End-of-Cycle Meeting Presentation
ML21166A372
Person / Time
Site: Byron, Braidwood  Constellation icon.png
Issue date: 06/15/2021
From:
NRC/RGN-III
To:
Shared Package
ML21050A252, ML21050A277 List:
References
7300217
Download: ML21166A372 (19)


Text

2020 Annual Assessment Webinar Braidwood and Byron For Audio, dial:

1-888-603-9743 Passcode: 7300217#

Microphones will be muted and cameras turned off.

During the presentation, your phones will be muted.

Nuclear Regulatory Commission Region III, Lisle, IL.

2020 End of Cycle Annual Assessment Webinar Braidwood and Byron

NRC Regional Staff Hironori Peterson Nirodh Shah Ashley Demeter Branch Chief Senior Project Engineer Project Engineer Division of Reactor Projects, Division of Reactor Division of Reactor Branch 3 Projects, Branch 3 Projects, Branch 3 3

Agenda

  • Presentation

- NRC Mission

- Reactor Oversight Process (ROP)

- NRC COVID-19 Actions

- 2020 Safety Performance Overview

  • Braidwood
  • Byron
  • Question-and-Answer Session 4

OUR MISSION To license and regulate the nations civilian use of radioactive materials to provide reasonable assurance of adequate protection of public health and safety and to promote the common defense and Region III Office, Lisle, IL security and protect the environment.

5

How do we meet our Mission?

Licensing Muzammil at Braidwood Oversight (Inspections)

Enforcement Incident Response Ashley at Byron NRC Main Operations Center 6

Reactor Oversight Process www.nrc.gov/reactors/operating/oversight.html 7

Action Matrix Columns Multiple/Repetitive Licensee Regulatory Degraded Unacceptable Degraded Response Response Performance Performance Cornerstone Increasing:

  • Safety Significance
  • Inspection
  • Management Involvement
  • Regulatory Action 8 www.nrc.gov/reactors/operating/oversight.html

NRC Response to COVID-19 More detailed information on NRC actions can be found on the NRC webpage: https://www.nrc.gov/about-nrc/covid-19/reactors/

Senior Resident Inspector Dan Kimble at Braidwood Senior Resident Inspector Diana Betancourt at Byron Resident Inspector Phil Smagacz at Braidwood Resident Inspector Jamie Weigandt at Byron 9

So how did the sites do?

Braidwood Byron

Braidwood Resident Inspectors Daniel Kimble Phillip Smagacz Senior Resident Inspector Resident Inspector 11

Braidwood 2020 Assessment Summary

  • Operated safely and in a manner that preserved the public health and safety and protected the environment
  • Licensee Response Column
  • 2555 hours0.0296 days <br />0.71 hours <br />0.00422 weeks <br />9.721775e-4 months <br /> of direct inspection
  • All Green Performance Indicators
  • One non-cited, Severity Level IV violation for the failure to follow procedures during blowdown of a multi-purpose cannister.
  • One Green finding with an associated non-cited violation for the main steam safety valves lift pressure setpoints not within Technical Specification.

https://www.nrc.gov/reactors/operating/oversight/listofasmrpt.html 12

Byron Resident Inspectors Diana Betancourt Jamie Weigandt Senior Resident Inspector Resident Inspector 13

Byron 2020 Assessment Summary

  • Operated safely and in a manner that preserved the public health and safety and protected the environment
  • Licensee Response Column
  • 2303 hours0.0267 days <br />0.64 hours <br />0.00381 weeks <br />8.762915e-4 months <br /> of direct inspection
  • All Green Performance Indicators
  • One Green finding and associated non-cited violation for the failure to have appropriate work order instructions to replace the flexible hoses on the 1B auxiliary feedwater pump
  • One Green finding and associated non-cited violation for performing incorrect valve manipulation during component cooling pump ASME surveillance testing
  • One Green finding and associated non-cited violation for entering a high radiation area prior to dose rates having been determined.

https://www.nrc.gov/reactors/operating/oversight/listofasmrpt.html 14

For more information

  • Inspection Reports

- https://www.nrc.gov/reactors/operating/oversight/listofrpts-body.html

  • Reactor Oversight Process

- https://www.nrc.gov/reactors/operating/oversight.html

  • Fact Sheets and Brochures

- https://www.nrc.gov/reading-rm/doc-collections/fact-sheets/

  • NRC Information Digest

- https://www.nrc.gov/reading-rm/doc-collections/nuregs/staff/sr1350/

  • Regulations

- https://www.nrc.gov/reading-rm/doc-collections/cfr/

15

NRC Social Media Channels Facebook: https://www.facebook.com/nrcgov/

Twitter: https://twitter.com/#!/nrcgov YouTube: http://www.youtube.com/user/NRCgov Linkedin: https://www.linkedin.com/company/u-s--nuclear-regulatory-commission/

Flickr: https://www.flickr.com/photos/nrcgov/

Meeting Feedback On Any Device or Computer:

Go to the Public Meeting Schedule at (www.nrc.gov/pmns/mtg?do=recent30days)

Locate this meeting using the sorting buttons and click on the Meeting Feedback Form Link.

Note: Meetings are sorted by date and time. Use last to get to the most recently completed meeting.

Region III Public Affairs Officers Viktoria Mitlyng Prema Chandrathil Office: 630-829-9662 Office: 630-829-9663 Cell: 630-201-1345 Cell: 630-515-6145 Viktoria.mitlyng@nrc.gov Prema.chandrathil@nrc.gov 18

QUESTIONS?

To ask a question either:

Questions submitted by phone will be answered in the order received.

Press *1 and inform the operator that you wish to ask a question or make a statement.

You may also email your questions after the Webinar to the PAOs.

Viktoria.mitlyng@nrc.gov Prema.chandrathil@nrc.gov 19