ML22103A243

From kanterella
Revision as of 00:13, 11 May 2022 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
E-mail - Request for Additional Information - License Amendment Request to Revise Emergency Plan and Emergency Action Level Scheme for Permanently Defueled Condition for Indian Point Energy Center
ML22103A243
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 04/13/2022
From: Cruz-Perez Z
Reactor Decommissioning Branch
To: Fleming J
Holtec Decommissioning International
Cruz-Perez Z
Shared Package
ML22103A241 List:
References
Download: ML22103A243 (2)


Text

From: Cruz Perez, Zahira To: Jean Fleming Cc: Bill Noval; Matthew Johnson; Walter Wittich; Watson, Bruce

Subject:

Request for Additional Information: License Amendment Request to Revise Emergency Plan and Emergency Action Level Scheme for Permanently Defueled condition for Indian Point Energy Center Date: Wednesday, April 13, 2022 10:54:00 AM Attachments:

Dear Ms. Fleming,

By letter dated December 22, 2021 (Agencywide Documents Access and Management System [ADAMS]) Accession No. Main Library [ML] ML21356B704), Holtec Decommissioning International, LLC (HDI) submitted a license amendment request for Indian Point Nuclear Generating Units Nos. 1, 2 and 3, collectively referred to as Indian Point Energy Center (IPEC). HDI submitted a revision to the license amendment requests on February 4, 2022 (ADAMS Accession No. ML22035A121). The requested license amendments would revise the IPEC Emergency Plan and Emergency Action Level (EAL) scheme for the permanently shutdown and defueled condition at IPEC. The NRC staff is reviewing the license amendment requests and has determined that additional information is required to complete its review.

On April 1, 2022 the draft request for additional information (RAI) questions were sent to you to ensure that they were understandable, the regulatory bases for the questions were clear, and to determine if the information was previously docketed. Teleconference was held on April 7, 2022 with your staff to clarify the RAI questions. HDI stated they would respond to the RAI within 30 days of the date of this email.

In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this email will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of ADAMS. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. If you have any questions, please contact me.

Zahira Zahira Cruz (Pronouns: She/Her/Hers)

Project Manager U.S. Nuclear Regulatory Commission Office of Nuclear Material Safety and Safeguards Reactor Decommissioning Branch Mail Stop: T-5A10 Rockville, MD 20852 Zahira.Cruz@nrc.gov 301-415-3808 Docket Nos.50-003, 50-247, and 50-286

Enclosure:

Request for Additional Information cc: Indian Point Listserv