ML21078A095

From kanterella
Revision as of 20:56, 23 May 2022 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Session W20 - James Petty - Slide Deck 3
ML21078A095
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 03/08/2021
From: Petty J
Exelon Nuclear
To:
NRC/RGN-III
References
Download: ML21078A095 (4)


Text

Risk Informed Completion Times Licensee Experience James T. Petty Director of Site Operations Braidwood Generating Station - Exelon Nuclear

TSTF-505 Overview

  • TSTF-505 license amendment requests (LAR) approval for Braidwood in March 2020.
  • A new Risk-Informed Completion Time (RICT) program was added to the Administrative Controls section of TS
  • RICT is only applied in Modes 1 and 2 (Exelon does not have a Shutdown PRA so Modes 3 and 4 were not included)
  • RICT may not exceed 30 days
  • If TS LCO is not restored prior to reaching RICT, then TS requirements for plant shutdown or other remedial action become applicable
  • RICT is not permitted for a loss of TS safety function configuration or inoperability of all required safety trains
  • Impacts on baseline CDF and LERF are periodically monitored

TSTF-505 Benefits

  • Emphasis on risk-significant configurations
  • Increased control of plant configuration during SSC unavailability
  • Avoided shutdowns = Avoided safety challenges
  • Increased flexibility in scheduling maintenance
  • Shorter, less-complex refueling outages - Outage work moved online
  • Reduced organizational stress with short work windows
  • Increased plant availability and capacity factors

RICT Examples at Braidwood

  • Station Auxiliary Transformer (SAT) work window - Fall 2020
  • Normally requires 3 separate 72-hour LCO windows to complete all PMs on both transformers.
  • Work window scope revision with RICT requires a single LCO window.
  • Results in less EDG and equipment manipulations.
  • Component Cooling Water (CC) system Heat Exchanger (HX) work - Winter 2021
  • CC HX flange degradation identified in 2011 required repairs to ensure minimum wall criteria/maximum allowable wall stresses are maintained.
  • Outage work scope would have required an ~12-day work window that would be scheduled only 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> off outage critical path.
  • 51 hours5.902778e-4 days <br />0.0142 hours <br />8.43254e-5 weeks <br />1.94055e-5 months <br /> of scope expansion contingency work would potentially challenge overall outage duration and goals.
  • Significant challenge to Shutdown Safety profile and Shutdown Cooling availability.