
£ PC s'd o'il s'ampling results:
SPOB sediment samp ILTP Submittal and Approval Sh~erman Dami 4
X o.
V E
t.
9
PROJECT CHALLENGES
- Additional Characterization is Required to Define Scope of Remediation
- Property Indenture Introduces Uncertainties With Shoreline Access and FERC Approvals
- Targeted LTP Schedule for NRC Approval, a Critical Path Activity, is <50% of Previous Industry Best X LTP Reflects Lessons Learned From Other Facilities
Regulatory Permitting Process is Complex and Multifaceted
.1 I
i_
Table I Non-radiological Regulatory Summary P.AE'sora AMW u
A-isS li.1
- 9.
S W.
rsd5 E
G FCI 1XI Cm III-WrAdfd SF.sga ICud.%ft g~Pd
.40 A=
_ _r W
gW%
%P* Du "am q p
8 rdddp Aaa.
C ksu stR 9..."
DS L Heed PasC E bm.
LP&W C-w 1t.,
11 i
4 f
I wI I -
I t
Ii 5
b~
<u~wa1,68A^
a' C hM A.
s sW s wA P q tt
'c ist p l t A
E*. d nE qA t a w s p n., g~ r U G EtA.EA,,dtsPOW, FEC.P -
FdW W W AMptq sI I RAUI.&*s A.n.ssI WR-.*WW-irlnL
-W4C.
M?;-Y.As-,'J Fliar~lypX4Ss2.x I-Required regulatory approvals and permits 10
- -'.s.-
zF-
...,.:.54.
REGULATORY PERMITTING PROCESS Non-RCRA CAP Status Requires a Yankee-Conceived Site Closure Process
- Number and Variety of Required Permits Requires Extensive Stakeholder Interaction Campaign o Constructive Engagement With Regulators Will Enhance Permit Timeliness
- Long Lead Time Permit Submittals Depend on Completion of Environmental Characterization X To Date, Stakeholder Interaction and Opposition Impact has Been low YNE
The requested LTP review interval is aggressive, but achievable
- Ycankee Rowe is a comparatively clean site
- Substantial prior characterization has been performed and additional workl is underway
- Process familiarity developed fronm past experience (CY) and industry lessons learned
'I.
YANKEE B.-.--
NRC.fo u s and support will enhance the quality andtimeliness of results s Decomnmissioning project success is important to demonstrate nuclear plant end-of-life costs are manageable and finite
- Key Yankee regulatory issues include:
- , LTP review interval Emergency response requirement - Statte Police
- .: NEIL Liability Insurance exemption 7-A 4E,Y J-ANKEE 12