ML22107A000

From kanterella
Revision as of 00:09, 11 May 2022 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
City of Oak Ridge Capital Improvement Program for 2022-2027: Reference for Kairos Hermes CP Application
ML22107A000
Person / Time
Site: Hermes
Issue date: 02/18/2021
From:
City of Oak Ridge, TN
To:
Office of Nuclear Material Safety and Safeguards
Dozier T
References
Download: ML22107A000 (126)


Text

CITY OF OAK RIDGE, TENNESSEE CAPITAL IMPROVEMENTS PROGRAM FOR FISCAL YEARS 2022-2027 Oak Ridge Municipal Planning Commission H. Stephen Whitson, Chairman Jim Dodson Jane Shelton Charlie Hensley Benjamin Stephens Claudia Lever Todd Wilson Greta Ownby Phil Yager Roger Petrie

TABLE OF CONTENTS I. TRANSMITTAL Transmittal Letter to City Council ................................................................................ I-1 Planning Commission Priority Rankings ....................................................................... I-3 II.

SUMMARY

OF FUNDING AND EXPENDITURES Summary of Programs by Responsible Department .................................................... II-1 Summary of Projects by Responsible Department ...................................................... II-2 Summary of Projects by Funding ................................................................................. II-5 Summary of Placeholder Projects by Responsible Department ................................ II-10 III. BOARD OF EDUCATION BOARD OF EDUCATION CAPITAL PROJECTS Summary of Capital Projects ....................................................................................... III-1 Linden Elementary School ........................................................................................... III-2 New West End School..III-3 Renovation of Jefferson Middle School ...................................................................... III-4 Replace Preschool/Administration Building ............................................................... III-5 Robertsville Middle School ......................................................................................... III-7 BOARD OF EDUCATION PLACEHOLDER PROJECTS Summary of Placeholder Projects ............................................................................... III-8 Glenwood Elementary School ..................................................................................... III-9 Willow Brook Elementary III-10 Woodland Elementary School...III-11 IV. CITY CLERK CITY CLERK CAPITAL PROJECTS Summary of Capital Projects ....................................................................................... IV-1 Court Room Improvements ........................................................................................ IV-2 V. CITY MANAGERS OFFICE CITY MANAGERS OFFICE CAPITAL PROJECTS Summary of Capital Projects ........................................................................................ V-1 Oak Ridge General Aviation Airport ............................................................................. V-2 VI. COMMUNITY DEVELOPMENT COMMUNITY DEVELOPMENT CAPITAL PROJECTS Summary of Capital Projects ....................................................................................... VI-1 Community Development Office Renovation ............................................................. VI-2 National Register District Study/AmendmentsVI-3 COMMUNITY DEVELOPMENT PLACEHOLDER PROJECTS Summary of Placeholder Projects ............................................................................... VI-4 Downtown Oak Ridge Streetscape Improvements ..................................................... VI-5

VII. ELECTRIC ELECTRIC DEPARTMENT CAPITAL PROJECTS Summary of Capital Projects ..................................................................................... VII-1 Electric Distribution System Improvements ............................................................. VII-2 Electric Substation Improvements ............................................................................. VII-3 Electric Technology Program ..................................................................................... VII-4 Facilities Expansion for New Loads and Services ...................................................... VII-6 Street Light Improvement Program ........................................................................... VII-7 Traffic Signal Control Replacement and Upgrade ..VII-8 ELECTRIC DEPARTMENT PLACEHOLDER PROJECTS Summary of Placeholder Projects .............................................................................. VII-9 Long Term Electric System Needs ............................................................................ VII-10 VIII. FIRE FIRE DEPARTMENT CAPITAL PROJECTS Summary of Capital Projects .................................................................................... VIII-1 Fire Station 2 Property for Relocation ...................................................................... VIII-2 Fire Station 3 Repair or Replace Training Tower ...VIII-3 IX. LIBRARY LIBRARY DEPARTMENT CAPITAL PROJECTS Summary of Capital Projects ...................................................................................... IX-1 Library Design Work ................................................................................................... IX-2 Library Renovations: Central Library... IX-3 Library Renovations: East Wing..... IX-4 Library Renovations: West Wing.... IX-5 X. POLICE DEPARTMENT POLICE DEPARTMENT CAPITAL PROJECTS Summary of Capital Projects ........................................................................................ X-1 Security Fencing for PD Parking Area ........................................................................... X-2 XI. PUBLIC WORKS PUBLIC WORKS CAPITAL PROJECTS Summary of Capital Projects ....................................................................................... XI-1 Sewer Collection system Rehab/CMOM..XI-2 Transportation/Pedestrian/Bicycle Safety Improvements..XI-4 Turtle Park Wastewater Treatment Plant...XI-5 Water Treatment Place - Existing XI-7 Water Treatment Plant - New... XI-8 PUBLIC WORKS PLACEHOLDER PROJECTS Summary of Placeholder Projects ............................................................................... XI-9 New Sidewalk Construction ...................................................................................... XI-10 Rarity Ridge Wastewater Treatment Plant .XI-11

PUBLIC WORKS/BOARD OF EDUCATION Summary of Capital Projects ..................................................................................... XI-12 City/Schools Joint for Facilities ................................................................................. XI-13 City/Schools Joint HVAC Projects .............................................................................. XI-17 City/Schools Joint Roof Projects ............................................................................... XI-18 PUBLIC WORKS/FIRE DEPARTMENT Summary of Capital Projects ..................................................................................... XI-19 Fire Station 2 Building Study ..................................................................................... XI-20 PUBLIC WORKS/LIBRARY Summary of Capital Projects ..................................................................................... XI-21 ADA Compliant Restrooms for Public Library ........................................................... XI-22 XII. RECREATION AND PARKS RECREATION AND PARKS CAPITAL PROJECTS Summary of Capital Projects ...................................................................................... XII-1 Briarcliff Park .............................................................................................................. XII-2 Greenway Implementation ........................................................................................ XII-3 Groves Park ................................................................................................................ XII-4 Oak Ridge Gateway..XII-5 Outdoor Pool Renovation.XII-6 Rowing Improvements .............................................................................................. XII-7 Solway Park ................................................................................................................ XII-8 RECREATION AND PARKS PLACEHOLDER PROJECTS Summary of Placeholder Projects .............................................................................. XII-9 Bobby Hopkins Baseball Field ................................................................................. XII-10 Melton Lake Park ..................................................................................................... XII-11 Neighborhood Park w/ Designated Areas for Skateboarding and Rollerblading..... XII-12 Pinewood Park ......................................................................................................... XII-13 Westwood Park ........................................................................................................ XII-14 Wolfe Creek Park...................................................................................................... XII-15 XIII. MAINTENANCE REPORTS Summary of Maintenance Programs ........................................................................ XIII-1 Summary of Maintenance Projects by Responsible Department ............................. XIII-2 Summary of Maintenance Projects by Funding ....................................................... XIII-4

Transmittal CITY OF OAK RIDGE OAK RIDGE MUNICIPAL PLANNING COMMISSION POST OFFICE BOX 1, OAK RIDGE, TENNESSEE 37831-0001 February 18, 2021 Honorable Mayor and Members of City Council City of Oak Ridge P.O. Box 1 Oak Ridge, TN 37831 Attention: Mark Watson, City Manager

Dear Members of City Council:

The Oak Ridge Municipal Planning Commission voted on February 18, 2021 to approve and transmit to City Council a Capital Improvements Program (CIP) in accordance with the City Charter. The CIP is submitted for City Councils use in providing guidance to the City Manager on how proposed projects align with adopted City plans as he begins preparation of the annual budget.

The Commission has carefully considered the capital improvements and maintenance projects of the CIP that were drafted by departmental staff. As has been the case for the past several years, the capital projects recommended have been reviewed and prioritized with an emphasis on fiscal restraint. Additionally, the Planning Commission relied heavily on the City Blueprint plan to shape the CIP and help guide their evaluations and rankings. The most highly-ranked projects were the new water treatment plant as well as roof and HVAC work in our City schools and facilities. Other highly ranked projects include maintenance and upgrades to the citys electrical system, the proposed Oak Ridge General Aviation Airport, and renovations to Robertsville Middle School.

The Commission has made a conscientious effort to recommend only the most needed projects, while still proposing key capital investments that move our City forward. The Commission noted the following items for special attention by City Council:

New/Existing Water Treatment Plant The new water treatment facility received the highest priority ranking from the Planning Commission for the second year in a row. Also given a high priority ranking were improvements to the existing water treatment plant.

I-1

City/Schools Facilities Projects Some of the other projects given the highest ranking by the Planning Commissioners were improvements and renovations to existing city and schools facilities. Projects the received a ranking of High include:

  • City/School Joint for Facilities
  • City/School Joint for HVAC Projects
  • City/School Joint for Roof Projects
  • Robertsville Middle School Oak Ridge General Aviation Airport The Oak Ridge General Aviation Airport was a new project in the CIP this year submitted by the City Managers Office. This project, funded primarily with grant and other state funding, was given a high priority ranking by the Commission.

Fire Projects Two Fire Department projects were given a high priority ranking by the Planning Commission. The first are improvements to the Training Tower at Fire Station 3. The second is the Fire Station 2 Building Study, which aims to determine the feasibility of relocating fire station 2 vs. building an additional station to provide improved fire services on the east end of town.

Electrical Infrastructure Projects The Commission has given a top priority to those projects that will help the City maintain a high level of electric service to both new and future customers, with upgrades to substation and distribution system.

Other High Ranking Projects: Turtle Park WWTP / ADA Compliant Restrooms at the Library Two other projects received a high priority ranking from the Planning Commission. The first project involves maintenance, repair, and replacement of equipment at the Turtle Park Wastewater Treatment Plant. The second is for the construction of ADA compliant restrooms in the Citys Library.

Respectfully submitted, H. Stephen Whitson, Chair Oak Ridge Municipal Planning Commission I-2

Projects funded by Capital Funds/General Obligation/Utilities Funds Department Project Ranking (High / Medium / Low)

Education New West End School Medium (New K-4 school on the west end of the City)

Education Renovation of Jefferson Middle School Medium (Renovation of MS including parking, mechanical, and administration area upgrades)

Education Replace Preschool/Administration Building Medium (New location for School Administration/former Preschool building)

Education Robertsville Middle School High (Overall renovation of MS building)

City Clerk Court Room Improvements Medium (General court room renovation, including furniture, technology, and security improvements)

City Managers Office Oak Ridge General Aviation Airport High (General aviation airport at ETTP site)

Community Community Development Office Renovations Medium Development (Office reconfiguration for improved safety and customer service)

Community National Register District Study/Amendments Low Development (Review and potential modification of OR National Register District)

Electric Electric Distribution System Improvements High (System-wide improvements to existing infrastructure)

Electric Electric Substation Improvements High (Equipment upgrades and replacement of certain substations)

Electric Electric Technologies Program Medium (System-wide technological upgrades for additional automation)

Electric Facilities Expansion for New Load and Services Medium (Costs associated with expanding services to new developments)

Electric Street Light Improvements Program Medium (Street light upgrades throughout the city)

Electric Traffic Signal Replacement and Upgrade Medium (Replacing traffic signals and technological upgrades)

I-3

Fire Fire Station 2 Property for Relocation Medium (identify and purchase property to move fire station 2)

Fire Fire Station 3 Repair or Replace Training Tower High (Engineering and construction for fire tower repairs)

Library Library Design Work Medium (Design for major library renovation)

Library Library Renovations: Central Library Medium (Library work room expansion and new circulation desk)

Library Library Renovations: East Wing Medium (Childrens room renovation and café/display area in lobby)

Library Library Renovations: West Wing Medium (Renovation of Oak Ridge Room and creation of conference rooms)

Police Department Security Fencing of PD Parking Area Medium (New security fencing on south side of municipal building)

Public Works Sewer Collection System Rehab/CMOM Medium (Program for upkeep of sewer collection system)

Public Works Transportation/Pedestrian/Bicycle Safety Improvements Medium (Primarily grant funded improvements to numerous sidewalks, crosswalks, etc.)

Public Works Turtle Park Wastewater Treatment Plant High (Maintenance and renovation of wastewater facility)

Public Works Water Treatment Plant - Existing High (Renovation of Citys existing water treatment plant)

Public Works Water Treatment Plant - New High (Design and construction of new water treatment plant)

Public Works / Board City/Schools Joint for Facilities High of Education (Capital maintenance projects at numerous city schools and facilities)

Public Works / Board City/Schools Joint HVAC Projects High of Education (HVAC replacement or repair at multiple city schools and facilities)

Public Works / Board City/Schools Joint Roof Projects High of Education (Continued repair or replacement of roofs at multiple city schools and facilities)

Public Works/Fire Fire Station 2 Building Study High Department (Study needed repairs and feasibility of moving station)

Public Works/Library ADA Compliant Restrooms for Library High (Renovation of restrooms in library for ADA compliance)

I-4

Recreation and Parks Briarcliff Park Low (Development of 8 acres into a park)

Recreation and Parks Greenway Implementation Medium (Rails to Trails project: design, acquisition, and construction)

Recreation and Parks Groves Park Low (Development of former landfill area into a neighborhood park)

Recreation and Parks Oak Ridge Gateway Medium (TDOT grant funded gateway monument in the median between S Illinois and Bethel Valley)

Recreation and Parks Outdoor Pool Renovation Low (Renovation of Oak Ridge outdoor pool shell)

Recreation and Parks Rowing Improvements Medium (Improvements to docks, parking, etc. at Melton Hill Lake facility)

Recreation and Parks Solway Park Low (General park upgrades including landscaping, playground, etc.)

I-5

Summary Capital Improvements Program - Capital Summary of Programs - ($000's)

Responsible Department FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Board of Education $0 $33,923 $0 $2,000 $9,400 $0 $45,323 City Clerk $50 $550 $150 $0 $0 $0 $750 City Manager's Office $13,347 $34,542 $7,103 $0 $0 $0 $54,992 Community Development $20 $275 $15 $0 $0 $0 $310 Electric $8,090 $7,202 $4,515 $2,763 $2,140 $2,093 $26,803 Fire Department $350 $310 $1,220 $0 $0 $0 $1,880 Library $66 $25 $105 $0 $0 $0 $195 Police Department $214 $0 $0 $0 $0 $0 $214 Public Works $28,619 $26,968 $4,288 $3,945 $6,232 $2,727 $72,778 Public Works / Board of Education $2,623 $4,911 $2,693 $1,363 $1,230 $2,251 $15,071 Public Works/Fire Department $18 $0 $0 $0 $0 $0 $18 Public Works/Library $210 $0 $0 $0 $0 $0 $210 Recreation and Parks $1,200 $3,474 $680 $150 $60 $4,900 $10,464 TOTAL CAPITAL IMPROVEMENTS PROGRAM $54,806 $112,180 $20,768 $10,221 $19,062 $11,971 $229,008 II - 1

Capital Improvements Program - Capital Summary of Projects By Responsible Department - ($000's)

Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Board of Education Linden Elementary School $0 $10,223 $0 $0 $0 $0 $10,223 New West End School $0 $23,700 $0 $0 $0 $0 $23,700 Renovation of Jefferson Middle School $0 $0 $0 $0 $0 $0 $0 Replace School Administration Building $0 $0 $0 $0 $0 $0 $0 Robertsville Middle School $0 $0 $0 $2,000 $9,400 $0 $11,400 Board of Education TOTAL: $0 $33,923 $0 $2,000 $9,400 $0 $45,323 City Clerk Court Room Improvements $50 $550 $150 $0 $0 $0 $750 City Clerk TOTAL: $50 $550 $150 $0 $0 $0 $750 City Manager's Office Oak Ridge General Aviation Airport $13,347 $34,542 $7,103 $0 $0 $0 $54,992 City Manager's Office TOTAL: $13,347 $34,542 $7,103 $0 $0 $0 $54,992 Community Development Community Development Office Renovation $20 $250 $0 $0 $0 $0 $270 National Register District Study/Amendments $0 $25 $15 $0 $0 $0 $40 Community Development TOTAL: $20 $275 $15 $0 $0 $0 $310 Electric Electric Distribution System Improvements $1,250 $1,000 $1,275 $1,000 $1,000 $1,000 $6,525 Electric Substation Improvements $355 $445 $395 $250 $20 $20 $1,485 Electric Technology Program $4,110 $3,462 $650 $703 $360 $413 $9,698 Facilities Expansion for New Loads and Services $715 $715 $665 $555 $555 $455 $3,660 II - 2

Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Street Light Improvement Program $310 $230 $180 $180 $180 $180 $1,260 Traffic Signal Control Replacement and Upgrade $1,350 $1,350 $1,350 $75 $25 $25 $4,175 Electric TOTAL: $8,090 $7,202 $4,515 $2,763 $2,140 $2,093 $26,803 Fire Department Fire Station 2 Property for relocation $300 $130 $1,220 $0 $0 $0 $1,650 Fire Station 3 Repair or replace Training Tower $50 $180 $0 $0 $0 $0 $230 Fire Department TOTAL: $350 $310 $1,220 $0 $0 $0 $1,880 Library Library Design Work $25 $0 $0 $0 $0 $0 $25 Library Renovation: Central Library $0 $25 $0 $0 $0 $0 $25 Library Renovations: East Wing $41 $0 $0 $0 $0 $0 $41 Library Renovations: West Wing $0 $0 $105 $0 $0 $0 $105 Library TOTAL: $66 $25 $105 $0 $0 $0 $195 Police Department Security Fencing for Police Department Parking Area $214 $0 $0 $0 $0 $0 $214 Police Department TOTAL: $214 $0 $0 $0 $0 $0 $214 Public Works Sewer Collection System Rehab/CMOM $2,016 $1,566 $1,050 $1,257 $4,130 $957 $10,975 Transportation/Pedestrian/Bicycle Safety $2,743 $1,250 $1,250 $0 $0 $0 $5,243 Improvements Turtle Park Wastewater Treatment Plant $1,130 $2,202 $1,988 $2,688 $2,102 $1,770 $11,880 Water Treatment Plant - Existing $1,230 $450 $0 $0 $0 $0 $1,680 Water Treatment Plant - New $21,500 $21,500 $0 $0 $0 $0 $43,000 Public Works TOTAL: $28,619 $26,968 $4,288 $3,945 $6,232 $2,727 $72,778 Public Works / Board of Education II - 3

Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total City / Schools Joint for Facilities $2,110 $1,074 $888 $665 $655 $1,315 $6,707 City / Schools Joint HVAC Projects $213 $237 $325 $282 $240 $270 $1,567 City / Schools Joint Roof Projects $300 $3,600 $1,480 $416 $335 $666 $6,797 Public Works / Board of Education TOT $2,623 $4,911 $2,693 $1,363 $1,230 $2,251 $15,071 Public Works/Fire Department Fire Station 2 Building Study $18 $0 $0 $0 $0 $0 $18 Public Works/Fire Department TOTAL: $18 $0 $0 $0 $0 $0 $18 Public Works/Library ADA compliant restrooms for Public Library $210 $0 $0 $0 $0 $0 $210 Public Works/Library TOTAL: $210 $0 $0 $0 $0 $0 $210 Recreation and Parks Briarcliff Park $0 $0 $0 $0 $60 $100 $160 Greenway Implementation $1,000 $3,074 $0 $0 $0 $0 $4,074 Groves Park $0 $0 $40 $150 $0 $100 $290 Oak Ridge Gateway $200 $200 $100 $0 $0 $0 $500 Outdoor Pool Renovation $0 $0 $500 $0 $0 $4,500 $5,000 Rowing Improvements $0 $200 $0 $0 $0 $0 $200 Solway Park $0 $0 $40 $0 $0 $200 $240 Recreation and Parks TOTAL: $1,200 $3,474 $680 $150 $60 $4,900 $10,464 TOTAL CAPITAL IMPROVEMENTS PROGRAM $54,806 $112,180 $20,768 $10,221 $19,062 $11,971 $229,008 II - 4

Capital Improvements Program - Capital Summary of Projects By Funding - ($000's)

Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Other State of TN Contribution Oak Ridge General Aviation Airport $3,667 $3,667 $3,667 $0 $0 $0 $11,000 Other State of TN Contribution $3,667 $3,667 $3,667 $0 $0 $0 $11,000 Anticipated CMAQ Grant Traffic Signal Control Replacement and Upgrade $1,000 $1,000 $1,000 $0 $0 $0 $3,000 Anticipated CMAQ Grant TOTAL $1,000 $1,000 $1,000 $0 $0 $0 $3,000 ARC Grant TN-18621-A Oak Ridge General Aviation Airport $4,628 $0 $0 $0 $0 $0 $4,628 ARC Grant TN-18621-A TOTAL: $4,628 $0 $0 $0 $0 $0 $4,628 Capital ADA compliant restrooms for Public Library $210 $0 $0 $0 $0 $0 $210 Capital TOTAL: $210 $0 $0 $0 $0 $0 $210 Capital Fund Library Renovations: West Wing $0 $0 $105 $0 $0 $0 $105 Capital Fund TOTAL: $0 $0 $105 $0 $0 $0 $105 Capital Funds City / Schools Joint for Facilities $2,110 $1,074 $888 $665 $655 $1,315 $6,707 City / Schools Joint HVAC Projects $213 $237 $325 $282 $240 $270 $1,567 City / Schools Joint Roof Projects $300 $3,600 $1,480 $416 $335 $666 $6,797 Capital Funds TOTAL: $2,623 $4,911 $2,693 $1,363 $1,230 $2,251 $15,071 Capital Projects Fund Briarcliff Park $0 $0 $0 $0 $60 $100 $160 Fire Station 2 Building Study $18 $0 $0 $0 $0 $0 $18 Fire Station 2 Property for relocation $300 $130 $1,220 $0 $0 $0 $1,650 Fire Station 3 Repair or replace Training Tower $50 $180 $0 $0 $0 $0 $230 II - 5

Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Groves Park $0 $0 $40 $150 $0 $100 $290 Library Design Work $25 $0 $0 $0 $0 $0 $25 Library Renovations: East Wing $41 $0 $0 $0 $0 $0 $41 Outdoor Pool Renovation $0 $0 $500 $0 $0 $4,500 $5,000 Rowing Improvements $0 $200 $0 $0 $0 $0 $200 Solway Park $0 $0 $40 $0 $0 $200 $240 Capital Projects Fund TOTAL: $434 $510 $1,800 $150 $60 $4,900 $7,854 CDBG National Register District Study/Amendments $0 $10 $0 $0 $0 $0 $10 CDBG TOTAL: $0 $10 $0 $0 $0 $0 $10 CDBG / COVID Funds Community Development Office Renovation $20 $250 $0 $0 $0 $0 $270 CDBG / COVID Funds TOTAL: $20 $250 $0 $0 $0 $0 $270 CWSRF Sewer Collection System Rehab/CMOM $1,000 $0 $0 $0 $3,380 $0 $4,380 Turtle Park Wastewater Treatment Plant $0 $2,052 $1,368 $2,538 $1,652 $1,620 $9,230 CWSRF TOTAL: $1,000 $2,052 $1,368 $2,538 $5,032 $1,620 $13,610 DOE Water Treatment Plant - Existing $615 $75 $0 $0 $0 $0 $690 DOE TOTAL: $615 $75 $0 $0 $0 $0 $690 Electric Electric Technology Program $2,470 $1,822 $642 $695 $352 $405 $6,386 Electric TOTAL: $2,470 $1,822 $642 $695 $352 $405 $6,386 Electric Fund Electric Distribution System Improvements $1,250 $1,000 $1,275 $1,000 $1,000 $1,000 $6,525 Electric Substation Improvements $355 $445 $395 $250 $20 $20 $1,485 Facilities Expansion for New Loads and Services $715 $715 $665 $555 $555 $455 $3,660 II - 6

Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Street Light Improvement Program $310 $230 $180 $180 $180 $180 $1,260 Traffic Signal Control Replacement and Upgrade $350 $350 $350 $75 $25 $25 $1,175 Electric Fund TOTAL: $2,980 $2,740 $2,865 $2,060 $1,780 $1,680 $14,105 FAA Contribution Oak Ridge General Aviation Airport $6,667 $6,667 $6,667 $0 $0 $0 $20,000 FAA Contribution TOTAL: $6,667 $6,667 $6,667 $0 $0 $0 $20,000 Federal/State/Other (80%)

Greenway Implementation $3,259 $0 $0 $0 $0 $0 $3,259 Federal/State/Other (80%) TOT $3,259 $0 $0 $0 $0 $0 $3,259 General Fund Library Renovation: Central Library $0 $25 $0 $0 $0 $0 $25 National Register District Study/Amendments $0 $15 $15 $0 $0 $0 $30 Security Fencing for Police Department Parking Area $214 $0 $0 $0 $0 $0 $214 General Fund TOTAL: $214 $40 $15 $0 $0 $0 $269 General Obligation Bonds Linden Elementary School $0 $10,223 $0 $0 $0 $0 $10,223 New West End School $0 $23,700 $0 $0 $0 $0 $23,700 Robertsville Middle School $0 $0 $0 $2,000 $9,400 $0 $11,400 General Obligation Bonds TOTA $0 $33,923 $0 $2,000 $9,400 $0 $45,323 GF Court Room Improvements $50 $550 $150 $0 $0 $0 $750 GF TOTAL: $50 $550 $150 $0 $0 $0 $750 ARC Grant TN- 18621-C1-302-20 Oak Ridge General Aviation Airport $0 $1,200 $800 $0 $0 $0 $2,000 ARC Grant TN- 18621-C1-302-20 $0 $1,200 $800 $0 $0 $0 $2,000 Grants Transportation/Pedestrian/Bicycle Safety Improvements $2,718 $1,250 $1,250 $0 $0 $0 $5,218 Grants TOTAL: $2,718 $1,250 $1,250 $0 $0 $0 $5,218 II - 7

Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total TN Aeronautics Economic Development Oak Ridge General Aviation Airport $5,000 $5,000 $5,000 $0 $0 $0 $15,000 TN Aeronautics Economic Devel $5,000 $5,000 $5,000 $0 $0 $0 $15,000 TN Aeronautics Economic Development Oak Ridge General Aviation Airport $367 $367 $367 $0 $0 $0 $1,100 TN Aeronautics Economic Devel $367 $367 $367 $0 $0 $0 $1,100 TN Aeronautics Economic Development Oak Ridge General Aviation Airport $367 $367 $367 $0 $0 $0 $1,100 TN Aeronautics Economic Devel $367 $367 $367 $0 $0 $0 $1,100 Matching Funds (City)/ADA Match Transportation/Pedestrian/Bicycle Safety Improvements $25 $0 $0 $0 $0 $0 $25 Matching Funds (City)/ADA Mat $25 $0 $0 $0 $0 $0 $25 Capital Projects Fund (20%)

Greenway Implementation $815 $0 $0 $0 $0 $0 $815 Capital Projects Fund (20%) TOT $815 $0 $0 $0 $0 $0 $815 SRF (30 year loan) 51%

Water Treatment Plant - New $10,965 $10,965 $0 $0 $0 $0 $21,930 SRF (30 year loan) 51% TOTAL: $10,965 $10,965 $0 $0 $0 $0 $21,930 TDOT Oak Ridge Gateway $200 $200 $100 $0 $0 $0 $500 TDOT TOTAL: $200 $200 $100 $0 $0 $0 $500 Water/Sewer Electric Technology Program $1,640 $1,640 $8 $8 $8 $8 $3,312 Water/Sewer TOTAL: $1,640 $1,640 $8 $8 $8 $8 $3,312 Waterworks Fund Sewer Collection System Rehab/CMOM $1,016 $1,566 $1,050 $1,257 $750 $957 $6,595 Turtle Park Wastewater Treatment Plant $1,130 $150 $620 $150 $450 $150 $2,650 Water Treatment Plant - Existing $615 $375 $0 $0 $0 $0 $990 Waterworks Fund TOTAL: $2,761 $2,091 $1,670 $1,407 $1,200 $1,107 $10,235 II - 8

Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total WIFIA (35 year loan) 49%

Water Treatment Plant - New $10,535 $10,535 $0 $0 $0 $0 $21,070 WIFIA (35 year loan) 49% TOTAL $10,535 $10,535 $0 $0 $0 $0 $21,070 TOTAL CAPITAL IMPROVEMENTS PROGRAM $65,227 $91,830 $30,532 $10,221 $19,062 $11,971 $228,844 II - 9

Capital Improvements Program - Capital Summary of Placeholder Projects By Responsible Department - ($000's)

Project Placeholder Board of Education Glenwood Elementary School $5,348 Willow Brook Elementary School $2,300 Woodland Elementary School $7,300 Board of Education TOTAL: $14,948 Community Development Downtown Oak Ridge Streetscape Improvements $280 Community Development TOTAL: $280 Electric Long Term Electric System Needs $11,500 Electric TOTAL: $11,500 Public Works New Sidewalk Construction $100 Rarity Ridge Wastewater Treatment Plant $3,000 Public Works TOTAL: $3,100 Recreation and Parks Bobby Hopkins Baseball Field $350 Melton Lake Park $450 Neighborhood Park with Designated Areas for Skateboarding & Rollerblading $220 Pinewood Park $250 Westwood Park $340 Wolfe Creek Park $270 Recreation and Parks TOTAL: $1,880 TOTAL CAPITAL IMPROVEMENTS PROGRAM $31,708 II - 10

Board of Education Capital Improvements Program - Capital Summary of Projects - ($000's) Board of Education Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Board of Education Linden Elementary School $0 $10,223 $0 $0 $0 $0 $10,223 New West End School $0 $23,700 $0 $0 $0 $0 $23,700 Renovation of Jefferson Middle School $0 $0 $0 $0 $0 $0 $0 Replace School Administration Building $0 $0 $0 $0 $0 $0 $0 Robertsville Middle School $0 $0 $0 $2,000 $9,400 $0 $11,400 TOTALS $0 $33,923 $0 $2,000 $9,400 $0 $45,323 III - 1

Project: Linden Elementary School Project Type: Capital Program: Schools Responsible Department: Board of Education Project Origination: 2010 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description Linden Elementary School was constructed in 1968 with a small renovation 1998 for ADA improvements and a stage addition to the gymnasium. The school serves K-4th grades and has had an increase in student enrollment in recent years. Linden was originally constructed with an open format which was later changed to individual classrooms by the addition of walls in each grade level pod. All traffic enters the site from a single access road which causes considerable difficulty with bus and parent traffic trying to access the site at the same time and backing up on Robertsville Road.

Status Linden was originally constructed with an open format which was later changed to individual classrooms by the addition of walls in each grade level pod. The new spaces do not meet current fire and life safety code regulations and will need to be redesigned to eliminate the open plenum ceiling, provide return air ductwork for the HVAC system, and extend the walls to the roof/ceiling deck. All life safety systems will need to be upgraded, the electrical systems are insufficient for current needs, administration and guidance areas do not meet present day educational standards, special areas are undersized or designs are outdated. Doors, windows, interior finishes, exterior parking and site access need improvement.

Justification Linden Elementary School was evaluated utilizing the facility study completed in 2007 by Cope and Associates Inc. An updated facility study completed in 2020 indicates that many deficiencies remain and will require remediation in the near future to maintain proper code compliance.

Their recommendation called for a 10.2 million renovation using 2020 construction costs and known deficiencies. An in-depth study and construction estimate would have to be performed prior to project approval to determine actual costs.

Complies with Policies: F-1, F-16, P-12, P-13, Q-6, Q-9, and Q-12 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Renovation of Linden $0 $10,223 $0 $0 $0 $0 $10,223 Elementary School TOTAL EXPENDITURES $10,223 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder General Obligation Bonds $0 $10,223 $0 $0 $0 $0 $10,223 TOTAL FUNDS $10,223 III - 2

Project: New West End School Project Type: Capital Program: Schools Responsible Department: Board of Education Project Origination: 2020 Project Status: New Project Budgeted:

Project Completion: Commission Status: New Description A new K-4 school is needed on the West end of the city to accommodate the growth anticipated over the next 4 years and to reduce the overcrowding in the current two west end schools, Linden and Willow Brook.

Status A location and design is needed as other adjustments to district facilities are implemented to handle the student enrollment growth until a new facility is constructed.

Justification A capacity study in conjunction with the facility study was completed in 2020 by Cope and Associates. The study used current growth projections as well as data collected from housing developers with projects in construction or planning phases and information from the City Community Development Department. An estimated cost of $23.7 million for a 400 student K - 4th grade facility is planned for in the school's facility / capacity study.

Complies with Policies: L-16, F-15, F-16, P-2, Q-11, Q-12, & M-2 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder New West End K - 4th Grade $0 $23,700 $0 $0 $0 $0 $23,700 $0 School TOTAL EXPENDITURES $23,700 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder General Obligation Bonds $0 $23,700 $0 $0 $0 $0 $23,700 $0 TOTAL FUNDS $23,700 III - 3

Project: Renovation of Jefferson Middle School Project Type: Capital Program: Schools Responsible Department: Board of Education Project Origination: 2010 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description Jefferson Middle School was constructed in 1968 with a major addition in 1994 to incorporate a new grade level. This school like Robertsville serves 5th through 8th grade. The school has need of additional parking space to accommodate sporting events and programs. The gymnasium has bleachers on one side and the little theater is in need of upgrades in stage size. The Administration offices, located on the second level, are not ideally located to provide for current security needs. Structurally the building is sound but doors, windows, and interior finishes need to be upgraded to meet current code, educational, or design standards.

Status Some of the original mechanical systems have been upgraded while some still remain. A large portion of the ACBMs have been removed but, some quantities still remain. Upgrades in electrical, mechanical, and data systems are still needed as well as renovations to meet current life safety codes, building and fire codes, ADA, and 21st century classroom standards. Regular maintenance and some capital maintenance projects have improved this facilitys IAQ and energy management, but this facility is still in need of a major renovation to address long term issues.

Justification The Jefferson Middle School facility was evaluated utilizing the facility study completed in 2007 and re-evaluated in 2020 by Cope and Associates Inc. Their recommendations call for a 12.2 million dollar renovation using 2020 construction costs and known deficiencies. The updated facility study indicates that several deficiencies remain and additional space may be required in the future to address a growing student population and changes in educational programming needs. An in-depth study and construction estimate would have to be performed prior to project approval to determine actual costs.

Complies with Policies: F-1, F-16, P-12, P-13, Q-6, Q-9, and Q-12 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Renovation of JMS Design $0 $0 $0 $0 $200 Renovation of JMS $0 $0 $0 $0 $0 $0 $0 $12,200 Construction TOTAL EXPENDITURES $0 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder General Obligation Bonds $0 $0 $0 $0 $12,400 TOTAL FUNDS III - 4

Project: Replace School Administration Building Project Type: Capital Program: Schools Responsible Department: Board of Education Project Origination: 2005 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description The School Administration Building, housed in the old Pine Valley School, is a WW II vintage facility in the Oak Ridge School system that has been renovated, remodeled, and expanded at least six times and has exceeded its useful life. The original building was not intended to be a long term facility, and due to its wood frame type construction does not lend itself to another major renovation to correct numerous Life Safety Code and ADA deficiencies. In addition this facility is at a point that does not allow for additional expansion of technology, electrical needs, or parking needs.

Status A programming and Master Plan Study of the School Administration Building was completed By Barber and McMurry, Inc. during FY 2000. The plan evaluated current space requirements and building deficiencies, provided concepts for site options, and gave an estimated cost for implementation of the plan. Also, an architectural study was completed for the Preschool and Alternative School programs, but with failure of a referendum, the projects were tabled pending available funding. In 2007, Cope and Associates Inc. completed a facility study for all the facilities in the Oak Ridge Schools except for the High School, which was under construction. The findings by Cope and Associates indicated that significant to critical deficiencies existed in the School Administration and Preschool program and in the physical conditions of the buildings.

Their recommendation echoed the same recommendations of the earlier study from 2000, that it would be more cost effective to abandon the current facility and seek a new or remodeled facility.

Justification The present School Administration Building is housed in the old Pine Valley School, constructed in 1944. The wood frame building is at a stage where major systems including electric, flooring, exterior siding, windows and doors, HVAC systems, plumbing, and fire and life safety systems are nearing or have exceeded their useful life. An in-depth study and construction estimate would have to be performed prior to project approval. Past delays in approval of these projects have only increased long term costs. Future delays will require not only additional construction costs but, will also increase the risk of health and safety problems for the occupants of this facility.

Complies with Policies: F-1, F-16, Q-6, Q-9, Q-12, P-12, and P-13 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Preschool Arch. & Eng. $0 $0 $0 $0 $0 $0 $0 $0 Admin. Bldg. Arch. & Eng. $0 $0 $0 $0 $0 $0 $0 $500 New/Renovation of Preschool $0 $0 $0 $0 $0 $0 $0 $0 Replace School $0 $0 $0 $0 $0 $0 $0 $6,800 Administration Building TOTAL EXPENDITURES $0 III - 5

Project: Replace School Administration Building Project Type: Capital Program: Schools Responsible Department: Board of Education Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder City bond issue $0 $0 $0 $0 $0 $0 $0 $7,300 TOTAL FUNDS $0 III - 6

Project: Robertsville Middle School Project Type: Capital Program: Schools Responsible Department: Board of Education Project Origination: 2010 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description Robertsville Middle School was originally constructed in 1953 with a major addition in 1994. This facility has had many of the original systems from 1953 replaced or upgraded, but serious and significant deficiencies are yet to be addressed and would be cost prohibitive in any project short of a major renovation. The building is in need of plumbing, electrical, mechanical, and technology upgrades to meet current 21st century classroom standards. Due to the age of the facility, it is known to have asbestos containing building materials (ACBMs) that will also require remediation during any future construction project. Guidance, administration, faculty parking, special areas, fire and life safety systems, and science programs are some of the areas known to be deficient in programming or current code standards. Additional room space may be needed in the near future to accommodate student growth in the city.

Status The 2007 and 2020 facility studies noted many issues including, the middle school science program working in classrooms designed for 1953 and even with minor changes made over the years; it is still inefficient for teaching modern lab technique and effectively incorporating technology.

Regular maintenance and some capital maintenance projects have aided this facility in improving its IAQ, energy management. The student lockers, science lab casework, and Auditorium seats and lights are vintage and need replacement. Additional space is needed for Administration, CDC, the Media Center, and classrooms for anticipated growth in student enrollment.

Justification The Robertsville Middle School facility was evaluated utilizing the facility study completed in 2007 and again in 2020 by Cope and Associates Inc. Their recommendation called for a 9.4 million dollar renovation using 2020 construction costs and known deficiencies. An in-depth study and construction estimate would have to be performed prior to project approval to determine actual costs. An updated facility study indicates some deficiencies still exist and space for expected student growth may be required.

Complies with Policies: F-1, F-16, P-12, P-13, Q-6, Q-9, and Q-12 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Renovation of RMS Design $0 $0 $0 $2,000 $0 $0 $2,000 $0 Renovation of RMS $0 $0 $0 $0 $9,400 $0 $9,400 $0 Construction TOTAL EXPENDITURES $11,400 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder General Obligation Bonds $0 $0 $0 $2,000 $9,400 $0 $11,400 $0 TOTAL FUNDS $11,400 III - 7

Board of Education Placeholder Projects

Capital Improvements Program - Capital Summary of Placeholder Projects By Responsible Department - ($000's)

Project Placeholder Board of Education Glenwood Elementary School $5,348 Willow Brook Elementary School $2,300 Woodland Elementary School $7,300 Board of Education TOTAL: $14,948 TOTAL CAPITAL IMPROVEMENTS PROGRAM $14,948 III - 8

Project: Glenwood Elementary School Project Type: Capital Program: Schools Responsible Department: Board of Education Project Origination: 2010 Project Status: Placeholder Project Budgeted:

Project Completion: 0 Commission Status:

Description Glenwood Elementary School construction began in 1988 and was completed in 1991. No additions have taken place but a major HVAC renovation was completed in 2007 which upgraded the system to current code standards for IAQ and energy management.

Status Evaluations by Cope and Associates indicate the facility is in need of additional space in the Media Center, special area classes, administration, and an update to the restrooms for ADA compliance.

Justification Glenwood Elementary School was evaluated utilizing the facility study completed in 2007 by Cope and Associates Inc. An updated facility study completed in 2020 indicates many deficiencies still exist and space may need to be added to meet program requirements. Their recommendation calls for a 5.3 million renovation using 2020 construction costs and known deficiencies. An in-depth study and construction estimate would have to be performed prior to project approval to determine actual costs.

Complies with Policies: F-1, F-16, P-12, P-13, Q-6, Q-9, and Q-12 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Renovation of Glenwood $0 $0 $0 $0 $0 $0 $0 $5,348 School TOTAL EXPENDITURES $0 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder General Obligation Bonds $0 $0 $0 $0 $0 $0 $0 $5,348 TOTAL FUNDS $0 III - 9

Project: Willow Brook Elementary School Project Type: Capital Program: Schools Responsible Department: Board of Education Project Origination: 2010 Project Status: Placeholder Project Budgeted:

Project Completion: 0 Commission Status:

Description Willow Brook Elementary School was originally constructed in 1949 with an addition and major renovation in 1990. Two portables were added in 2010 to provide for the increasing student enrolment and programming needs. This school operates on a balanced calendar with intercession programs between the grading periods.

Status The kitchen and cafeteria are vastly undersized for the number of student lunches prepared and served each day. Also the cafeteria doubles as the space used for before and after school care which limits that programs effectiveness and places a burden on the staff to clean and prepare the area each morning and afternoon for the next program needs. The Media Center, administration, guidance, special area, parking, parent and student drop off; need design upgrades and improvements to meet current education and code requirements. This facility also needs improvements in electrical, mechanical, and data systems to address code or program deficiencies. Expected student growth and the use of aging portable classrooms may require a future addition to meet student needs.

Justification The Willow Brook Elementary School facility was evaluated utilizing the facility study completed in 2007 by Cope and Associates Inc. An updated facility study completed in 2020 indicates the need for possible expansion due to expected student population and lack of program space. The recommendation calls for a 4.2 million dollar renovation and expansion using 2020 construction costs and known deficiencies. An in-depth study and construction estimate would have to be performed prior to project approval to determine actual costs.

Complies with Policies: F-1, F-16, P-12, P-13, Q-6, Q-9, and Q-12 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Renovation of Willow Brook $0 $0 $0 $0 $2,000 $0 $2,000 $2,300 Design Renovation of Willow Brook $0 $0 $0 $0 $0 $4,200 $4,200 $0 School Construction TOTAL EXPENDITURES $6,200 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder General Obligation Bonds $0 $0 $0 $0 $2,000 $0 $2,000 $2,300

$0 $0 $0 $0 $0 $4,200 $4,200 $0 TOTAL FUNDS $6,200 III - 10

Project: Woodland Elementary School Project Type: Capital Program: Schools Responsible Department: Board of Education Project Origination: 2010 Project Status: Placeholder Project Budgeted:

Project Completion: 0 Commission Status:

Description The Woodland Elementary School building was originally constructed in 1948 and has undergone many renovations and expansions over the years. This facility, located in the Woodland community currently utilizes portable classrooms to accommodate the existing programs. Also, due to the increasing enrollment numbers at this facility, several special area classes, the cafeteria, kitchen, media center, guidance, administration, technology, parking, building storage , and drop off and pick up areas are inadequate for current program needs.

Status The last major renovation that impacted the learning environment was conducted in 1988. A renovation to the building façade and correction of some structural issues was performed in 2010. Space continues to be an ongoing issue with a portable classroom being utilized for additional classroom and program functions. The size of the cafeteria places a burden on the school to be able to serve the current size student body within a reasonable timeframe. Parking and student drop off areas are inadequate which causes considerable traffic backup along Manhattan Avenue.

Justification The Woodland School facility was evaluated utilizing the facility study completed in 2007 by Cope and Associates Inc. An updated facility study performed in 2020 indicates that the current building may need an addition and renovation to meet expected student population growth and programming needs. Their recommendation calls for a 7.3 million renovation using 2020 construction costs and known deficiencies. An in-depth study and construction estimate would have to be performed prior to project approval to determine actual costs.

Complies with Policies: F-1, F-16, P-12, P-13, Q-6, Q-9, and Q-12 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Renovation of Woodland $0 $0 $0 $0 $0 $0 $0 $7,300 School TOTAL EXPENDITURES $0 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder General Obligation Bonds $0 $0 $0 $0 $0 $0 $0 $7,300 TOTAL FUNDS $0 III - 11

City Clerk Capital Improvements Program - Capital Summary of Projects - ($000's) City Clerk Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total City Clerk Court Room Improvements $50 $550 $150 $0 $0 $0 $750 TOTALS $50 $550 $150 $0 $0 $0 $750 IV - 1

Project: Court Room Improvements Project Type: Capital Program: City Clerk Responsible Department: City Clerk Project Origination: 2019 Project Status: New Project Budgeted: 750 Project Completion: 2023 Commission Status: New Description Renovate Municipal Building Courtroom to maximize its usefulness for all City, Municipal Court and School Board functions, and enhance safety and comfort of all users. Improvements will increase meeting efficiency, and significantly enhance transparency and communications with the public.

Status Technology, security, and general FF&E improvements have not kept up with current standards.

Justification Changes are needed due to the elimination of state requirements for cable companies to negotiate cable franchise agreements with individual local governments. This action results in a need to create greater efficiencies with the assignment of Public, Educational, and Government access (PEG) channels for municipal and school programming. This project will target resources to improve overall meeting effectiveness and communications with public/taxpayers for the city and school board. The project includes improvements to security of users and equipment.

Complies with Policies: F-11 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Design $50 $0 $0 $0 $0 $0 $50 $0 Technology Upgrades $0 $200 $100 $0 $0 $0 $300 $0 Security Upgrades $0 $200 $50 $0 $0 $0 $250 $0 FF&E $0 $0 $0 $0 $0 $0 $0 $0

$0 $150 $0 $0 $0 $0 $150 $0 TOTAL EXPENDITURES $750 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder GF $50 $550 $150 $0 $0 $0 $750 $0 TOTAL FUNDS $750 IV - 2

City Manager's Office Capital Improvements Program - Capital Summary of Projects - ($000's) City Manager's Office Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total City Manager's Office Oak Ridge General Aviation Airport $13,347 $34,542 $7,103 $0 $0 $0 $54,992 TOTALS $13,347 $34,542 $7,103 $0 $0 $0 $54,992 V-1

Project: Oak Ridge General Aviation Airport Project Type: Capital Program: Responsible Department: City Manager's Office Project Origination: 2021 Project Status: New Project Budgeted:

Project Completion: Commission Status:

Description In August 2020, the City became the primary sponsor of the planning, design, and construction of an Oak Ridge General Aviation Airport to be built at the East Tennessee Technology Park. Previously, the Metropolitan Knoxville Airport Authority (MKAA) was the primary sponsor, but after discussion with the City and Federal Aviation Administration (FAA), MKAA determined it was in the best interest of the project to transfer sponsorship to the City. In July 2020, the City Council approved a resolution supporting the City taking over sponsorship, as well as giving the City Manager the authority to execute various contracts, agreements, work, etc. required as sponsor of the project.

Status The Benefit-Cost Analysis (BCA) is being reviewed by the FAA. The project has secured funding sources in the form of grants from the Appalachian Regional Commission and the Tennessee Department of Transportation Aeronautics Divisions Aeronautics Economic Development Fund.

Justification As identified in the BCA, a general aviation airport constructed in Oak Ridge is the ideal solution to increase the available air capacity of the area.

Analysis has shown that increasing hangar capacity at McGee-Tyson Airport is not feasible without substantial renovation and property acquisition due to space limitations at the location. Expansion of the Downtown-Island Home Airport in Knoxville is impossible due to its location on an island in the Tennessee River. A general aviation airport would serve the community and business interests of the city and would also help support the Department of Energy operations at Y-12 and Oak Ridge National Laboratory. A number of existing companies in the area have expressed interest in utilizing the proposed airport, and many others have identified the airport project as a key feature attracting them to potentially move to Oak Ridge.

Complies with Policies: T-14 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Environmental and $13,347 $0 $0 $0 $0 $0 $13,347 $0 Engineering Study/Permits Earth Work $0 $23,888 $0 $0 $0 $0 $23,888 $0 Construction $0 $10,654 $7,103 $0 $0 $0 $17,757 $0 TOTAL EXPENDITURES $54,992 V-2

Project: Oak Ridge General Aviation Airport Project Type: Capital Program: Responsible Department: City Manager's Office Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder TN Aeronautics Economic $5,000 $5,000 $5,000 $0 $0 $0 $15,000 $0 Development Fund FY2018 Grant TN Aeronautics Economic $367 $367 $367 $0 $0 $0 $1,100 $0 Development Fund FY2019 Grant TN Aeronautics Economic $367 $367 $367 $0 $0 $0 $1,100 $0 Development Fund FY2020 Grant ARC Grant TN-18621-A $4,628 $0 $0 $0 $0 $0 $4,628 $0 ARC Grant TN- 18621-C1-302- $0 $1,200 $800 $0 $0 $0 $2,000 $0 20 FAA Contribution $6,667 $6,667 $6,667 $0 $0 $0 $20,000 $0 Other State of TN $3,667 $3,667 $3,667 $0 $0 $0 $11,000 $0 Contribution TOTAL FUNDS $54,828 V-3

Community Development Capital Improvements Program - Capital Summary of Projects - ($000's) Community Development Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Community Development Community Development Office Renovation $20 $250 $0 $0 $0 $0 $270 National Register District Study/Amendments $0 $25 $15 $0 $0 $0 $40 TOTALS $20 $275 $15 $0 $0 $0 $310 VI - 1

Project: Community Development Office Renovation Project Type: Capital Program: Responsible Department: Community Development Project Origination: 2019 Project Status: New Project Budgeted: 270 Project Completion: 2023 Commission Status: New Description Redesign and construct office configuration for building security, office efficiency, and citizen/customer service improvement.

Status Office configuration and use has evolved over many years.

Justification Existing configuration is no longer relevant or efficient for current use and needs, especially in terms of security and customer service.

Complies with Policies: F-11 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Desgin $20 $0 $0 $0 $0 $0 $20 $0 Construction $0 $200 $0 $0 $0 $0 $200 $0 FF&E $0 $50 $0 $0 $0 $0 $50 $0 TOTAL EXPENDITURES $270 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder CDBG / COVID Funds $20 $250 $0 $0 $0 $0 $270 $0 TOTAL FUNDS $270 VI - 2

Project: National Register District Study/Amendments Project Type: Capital Program: Responsible Department: Community Development Project Origination: 2019 Project Status: New Project Budgeted: 40 Project Completion: 2024 Commission Status: New Description Review history of National Register District development and analyze most effective approach to district boundary. Initiate inventory update as basis for redistricting consideration.

Status Inventory and district creation were done in 1991 a great deal of change has occurred in historic neighborhoods since that time. The district definition may need to be amended in light of changes that now make some areas ineligible or inappropriate for designation.

Justification Many homes have been significantly modified and/or deteriorated to the point that they are no longer eligible or able to be renovated.

Blighted homes that cannot or will not be improved are, in some cases, causing significant neighborhood deterioration and negatively impacting intact historic properties nearby.

Complies with Policies: Q-5, Q-7 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Inventory $0 $15 $0 $0 $0 $0 $15 $0 District Boundary Analysis $0 $10 $0 $0 $0 $0 $10 $0 and Recommendation Boundary Change Application $0 $0 $15 $0 $0 $0 $15 $0 TOTAL EXPENDITURES $40 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder General Fund $0 $15 $15 $0 $0 $0 $30 $0 CDBG $0 $10 $0 $0 $0 $0 $10 $0 TOTAL FUNDS $40 VI - 3

Community Development Placeholder Projects

Capital Improvements Program - Capital Summary of Placeholder Projects By Responsible Department - ($000's)

Project Placeholder Community Development Downtown Oak Ridge Streetscape Improvements $280 Community Development TOTAL: $280 TOTAL CAPITAL IMPROVEMENTS PROGRAM $280 VI - 4

Project: Downtown Oak Ridge Streetscape Improvements Project Type: Capital Program: Responsible Department: Community Development Project Origination: Project Status: Placeholder Project Budgeted: 280 Project Completion: 2023 Commission Status: New Description Functional and Aesthetic streetscape improvements to support the Downtown Oak Ridge vision and private investment.

Status Plan completed. Private investment being solicited.

Justification Ehancement to street, sidewalks, intersections, etc. will be a necessary part of fostering private development investment in our downtown.

Complies with Policies: E-3, E-6, L-2 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Design $0 $0 $0 $0 $0 $0 $0 $30 Sidewalks, Crosswalks, $0 $0 $0 $0 $0 $0 $0 $250 Parking, etc.

$0 $0 $0 $0 $0 $0 $0 $0 TOTAL EXPENDITURES $0 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Oak Ridge Land Bank $0 $0 $0 $0 $0 $0 $0 $280 Potential TDOT Funding $0 $0 $0 $0 $0 $0 $0 $0 TOTAL FUNDS $0 VI - 5

Electric Capital Improvements Program - Capital Summary of Projects - ($000's) Electric Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Electric Electric Distribution System Improvements $1,250 $1,000 $1,275 $1,000 $1,000 $1,000 $6,525 Electric Substation Improvements $355 $445 $395 $250 $20 $20 $1,485 Electric Technology Program $4,110 $3,462 $650 $703 $360 $413 $9,698 Facilities Expansion for New Loads and Services $715 $715 $665 $555 $555 $455 $3,660 Street Light Improvement Program $310 $230 $180 $180 $180 $180 $1,260 Traffic Signal Control Replacement and Upgrade $1,350 $1,350 $1,350 $75 $25 $25 $4,175 TOTALS $8,090 $7,202 $4,515 $2,763 $2,140 $2,093 $26,803 VII - 1

Project: Electric Distribution System Improvements Project Type: Capital Program: Utilities Responsible Department: Electric Project Origination: 2005 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description This project provides for the upgrade of existing system components, including conductors, underground service vaults, and the addition of specific protection devices. It describes non-routine work done by the department to rectify identified inadequacies, along with items required to enhance system performance.

Status All circuits are continually monitored for overloading, deterioration or other conditions that require updating. Cost are included for this.

The underground replacement program continues to be a major project. There has been an increase in pole replacement and spacer cable replacement that is resulting in a short term spike in this cost area.

Justification Line segments, both overhead and underground, are routinely evaluated via the Departments system model for potential use in switching operations, alternate feeds and line loss; as well as age, condition and functionality. A large effort for pole replacement is underway. Other structures, particularly underground vaults, need to be upgraded. With new equipment installed, annual operating costs should decrease and system safety improved.

Complies with Policies: F-1 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Circuit Improvement $450 $300 $300 $300 $300 $300 $1,950 $0 Underground Cable $550 $450 $450 $450 $450 $450 $2,800 $0 Replacement Site Specific Automation $250 $250 $250 $250 $250 $250 $1,500 $0 Clinch River Crossing $0 $0 $275 $0 $0 $0 $275

$0 TOTAL EXPENDITURES $6,525 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Electric Fund $1,250 $1,000 $1,275 $1,000 $1,000 $1,000 $6,525 $0 TOTAL FUNDS $6,525 VII - 2

Project: Electric Substation Improvements Project Type: Capital Program: Utilities Responsible Department: Electric Project Origination: 2004 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description This project allows for equipment upgrades and replacement in substations.

Status Replacement of protective relays continues with a view toward standardization and future electronic (SCADA) control. New voltage regulator controls are being examined as well as various communication equipment. Broadband communications and improved security systems are enhancing the stations and preparing them for the future volt/VAR control. In 2022 selected 13KV breakers will be changed at Substations 400 and 700. Beginning in 2023, 69KV breakers installed in 1989 and 1990 will need to be changed out due to obsolescence.

Justification Without routine replacement, equipment in substations becomes antiquated and then obsolete. Replacement parts become expensive and then unavailable. Replacement equipment has a higher reliability and extensive communication ability which can be used in a SCADA and Volt/VAR controlled environment. Some older metering equipment and relays require replacement. The enhancements in communications and control will also provide a gateway into better security for the facilities.

Complies with Policies: F-1, F-9, PH-12, and Q-6 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Security Upgrades $50 $50 $0 $0 $0 $0 $100 $0 Switch House Meter Upgrade $45 $45 $45 $0 $0 $0 $135 $0 Communication Equipment $100 $100 $100 $0 $0 $0 $300 $0 (SCADA Ready)

Routine Equipment $160 $250 $250 $250 $20 $20 $950 $0 Replacement TOTAL EXPENDITURES $1,485 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Electric Fund $355 $445 $395 $250 $20 $20 $1,485 $0 TOTAL FUNDS $1,485 VII - 3

Project: Electric Technology Program Project Type: Capital Program: Utilities Responsible Department: Electric Project Origination: 2005 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description This item supports the implementation of the Electric Department Technology Roadmap. The roadmap was designed to provide an orderly path forward for implementation of areas of Engineering, Operational Control and accommodation of changing industry models. Focus areas include Network Reliability, Staking and Mapping, SCADA, Substation Automation, Peak Demand Reduction, Automatic Meter Infrastructure and Outage Management. Details are included in roadmap documents.

Status The Technology Roadmap has been aligned with schedules that recognize available resources.

Plans have been developed for a server room at the CSC to accommodate necessary servers and associated equipment. An RFI for both SCADA vendors is expectedby Spring 2020. Proposals for the AMI system have been received. Vendors for engineering software have been selected and integration issues discussed. The fiber optic ring is functioning and being used by both the City general government, schools and utilities at some substations. Substation automation is nearing completion at Substations 400 and 900. Distributed automation systems are in place and operating at two locations with a third nearing completion.

For 2021:

Substation Automation should be completed at Substations 100, 200, 300, 400 and 900. Work will begin on Substation 600.

The new data center, servers, backup systems and security systems including cyber defense systems were delayed due to Covid-19 impacts, but are on track for FY2022.

Operation Technology Upgrades should include operating two to four substations under the existing control systems while selecting the SCADA software vendor and beginning installation.

Advanced Metering Infrastructure AMI pilot programshould begin Summer of 2021.

A new distributed automation (tele-team) project should be brought on line for Bethel Valley Industrial Park.

Sensors should be selected for the 69kV system.

Details of future years are included in the Technology Roadmap document.

Justification Changes in the electric landscape are necessitating upgrades to the technology associated with monitoring, control and billing of electric power.

For example, TVA has already placed Oak Ridge on a Wholesale Time of Use Rate (TOU) that rewards demand reduction through voltage control and direct load control. TVA is supporting a push toward retail TOY programs and has already issued strong economic incentives for adoption of retail TOU, especially in the industrial area.Special rates, such as those for electric transportation, are under development VII - 4

Project: Electric Technology Program Project Type: Capital Program: Utilities Responsible Department: Electric The upgrade of billing software, and the addition of SCADA and Remote Metering will be required for us to participate in and benefit from these new rates. Failure to offer them will place Oak Ridge at a disadvantage, both from an economic development and job retention standpoint.

In addition to savings for our customers overall, other benefits include replacement of obsolete equipment and software, removing limitations inherent in the systems; smoother integration of distributed and renewable resurces into the system; push notifications to customers of unusual events such as leaks or unusual electric use at customer's premises; better employee safety through customer handling; providing available alternatives to disconnect for non-payment through a pre-payment or similar program; and reduction of carbon emissions through reduced truck rolls and energy efficiency.

Most importantly, however, is that this program will position the City of Oak Ridge to be able to respond to future mandates and benefit from economic incentives necessary for us to operate in the modern energy market, enabling us to provide savings and increased levels of service on to our customers.

Complies with Policies: F-1, F-9, PH-12, and Q-6 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Fiber Optic Ring Expansion $100 $50 $20 $20 $20 $20 $230 $0 Substation Automation $430 $302 $200 $223 $190 $20 $1,365 $0 Operational Network $585 $100 $15 $15 $40 $40 $795 $0 Operational Technology $140 $185 $40 $90 $40 $273 $768 $233 Advance Metering $2,780 $2,780 $15 $15 $15 $15 $5,620 $100 Infrastructure Transmission & Distribution $45 $45 $350 $340 $45 $45 $870 $85 Automation Testing Equipment $30 $0 $10 $0 $10 $0 $50 $0 TOTAL EXPENDITURES $9,698 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Electric $2,470 $1,822 $642 $695 $352 $405 $6,386 $0 Water/Sewer $1,640 $1,640 $8 $8 $8 $8 $3,312 $0 Other Funds $0 $0 $0 $0 $0 $0 $0 $0 TOTAL FUNDS $9,698 VII - 5

Project: Facilities Expansion for New Loads and Services Project Type: Capital Program: Utilities Responsible Department: Electric Project Origination: 2005 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description This item includes various elements of the Departments efforts to serve new loads with the exception of Substations and major feeder lines.

These include line extensions, construction within subdivisions and other such activities. Cost depends on development activity and should be treated as a place holder.

Status The cost and timelines for these projects are development driven, and thus difficult to predict. We have seen an uptick in residential expenditures and commercial expenditures are accelerating as well. These trends are anticipated to continue for the next three years. Re-evaluation of trends is an ongoing process.

Justification This expense is required to serve new loads under existing council policy. All cost expended in this item are protected by the City's justified investment policy, which should provide for cost recovery through the rate over time.

Complies with Policies: F-1, F-9, PH-12, and Q-6 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder UG Residential $450 $450 $400 $300 $300 $200 $2,100 $0 OH Residential $65 $65 $65 $55 $55 $55 $360 $0 UG Commercial $150 $150 $150 $150 $150 $150 $900 $0 OH Commercial $50 $50 $50 $50 $50 $50 $300 $0 TOTAL EXPENDITURES $3,660 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Electric Fund $715 $715 $665 $555 $555 $455 $3,660 $0 TOTAL FUNDS $3,660 VII - 6

Project: Street Light Improvement Program Project Type: Capital Program: Utilities Responsible Department: Electric Project Origination: 2005 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description This project provides for the correction of problems to improve the level of street lighting within the city. Current funding allows for minor improvements to critical need locations. Based on interest expressed in past years, an item has been added for "high-efficiency" and dark sky compliant lighting.

Status Street light improvements are ongoing, depending on needs. We plan to continue our replacement program at current funding levels. Melton Lake Drive improvements will be completed this year. Lighting is anticipated to be added on Laboratory Road and side streets in 2021.

Justification The Electric Department has a street light survey of the City and has policies and guidelines for street lighting. This program will address the street lights in areas with deteriorated or inadequate lighting. No money is included for significant new lighting, but a small extension of lighting is being considered in a developed section of the City.

Council and Planning Commission have expressed interest in dark skies, high-efficiency lighting. Funds are provided to support this interest.

Complies with Policies: F-1, F-9, PH-12, and Q-6 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Design & Construction $30 $30 $30 $30 $30 $30 $180 $0 High Efficiency Lighting $200 $200 $150 $150 $150 $150 $1,000 $0 Laboratory Road Area Lighting $80 $0 $0 $0 $0 $0 $80 $0 TOTAL EXPENDITURES $1,260 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Electric Fund $310 $230 $180 $180 $180 $180 $1,260 $0 TOTAL FUNDS $1,260 VII - 7

Project: Traffic Signal Control Replacement and Upgrade Project Type: Capital Program: Utilities Responsible Department: Electric Project Origination: 2015 Project Status: New Project Budgeted:

Project Completion: Commission Status:

Description This project will provide funding to replace existing traffic signal cabinets and controllers. A new communication system is also included. Some replacement or modification of traffic signal devices, such as the addition of pedestrian signals, is also anticipated.

Status The City has completed a major study of the traffic signal system. The study, in combination with staff experience, indicates that a major upgrade is required both of the signal controllers as well as the communication systems. Replacement of the system through grant funding is proceeding. Funding for any match from the grants will be included.

Justification Improvements in technology, ranging from vehicle detection to flow optimization have occurred over the last several years. These improved systems are currently being installed at selected intersections along ORTP. Replacement of the remainder of the 2000 era signal controllers is needed. A failing communication system along with outmoded controllers makes further optomization of traffic flow impossible.

Implementation of this plan will result in improved traffic flow in the City as well as improved provisions for bicycles and pedestrians.

Complies with Policies: N/A Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Traffic Signal Upgrades $350 $350 $350 $25 $25 $25 $1,125 $0 Traffic Signal System $1,000 $1,000 $1,000 $50 $0 $0 $3,050 $0 Replacement TOTAL EXPENDITURES $4,175 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Electric Fund $350 $350 $350 $75 $25 $25 $1,175 $0 Anticipated CMAQ Grant $1,000 $1,000 $1,000 $0 $0 $0 $3,000 $0 TOTAL FUNDS $4,175 VII - 8

Electric Placeholder Projects

Capital Improvements Program - Capital Summary of Placeholder Projects By Responsible Department - ($000's)

Project Placeholder Electric Long Term Electric System Needs $11,500 Electric TOTAL: $11,500 TOTAL CAPITAL IMPROVEMENTS PROGRAM $11,500 VII - 9

Project: Long Term Electric System Needs Project Type: Capital Program: Utilities Responsible Department: Electric Project Origination: 2005 Project Status: Placeholder Project Budgeted:

Project Completion: 0 Commission Status:

Description These projects reflect anticipated system needs that will be triggered by specific events or new loads, but which are unlikely over the next few years.

Status These projects are all conceptual in nature and awaiting need. Cost can vary significantly based on a number of factors.

Justification Transmission line project will improve reliability in remote areas such as extreme west end and provide alternate feeds for large loads.

Power transformer will be needed upon failure at Substation 600.

A remote substation might be required at any of several sites, depending on load distribution and nature.

Continued interest in the Heritage Center for large power users may require a station on site at that location.

Complies with Policies: F-1, F-9, PH-12, and Q-6 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Power Transformer $0 $0 $0 $0 $0 $0 $0 $2,500 Replacement Remote Substation $0 $0 $0 $0 $0 $0 $0 $4,000 Transmission System $0 $0 $0 $0 $0 $0 $0 $1,000 Expansion ETTP Substation $0 $0 $0 $0 $0 $0 $0 $4,000 TOTAL EXPENDITURES $0 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Electric Fund $0 $0 $0 $0 $0 $0 $0 $11,500 TOTAL FUNDS $0 VII - 10

Fire Department Capital Improvements Program - Capital Summary of Projects - ($000's) Fire Department Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Fire Department Fire Station 2 Property for relocation $300 $130 $1,220 $0 $0 $0 $1,650 Fire Station 3 Repair or replace Training Tower $50 $180 $0 $0 $0 $0 $230 TOTALS $350 $310 $1,220 $0 $0 $0 $1,880 VIII - 1

Project: Fire Station 2 Property for relocation Project Type: Capital Program: Relocation Fire Sta. Responsible Department: Fire Department Project Origination: 2016 Project Status: New Project Budgeted: 1650 Project Completion: Commission Status:

Description Acquire 2 acres of property for the relocation of fire station 2 in order to better serve the Southeast region of the city on or near Melton Lake Drive at the intersection of the Turnpike. A relocation study for that exact location will be conducted.

Status A relocation study for the exact location will be conducted. This is still in the planning stages at this point.

Justification There are currently several properties (homes and business property) outside the 5 mile response area on the southeast portion of the city.

Relocating fire station 2 further east/southeast of the current location will place all properties within the 5-mile response area. The relocation study will assist in determining the best location for station 2.

Complies with Policies: F-1 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Purchase of land $300 $0 $0 $0 $0 $0 $300 $0 New Station Design $0 $130 $0 $0 $0 $0 $130 $0 Construct New Station $0 $0 $1,220 $0 $0 $0 $1,220 $0 TOTAL EXPENDITURES $1,650 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund $300 $130 $1,220 $0 $0 $0 $1,650 $0 TOTAL FUNDS $1,650 VIII - 2

Project: Fire Station 3 Repair or replace Training Tower Project Type: Capital Program: Fire Training Tower Responsible Department: Fire Department Project Origination: 2019 Project Status: New Project Budgeted: 180 Project Completion: Commission Status: New Description The training tower is more than 20 years old and in need of major repairs. It needs an engineering study to determine if it can be repaired or needs to be torn down and replaced with a modern light weight type facility.

Status In 2019, Bender & Associates Structural Engineers conducted a structural assessment on the tower. The report recommended replacing the stairs and testing the slabs and walls prior to the provision of the stair design so that Bender could make a more informed decision regarding the stair, slabs, and the tower as a whole. GeoServices are scheduled to perform this work on Feb. 8, 2021. Once completed, a report will be sent to the city and Bender in order for them to finish their evaluation.

Justification The training tower is required to maintain the training and proficiency of our fire suppression staff.

Complies with Policies: F-1 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Study and design $50 $0 $0 $0 $0 $0 $50 $0 Construct $0 $180 $0 $0 $0 $0 $180 $0 TOTAL EXPENDITURES $230 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund $50 $180 $0 $0 $0 $0 $230 $0 TOTAL FUNDS $230 VIII - 3

VIII - 4 VIII - 5 Library Capital Improvements Program - Capital Summary of Projects - ($000's) Library Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Library Library Design Work $25 $0 $0 $0 $0 $0 $25 Library Renovation: Central Library $0 $25 $0 $0 $0 $0 $25 Library Renovations: East Wing $41 $0 $0 $0 $0 $0 $41 Library Renovations: West Wing $0 $0 $105 $0 $0 $0 $105 TOTALS $66 $25 $105 $0 $0 $0 $195 IX - 1

Project: Library Design Work Project Type: Capital Program: Library Renovations Responsible Department: Library Project Origination: 2019 Project Status: New Project Budgeted: 25 Project Completion: Commission Status: New Description The project would provide the design work necessary to address the structural changes, both interior and exterior, needed to provide modern library services. Due to a settling foundation, the floor of the library has begun to sink causing stress to the supporting walls and windows.

Additionally, in order to make the best use of the space we do have, there will need to be renovations to the current building in order to provide adequate space for current programming.

Status Justification With an average daily attendance of 400-500 visitors, Oak Ridge Public Library is a popular and heavily used city service. A vibrant public library is essential to attracting and retaining new residents and businesses, and simultaneously keeps our current community resilient in the face of outside forces. Although a major expansion may not be currently feasible, neglecting the current building will only work contrary to the city's goal of fostering livability and community vibrancy.

Complies with Policies: F-10 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Design $25 $0 $0 $0 $0 $0 $25 $0 TOTAL EXPENDITURES $25 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund $25 $0 $0 $0 $0 $0 $25 $0

$0 $0 $0 $0 $0 $0 $0 TOTAL FUNDS $25 IX - 2

Project: Library Renovation: Central Library Project Type: Capital Program: Central Library Reno Responsible Department: Library Project Origination: 2020 Project Status: New Project Budgeted: 25 Project Completion: Commission Status:

Description This project would expand the library workroom to create space for the Friends of the Library Used Book sales, a cornerstone program raising money for the library. This project also incorporates a new circulation desk in order to provide better security for the facility as a whole and to create space for a business center for the public.

Status A preliminary design has been completed.

Justification The Friends of the Library have been a fundraising supporter of the library since it's inception. However, they have never had dedicated space to work from. As a service to the city, the accept and resale gently used books and need both storage space and retail space to do so. A new circulation desk will not only allow the library to serve the public more efficiently and with fewer staff, it will provide greater security to the library's collection. Also making better use of the space available, a modified circulation desk will create space to offer a self-serve business services such as copying, scanning, faxing, and others to the public.

Complies with Policies: F-10 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Construction $0 $25 $0 $0 $0 $0 $25 $0 TOTAL EXPENDITURES $25 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder General Fund $0 $25 $0 $0 $0 $0 $25 $0 TOTAL FUNDS $25 IX - 3

Project: Library Renovations: East Wing Project Type: Capital Program: East Wing Renovation Responsible Department: Library Project Origination: 2019 Project Status: Ongoing Project Budgeted: 40.5 Project Completion: Commission Status:

Description To replace the carpeting and provide updated furniture and shelving as needed in the library's Children's Room. Additionally, this design incorporates a café and art display area into the library's lobby.

Status Planning. A preliminary design was completed by the East TN Community Design Center in 2020.

Justification The Children's Room is a heavily used and popular room at the library with an annual attendance of 27,670 people in calendar year 2019.

However, the room is still functioning with carpeting, shelving, and seating original to the library in 1970. The carpeting, which is damaged in many places and has been repaired continually with tape, is a tripping hazard. In the ensuing 50 years since the library's opening, both the collection of physical materials and the amount of use this room recieves have grown dramatically. With the expansion of materials and formats, programs and activities, the room has become too crowded to accommodate it's growing following. Of all the requests from the public for services available at the library, a café is the most single requested service. Providing sense of place, a gathering place for the community, an opportunity for a local business, and a new draw to the library, a library café is easily incorporated into our lobby. Additionally, re-envisioning the lobby as a gallery space for local artists continues to build on the City's overall plan to create a new downtown and establish Oak Ridge as a desirable location to relocate.

Complies with Policies: F-10 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Construction/Renovation $41 $0 $0 $0 $0 $0 $41 $0 Work TOTAL EXPENDITURES $41 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund $41 $0 $0 $0 $0 $0 $41 $0 TOTAL FUNDS $41 IX - 4

Project: Library Renovations: West Wing Project Type: Capital Program: West Wing Renovation Responsible Department: Library Project Origination: 2020 Project Status: New Project Budgeted: 104.5 Project Completion: Commission Status:

Description The Oak Ridge Room, the library's local history room, was expanded into the west wing of the library in 2020. This area now needs to be partioned for security of the collection. This project would also create a new, smart conference room and three small reading rooms and staff space in the west wing of the library.

Status A prelimary design has been completed Justification The Oak Ridge Room houses an irreplacable collection of photographs, interviews, books, and documents pretaining to the history of the City of Oak Ridge. In order to protect this collection, this area needs to be partitioned separately from the rest of the library. Additionally, as part of our effort to have more staff on the library floor to alleviate workroom crowding, we will need to create office space in the west wing for our Community Services staff.

Complies with Policies: F-10 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Construction/Renovation $0 $0 $105 $0 $0 $0 $105 $0 Work TOTAL EXPENDITURES $105 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Fund $0 $0 $105 $0 $0 $0 $105 $0 TOTAL FUNDS $105 IX - 5

Police Department Capital Improvements Program - Capital Summary of Projects - ($000's) Police Department Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Police Department Security Fencing for Police Department Parking Area $214 $0 $0 $0 $0 $0 $214 TOTALS $214 $0 $0 $0 $0 $0 $214 X-1

Project: Security Fencing for Police Department Parking Area Project Type: Capital Program: Responsible Department: Police Department Project Origination: 2020 Project Status: New Project Budgeted: 214 Project Completion: Commission Status:

Description Six (6) foot security fence with two motorized entrance/exit gates on the south-side of the Municipal Building. Fencing would provide security for police vehicles and the emergency power generator.

Status Justification There have been several documented instances where suspicious persons were observed in the police department parking lot. Additionally, nails and screws have been found and removed from the tires of police vehicles. Security fencing for the Police Department parking area on the south side of the municipal building would enhance the safety of employees and protect city vehicles from harm. To maintain continuity of operations for the emergency communications center and other emergency management services, it is critical to ensure the security of the emergency power generator in the event of a power outage.

Complies with Policies: N/A Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Construction of Fence $188 $0 $0 $0 $0 $0 $188 $0 Power for Gate Openers $26 $0 $0 $0 $0 $0 $26 $0 TOTAL EXPENDITURES $214 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder General Fund $214 $0 $0 $0 $0 $0 $214 $0 TOTAL FUNDS $214 X-2

Public Works Capital Improvements Program - Capital Summary of Projects - ($000's) Public Works Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Public Works Sewer Collection System Rehab/CMOM $2,016 $1,566 $1,050 $1,257 $4,130 $957 $10,975 Transportation/Pedestrian/Bicycle Safety $2,743 $1,250 $1,250 $0 $0 $0 $5,243 Improvements Turtle Park Wastewater Treatment Plant $1,130 $2,202 $1,988 $2,688 $2,102 $1,770 $11,880 Water Treatment Plant - Existing $1,230 $450 $0 $0 $0 $0 $1,680 Water Treatment Plant - New $21,500 $21,500 $0 $0 $0 $0 $43,000 TOTALS $28,619 $26,968 $4,288 $3,945 $6,232 $2,727 $72,778 XI - 1

Project: Sewer Collection System Rehab/CMOM Project Type: Capital Program: Utilities Responsible Department: Public Works Project Origination: 2015 Project Status: Ongoing Project Budgeted:

Project Completion: Commission Status:

Description This program is to provide funding for the Management-Operations-Maintenance (MOM) program for the sewer collection lines, pump stations and equalization basins. Sewer Lift/Pump Stations and WWTP rehabilitation costs are included as a separate item in the CIP.

Status A requirement of the 2010 EPA Administrative Order was the development of a MOM program to ensure that the sewer collection system inclusive of lines and equalization basins are properly managed, operated and maintained, and not allow it to fall into disrepair to help mitigate sanitary sewer overflows (SSOs).

Justification Annual wastewater collection system rehabilitation/replacement is required to help mitigate SSOs and to reduce the amount of I/I that enters into the collection system, which impacts treatment. Projects and estimated costs are taken from February 2017 Post Remediation Plan completed by LDA & developed by the PWD Engineering Division based on repeat overflow locations, work orders and on-going sewer evaluations.

1. Turtle Park Sewer Shed
2. Central City Sewer Shed
3. East Plant Sewer Shed
4. Y-12 Sewer Shed
5. Rarity Ridge Sewer Shed
6. System Wide Rehab
7. Annual Manhole, point repairs and sewer speciality work
8. Evaluation of the capacity of the Rarity Ridge Wastewater Treatment Plant to anticipate expansion needs and timing based on active development occuring in the area
9. Evaluation and repair of the City's primary trunk line to minimize I/I.
10. Misc. Annual Maintenance.

Complies with Policies: F-6, F-1 and P-12 XI - 2

Project: Sewer Collection System Rehab/CMOM Project Type: Capital Program: Utilities Responsible Department: Public Works Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Annual Manhole Repair $150 $150 $150 $150 $150 $150 $900 $0 Annual Point Repair $200 $200 $200 $200 $200 $200 $1,200 $0 Annual Sewer Specialty Work $150 $150 $150 $150 $150 $150 $900 $0 Rarity Ridge WWTP $100 $0 $0 $0 $0 $0 $100 $0 Expansion Analysis Phase I-V Trunk Line $16 $16 $50 $50 $0 $0 $131 $0 Evaluation Phase I-V Trunk Line Repairs $0 $100 $100 $100 $100 $100 $500 $0 Emory Valley & EP Sewer $50 $300 $0 $0 $0 $0 $350 $0 Shed Design & Rehab Misc. Sewer Shed Rehab $0 $0 $250 $250 $0 $0 $500 $0 CWSRF Year Sewer Rehab $1,000 $0 $0 $0 $0 $0 $1,000 $0 (On-Going)

Meco Lane Sewer Line Repair $200 $0 $0 $0 $0 $0 $200 $0 CRIP Sewer Line Repair $0 $500 $0 $0 $0 $0 $500 $0 Turtle Park Sewer Shed $0 $0 $0 $0 $0 $0 $0 $0 Central City Sewer Shed $0 $0 $0 $0 $0 $207 $207 $0 East PlantSewer Shed $0 $0 $0 $207 $3,380 $0 $3,587 $0 Y-12 Sewer Shed $0 $0 $0 $0 $0 $0 $0 $0 Rarity Ridge Sewer Shed $0 $0 $0 $0 $0 $0 $0 $0 Annual Misc. Maintenance $150 $150 $150 $150 $150 $150 $900 $0 TOTAL EXPENDITURES $10,975 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Waterworks Fund $1,016 $1,566 $1,050 $1,257 $750 $957 $6,595 $0 CWSRF $1,000 $0 $0 $0 $3,380 $0 $4,380 $0 TOTAL FUNDS $10,975 XI - 3

Project: Transportation/Pedestrian/Bicycle Safety Improvements Project Type: Capital Program: Transportation Responsible Department: Public Works Project Origination: 2012 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description These projects are to provide funding to improve traffic capacity/safety, school crossings, and bicycle/pedestrian safety at various locations within the City as identified by transportation enhancement projects and the Oak Ridge Bicycle and Pedestrian Plan. Initial projects are located at intersections along Oak Ridge Turnpike and other residential streets. Improvements include crosswalks, pedestrian signals with countdown timers, traffic signs, pavement markings, and new sidewalks to connect missing link sections.

Status In FY2017, TDOT awarded the City $927,021 in Multimodal Access Funds. This is 95% of a $975,811 project for the purpose of constructing approximately 43 - ADA accessible ramps, 30 crosswalks and over one mile of new sidewalk to fill gaps between existing sidewalk sections along the south side of Oak Ridge Turnpike. This project is in the design phase by Kimley-Horn.

In FY2019, the City also received a 100% Funded Signalization Improvement Grant totaling $2,855,440, which includes 11 new controls, fiber links to 14 intersections, LED signal head and radar detectors. In FY2020, the City received $2.9M in grant funding to fund signalization/sidewalk improvement.

Justification Improvements are intended to provide traffic calming to enhance safety.

Complies with Policies: N/A Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder SR95 Phase I Project 95/5 $488 $0 $0 $0 $0 $0 $488 $0 SPLIT MultiModal SR95 Phase II Project 100% $1,855 $0 $0 $0 $0 $0 $1,855 $0 CMAQ Signalization Phase III Project $400 $1,250 $1,250 $0 $0 $0 $2,900 $0 100% CMAQ TOTAL EXPENDITURES $5,243 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Matching Funds (City)/ADA $25 $0 $0 $0 $0 $0 $25 $0 Match Grants $2,718 $1,250 $1,250 $0 $0 $0 $5,218 $0 TOTAL FUNDS $5,243 XI - 4

Project: Turtle Park Wastewater Treatment Plant Project Type: Capital Program: Utilities Responsible Department: Public Works Project Origination: 2005 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description The different projects listed provides funding for proactive maintenance, repair and replacment of equipment that is critical to the operation of the plant and meeting our NPDES permit.

Status This is part of the ongoing maintenance of the Citys wastewater treatment system. Several projects have been completed including the following:

1. Rehab of the TPPS to replace antiquated pumps.
2. Installation of a new UV system which should save the City money from reduced electrical costs.
3. WWTP Evaluation has been completed that provides short and long term recommendations for the operation of the plant and to meet Tier III requirements that are anticipated to be included in our next NPDES permit.
4. Installation of new drum screens to replace failing drum screens. Project will be started in FY21 and completed in FY22.

Justification The Turtle Park Wastewater Treatment Plant was originally constructed in the 1980's and renovations were completed in the 1990's. Some of the equipment is over 30 years old and requires replacement.

The following projects are recommended at the WWTP to help the City remain in compliance with our State NPDES permit, increase efficiency of operation, and reduce electrical consumption.

1. Annual Capital Maintenance - For unknowns that often occur.
2. NPDES Tier III Biological Process - Includes new blowers, upgrades to Aeration Basins and automation of operation of blowers and assist in upcoming Tier III nutruient removal requirements.
3. Clarification and Filtration Upgrades - To replace olders systems so we can maintain compliance.
4. Sludge Dewatering - Future FY29 project
5. Electric Gear Replacement & SCADA - To replace older equiment and new SCADA that matches the WTP SCADA
6. Odor Control - For Screening Building, future project FY29.
7. Drum Screen Replacement - Ongoing should finish in FY22.
8. Turtle Park Pump Station Screen Replacement - Future Project FY30.

Complies with Policies: F-1 and F-7 XI - 5

Project: Turtle Park Wastewater Treatment Plant Project Type: Capital Program: Utilities Responsible Department: Public Works Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Maintenance (Annual) $150 $150 $150 $150 $150 $150 $900 $0 Biological Process NPDES Tier $380 $2,052 $1,368 $0 $0 $0 $3,800 $0 III Clarification & Filtration $0 $0 $470 $2,538 $1,652 $0 $4,660 $0 Upgrades Sludge Dewatering $0 $0 $0 $0 $0 $0 $0 $0 Improvements Elec. Gear Replacement & $0 $0 $0 $0 $300 $1,620 $1,920 $0 SCADA Screening Blding Odor Control $0 $0 $0 $0 $0 $0 $0 $0 Drum Screen Replacement $600 $0 $0 $0 $0 $0 $600 $0 TTPS Screen Replacement $0 $0 $0 $0 $0 $0 $0 $0

$0 $0 $0 $0 $0 $0 $0 $0 TOTAL EXPENDITURES $11,880 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Waterworks Fund $1,130 $150 $620 $150 $450 $150 $2,650 $0 CWSRF $0 $2,052 $1,368 $2,538 $1,652 $1,620 $9,230 $0 TOTAL FUNDS $11,880 XI - 6

Project: Water Treatment Plant - Existing Project Type: Capital Program: Utilities Responsible Department: Public Works Project Origination: 2005 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description Projects associated with this category include the rehabilitation, upgrades and/or replacement of key assets associated with the raw water intake, intermediate raw water booster pump station and existing water treatment plant to keep it operational until the new WTP is online.

The Public Works Department has evaluated the long term use of the existing water treatment plant and associated assets versus the construction of a new water treatment plant at a different location. The results of this study conclude that a new plant is the best option, but the existing plant will have to remain fully operational until a new plant can be constructed and placed into service. This project represents the estimated costs associated with the general capital maintenance needed to maintain the existing plant until the new plant is fully constructed and on-line or the rehabilitation work is completed.

Status To date, the controller at the operations center, which includes meters and telemetry, has been replaced along with the turbidimeter, particle counter system, the filter control system, and numerous valves on the incoming raw water lines. The roofs on the maintenance building the main plant building have been replaced. The upflow clarifiers have been repaired and painted. Structural repairs have been done. Windows have been replaced and the surge tank rehab was completed in FY17. In FY22 , the original concrete 3 MG treated water storage reservior will be rehabed. In FY23, a new liner will be purchased and installed for the existing 4MG water reservior. Both of these projects have been recommended in a recent tank evaluation completed by CTI Engineerings for long term use of the tanks and it compliments the New WTP Project.

Justification For the continued safe production of potable water in accordance with state and federal regulations. Note that WTP maintenance is a 50/50 split with DOE and City Waterworks Fund.

Complies with Policies: F-1 and F-4 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder

  • Existing WTP/Assets Capital $150 $150 $0 $0 $0 $0 $300 $0 Maintenance 3 MG Tank Rehab $1,080 $0 $0 $0 $0 $0 $1,080 $0 4 MG Tank Liner Replacement $0 $300 $0 $0 $0 $0 $300 $0 TOTAL EXPENDITURES $1,680 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Waterworks Fund $615 $375 $0 $0 $0 $0 $990 $0 DOE $615 $75 $0 $0 $0 $0 $690 $0 TOTAL FUNDS $1,680 XI - 7

Project: Water Treatment Plant - New Project Type: Capital Program: Utilities Responsible Department: Public Works Project Origination: 2017 Project Status: New Project Budgeted:

Project Completion: Commission Status:

Description The Public Works Department commissioned a study of the existing water plant in April 2016 to determine if the plant should be extensively rehabilitated or a new plant constructed at a different location. The results of this study recommend the construction of a new plant to be located on the property with the raw water intake. The costs of project reflect the following activities:

1. Completion of a preliminary design report that discusses hydraulic and design needs of the City and the DOE complex (Completed).
2. Professional engineering design and bid fees. (FY21 Completion)
3. Estimated construction costs associated with the construction of a new water treatment plant. (FY21 Completion)
4. Construction FY22 - FY23.

Status The evaluation study was completed in FY2017. Funding for this project will be through two loan programs (WIFIA & DWSRF). The estimate for a new water treatment plant is $43 to $45 million.

Justification The City's current water supply facilities and infrastructure is old and needs replacing for the continued production of safe potable water production, in accordance with state and federal regulations.

Complies with Policies: F-1 and F-4 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Design/Permiting FY21 $0 $0 $0 $0 $0 $0 $0 $0 Bid/Award FY21 $0 $0 $0 $0 $0 $0 $0 $0 Construction FY22-FY23 $21,500 $21,500 $0 $0 $0 $0 $43,000 $0 TOTAL EXPENDITURES $43,000 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Waterworks Fund $0 $0 $0 $0 $0 $0 $0 $0 WIFIA (35 year loan) 49% $10,535 $10,535 $0 $0 $0 $0 $21,070 $0 SRF (30 year loan) 51% $10,965 $10,965 $0 $0 $0 $0 $21,930 $0 TOTAL FUNDS $43,000 XI - 8

Public Works Placeholder Projects

Capital Improvements Program - Capital Summary of Placeholder Projects By Responsible Department - ($000's)

Project Placeholder Public Works New Sidewalk Construction $100 Rarity Ridge Wastewater Treatment Plant $3,000 Public Works TOTAL: $3,100 TOTAL CAPITAL IMPROVEMENTS PROGRAM $3,100 XI - 9

Project: New Sidewalk Construction Project Type: Capital Program: Transportation Responsible Department: Public Works Project Origination: 2007 Project Status: Placeholder Project Budgeted:

Project Completion: 0 Commission Status:

Description This project is to provide funding as a match to grants sought to implement a sidewalk master plan to be developed by the Planning Commission. Funding sources are undetermined at this time.

Status Placeholder project to be completed when funding is available.

Justification Staff believes it would be desirable to expand the sidewalk system throughout the City and this item identifies this project for placeholder status should funds become available. This funding would provide for matching funds for any grants obtained.

Complies with Policies: T-8, Q-6. & Q-12 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder New Sidewalk Construction $0 $0 $0 $0 $0 $0 $0 $100 TOTAL EXPENDITURES $0 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund $0 $0 $0 $0 $0 $0 $0 $100 TOTAL FUNDS $0 XI - 10

Project: Rarity Ridge Wastewater Treatment Plant Project Type: Capital Program: Utilities Responsible Department: Public Works Project Origination: 2015 Project Status: Placeholder Project Budgeted:

Project Completion: Commission Status:

Description This project describes identified wastewater treatment plant improvements for development of the western portion of the City.

Status These improvements are development driven.

Justification Should significant development occur in the west end of the City, (commercial and residential) the existing plant will need to be expanded for capacity reasons.

Complies with Policies: F-1 and F-7 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Plant Expansion - Phase I $0 $0 $0 $0 $0 $0 $0 $1,500 (increase capacity to 1.2 MGD)

Plant Expansion - Phase II $0 $0 $0 $0 $0 $0 $0 $1,500 (increase capacity to 1.8 MGD)

TOTAL EXPENDITURES $0 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Waterworks Fund $0 $0 $0 $0 $0 $0 $0 $3,000 TOTAL FUNDS $0 XI - 11

Public Works/Board of Education Capital Improvements Program - Capital Summary of Projects - ($000's) Public Works / Board of Education Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Public Works / Board of Education City / Schools Joint for Facilities $2,110 $1,074 $888 $665 $655 $1,315 $6,707 City / Schools Joint HVAC Projects $213 $237 $325 $282 $240 $270 $1,567 City / Schools Joint Roof Projects $300 $3,600 $1,480 $416 $335 $666 $6,797 TOTALS $2,623 $4,911 $2,693 $1,363 $1,230 $2,251 $15,071 XI - 12

Project: City / Schools Joint for Facilities Project Type: Capital Program: capital maintenance Responsible Department: Public Works / Board of Project Origination: 2017 Project Status: Ongoing Project Budgeted:

Project Completion: Commission Status:

Description Capital maintenance projects for City and Schools facilities.

Status Ongoing Justification Complies with Policies: N/A XI - 13

Project: City / Schools Joint for Facilities Project Type: Capital Program: capital maintenance Responsible Department: Public Works / Board of Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Schools - Major Mechanical $205 $215 $315 $280 $245 $270 $1,530 HVAC Systems G-Building - Building Controls $0 $0 $0 $0 $0 $0 $0 $0 and HVAC units

$0 $0 $0 $0 $0 $0 $0 $0 Schools - Cafeteria Equipment Systemwide - Replacement of $0 $0 $0 $50 $50 $150 $250 $0 Cafeteria Equipment ORHS - Replace Dish Machine $125 $0 $0 $0 $0 $0 $125 $0 Woodland - Replace Steamer $17 $0 $0 $0 $0 $0 $17 $0 RMS and Woodland - Replace $50 $50 $0 $0 $0 $0 $100 $0 Dish Machine Willow Brook - Replace Walk- $0 $0 $100 $0 $0 $0 $100 $0 in Refrigerator Freezer Schools - MISC Projects RMS - Locker Replacement $0 $0 $0 $0 $0 $200 $200 $0 JMS - Electrical Switchgear $0 $0 $0 $0 $75 $0 $75 $0 Service Linden - Electrical Switchgear $0 $0 $0 $0 $50 $0 $50 $0 Service JMS - Remodel $0 $0 $0 $0 $0 $200 $200 $0 Administration Office and CDC Systemwide - Door Hardware $0 $0 $0 $0 $0 $50 $50 $0 Improvements

$0 $0 $0 $0 $0 $0 Schools - Recreation /

Athletics XI - 14

Project: City / Schools Joint for Facilities Project Type: Capital Program: capital maintenance Responsible Department: Public Works / Board of Ben Martin Track - Running $450 $0 $0 $0 $0 $0 $450 $0 Surface Replacement JMS - Replace Gym Bleachers $0 $0 $0 $0 $0 $250 $250 $0 and Reconfigure Court Blankenship Field - Home $450 $0 $0 $0 $0 $0 $450 $0 Bleachers Schools - Paving Systemwide Paving and $200 $150 $50 $50 $100 $0 $550 $0 Sidewalk Replacement RMS - Repave Ivanhoe Lane $75 $0 $0 $0 $0 $0 $75 $0 JMS - Pave Overflow Parking $0 $0 $0 $150 $0 $0 $150 $0 RMS - Pave Staff Parking Lot $0 $0 $0 $0 $0 $90 $90 $0

$0 City Misc.

205 Badger Avenue $100 $325 $0 $0 $0 $0 $425 $0 Marina Building Misc. $10 $10 $10 $10 $10 $10 $60 $0 Maintenance Civic Center Fire Alarm $50 $0 $0 $0 $0 $0 $50 CSC Carpet Replacement $25 $25 $25 $0 $0 $0 $75 Oak Ridge Civic Center - Plaza $25 $25 $0 $0 $0 $0 $50 $0 Repair Oak Ridge Civic Center - $25 $25 $25 $25 $25 $25 $150 $0 Equipment Maintenance Municipal Building - Paint $0 $0 $0 $30 $30 $0 $60 $0 Building Exterior and Replace Interior Wall Covering Municipal Building - Replace $20 $20 $20 $20 $20 $20 $120 $0 Carpet in the Hallway and Select Offices Municipal Building - Usability $50 $0 $50 $0 $0 $0 $100 $0 Study XI - 15

Project: City / Schools Joint for Facilities Project Type: Capital Program: capital maintenance Responsible Department: Public Works / Board of Parking Lot Maintenance $50 $50 $50 $50 $50 $50 $300 $0 School Bus Drop Off $0 Improvements Glenwood/Robertsville $183 $0 $0 $0 $0 $0 $183 $0 Linden/Willowbrook $0 $179 $0 $0 $0 $0 $179 $0 Woodland/Jefferson $0 $0 $243 $0 $0 $0 $243 $0 TOTAL EXPENDITURES $6,707 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Funds $2,110 $1,074 $888 $665 $655 $1,315 $6,707 $0

$0 TOTAL FUNDS $6,707 XI - 16

Project: City / Schools Joint HVAC Projects Project Type: Capital Program: Capital Maintenance Responsible Department: Public Works / Board of Project Origination: 2018 Project Status: Ongoing Project Budgeted:

Project Completion: Commission Status:

Description The remaining HVAC projects represents equipment not completed as part of the energy savings project. Many of the City and School HVAC units are old and require replacement. The proposed budget represents the required funding needed over multiple fiscal years. The actual HVACs replaced in a fiscal year may vary depending on specific building needs and equipment.

Status Many of the City/School HVAC equipment was replaced as part of the energy savings project. Additional funding is needed for the remaining HVAC units.

Justification Over the next several years, the City/Schools HVAC units will have reached the end of their useful life and require replacement.

Complies with Policies: N/A Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Schools HVAC Repair/Replacement $202 $215 $312 $282 $240 $270 $1,521 $0 Projects City HVAC Repair/Replacement $11 $22 $13 $0 $0 $0 $46 $0 Projects TOTAL EXPENDITURES $1,567 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Funds $213 $237 $325 $282 $240 $270 $1,567 $0 TOTAL FUNDS $1,567 XI - 17

Project: City / Schools Joint Roof Projects Project Type: Capital Program: Capital Maintenance Responsible Department: Public Works / Board of Project Origination: 2018 Project Status: Ongoing Project Budgeted:

Project Completion: Commission Status:

Description A roofing study was completed in December 2017 by RoofConnect, for all City and School buildings. The results of the analysis indicated that over the next 10 to 12 years, a total combined cost of $12M is needed to rehabilitate and/or replace these roofs. The proposed budget represents the required funding needed over multiple fiscal years. The actual roofs completed in a fiscal year may vary from the roof study.

Status The following roofs have been completed or are in the process of completion:

RMS CSC 1010 Building Section 3 Municipal Building Library Centennial Golf Course Glenwood Elementary Portions of ORHS Willowbrook Elementary Justification Over the next 10 years, the City and School roofs will have reached the end of their useful lives and require replacement. Many have on-going leaks that require repairs.

Complies with Policies: N/A Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Schools Roof Repair / Replacement $0 $3,600 $900 $312 $53 $596 $5,461 $0 Projects City Roof Repair / Replacement $300 $0 $580 $104 $282 $70 $1,336 Projects TOTAL EXPENDITURES $6,797 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Funds $300 $3,600 $1,480 $416 $335 $666 $6,797 $0 TOTAL FUNDS $6,797 XI - 18

Public Works/Fire Department Capital Improvements Program - Capital Summary of Projects - ($000's) Public Works/Fire Department Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Public Works/Fire Department Fire Station 2 Building Study $18 $0 $0 $0 $0 $0 $18 TOTALS $18 $0 $0 $0 $0 $0 $18 XI - 19

Project: Fire Station 2 Building Study Project Type: Capital Program: General Responsible Department: Public Works/Fire Department Project Origination: 2011 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description Perform an engineering study to determine if the east side of building is still settling and the cost to stop the settling and repair the structure.

Status The engineering study will be initiated by Public Works. Fire Chief will pursue comparing the cost of building repairs to the cost of relocating the station to serve additional properties, which are not located within 5 miles of a fire station and receiving an ISO class 10 (no fire protection) rating.

Justification Study the cost of repairs to station 2 and look at the feasibility of relocating station 2 vs. building an additional station to serve those properties outside the 5 mile response zone of station 2 and 3.

Properties which do not have sprinkler systems but are within 5 miles of a fire station and 1000 feet of a fire hydrant have an Insurance Service Office (ISO) rating of Class 3, which saves approximately 35 to 40 percent on property insurance. Properties which do not have sprinkler systems but are within 5 miles of a fire station but more than 1000 feet of a fire hydrant have an Insurance Service Office (ISO) rating of Class 7, which saves approximately 15 percent on homeowners insurance policies. Properties which do not have sprinkler systems but are located more than 5 miles from a fire station have an Insurance Service Office (ISO) rating of Class 10 (no fire protection). There are a number of properties (homes, apartments, condos and buildings) in the southeast quadrant of the City which are located more than 5 miles from an Oak Ridge fire station.

Complies with Policies: F-1 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Engineering Study $18 $0 $0 $0 $0 $0 $18 $0 TOTAL EXPENDITURES $18 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund $18 $0 $0 $0 $0 $0 $18 $0 TOTAL FUNDS $18 XI - 20

Public Works/Library Capital Improvements Program - Capital Summary of Projects - ($000's) Public Works/Library Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Public Works/Library ADA compliant restrooms for Public Library $210 $0 $0 $0 $0 $0 $210 TOTALS $210 $0 $0 $0 $0 $0 $210 XI - 21

Project: ADA compliant restrooms for Public Library Project Type: Capital Program: Library Responsible Department: Public Works/Library Project Origination: 2019 Project Status: New Project Budgeted:

Project Completion: Commission Status:

Description This project would renovate the public restrooms at the library to be ADA compliant.

Status Justification The library's public restrooms do not currently meet ADA standards.

Complies with Policies: N/A Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder ADA compliant public $210 $0 $0 $0 $0 $0 $210 $0 restrooms TOTAL EXPENDITURES $210 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital $210 $0 $0 $0 $0 $0 $210 $0 TOTAL FUNDS $210 XI - 22

Recreation and Parks Capital Improvements Program - Capital Summary of Projects - ($000's) Recreation and Parks Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Recreation and Parks Briarcliff Park $0 $0 $0 $0 $60 $100 $160 Greenway Implementation $1,000 $3,074 $0 $0 $0 $0 $4,074 Groves Park $0 $0 $40 $150 $0 $100 $290 Oak Ridge Gateway $200 $200 $100 $0 $0 $0 $500 Outdoor Pool Renovation $0 $0 $500 $0 $0 $4,500 $5,000 Rowing Improvements $0 $200 $0 $0 $0 $0 $200 Solway Park $0 $0 $40 $0 $0 $200 $240 TOTALS $1,200 $3,474 $680 $150 $60 $4,900 $10,464 XII - 1

Project: Briarcliff Park Project Type: Capital Program: Recreation and Parks Responsible Department: Recreation and Parks Project Origination: 2005 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description The proposed project includes continued development of eight acres of Parcel 616 into a neighborhood park. General park improvements are planned for FY2025 and FY2026. Neighborhood input on improvements will be obtained at time of funding availability.

Status Prior improvements to the park include the construction of a parking lot, installation of playground equipment in 1987, park benches, drinking fountain, split-rail fencing, and landscape improvements. ADA access was completed during FY2013.

Justification The Comprehensive Plan outlines a plan to develop a neighborhood park within walking distance of each neighborhood. Continued development of Briarcliff Park will fulfill that requirement.

Complies with Policies: F-1, L-16, P-12, PK-4, and Q-6 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Picnic Shelter $0 $0 $0 $0 $60 $0 $60 $0 Walking Trail/Security $0 $0 $0 $0 $0 $100 $100 $0 Lighting TOTAL EXPENDITURES $160 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund $0 $0 $0 $0 $60 $100 $160 $0 TOTAL FUNDS $160 XII - 2

Project: Greenway Implementation Project Type: Capital Program: Recreation and Parks Responsible Department: Recreation and Parks Project Origination: 2005 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description The Citywide Greenway system recommended by the Greenway Task Force has been endorsed by City Council and has moved into the implementation stage. The City has been awarded a Transportation Alternatives Program (TAP) Grant from the Tennessee Department of Transportation (TDOT) in the amount of $1.224 M for Design & Engineering and Right of Way Acquisition. Approximately $18K of Capital Improvement Program Funds were expended in FY2019 on Design & Engineering, along with approximately $74K of funding from the TDOT TAP grant. FY2020 thus far, approximately $23K in Capital Improvement Program Funds have been expended on Design & Engineering along with approximately $94K of funding from the TDOT TAP grant. The balance of funds from the grant will be used for Design & Engineering in FY2020 and Right of Way acquisition in FY2021. Additional funding for construction has been included in the Knoxville Regional Transportation Planning Organizaion (TPO) Transportation Improvement Program FY2020-2023. Funding includes $2,249K in Federal grant funding and $615K in local funding , for a total of $3,074K.

Status The City Council, Planning Commission, and EQAB have all adopted the Greenway Concept and it is now in the implementation stage. In 2002, Phase III of the Melton Lake Greenway was completed. The Emory Valley Greenway was completed in 2006. Phase IV of the Melton Lake Greenway was completed in 2012.

Justification The Greenway system will bring the advantage of parkland nearer to all Oak Ridge citizens. Other advantages include: (1) provides for the opportunity for motorless commuting; (2) provides flora and fauna habitat and learning experiences about wildlife; (3) provides a means of enjoyable physical exercise; (4) links strategic locations in the community including parks, schools, and shopping areas; (5) reduces short trip auto traffic; (6) provides a buffer zone.

Complies with Policies: PK-2, Q-6, and T-10 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Rail Line Acquisition, Design $1,000 $3,074 $0 $0 $0 $0 $4,074 $0 and Trail Construction TOTAL EXPENDITURES $4,074 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund (20%) $815 $0 $0 $0 $0 $0 $815 $0 Federal/State/Other (80%) $3,259 $0 $0 $0 $0 $0 $3,259 $0 TOTAL FUNDS $4,074 XII - 3

Project: Groves Park Project Type: Capital Program: Recreation and Parks Responsible Department: Recreation and Parks Project Origination: 2005 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description The proposed project envisions the development of a neighborhood park. The project consists of a 40-car parking area in FY 2024, and a play area in FY 2026. A master plan for the park will be developed in FY 2023.

Status Former land fill area. An 18-hole disc golf course was built in 2008.

Justification Adjacent residential area and development across the street support the need for a neighborhood park.

Complies with Policies: F-1, P-12, PK-3, and Q-6 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Parking $0 $0 $0 $150 $0 $0 $150 $0 Playground $0 $0 $0 $0 $0 $100 $100 $0 Master Plan $0 $0 $40 $0 $0 $0 $40 $0 TOTAL EXPENDITURES $290 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund $0 $0 $40 $150 $0 $100 $290 $0 TOTAL FUNDS $290 XII - 4

Project: Oak Ridge Gateway Project Type: Capital Program: Recreation & Parks Responsible Department: Recreation and Parks Project Origination: 2019 Project Status: Ongoing Project Budgeted: FY2020 Project Completion: Commission Status:

Description In 2015, City staff engaged the East Tennessee Community Design Center to develop preliminary designs for enhancement of the entrance to Oak Ridge along South Illinois Avenue. The first phase of this project will be the design and construction of a Gateway Monument in the median between South Illinois Ave and Bethel Valley Road.

Status In FY2019, the City of Oak Ridge was awarded a State appropriation of $500K for the construction of a Gateway Monument. This allocation is managed through the Tennessee Department of Transportation (TDOT). The city has awarded an engineering and design consultant contract for the project. The Gateway Monument will be designed, using the original work of the East Tennessee Community Design Center as inspiration.

Once the design is complete and approved by TDOT, the project will move to construction. Completion is tentatively planned for the fall of 2022.

Justification Because the City Center is located some distance from the main city entry on South Illinois Avenue, visitors to Oak Ridge and the DOE facilities are often unaware when they have entered the city. The Gateway Monument will provide visitors with a clear indication that they have arrived at the City of Oak Ridge. The Gateway Monument will be designed specifically for Oak Ridge, complete with imagery to define a sense of place and arrival.

Complies with Policies: E-5, L-17, P-3, Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Design & Construction $200 $200 $100 $0 $0 $0 $500 $0 TOTAL EXPENDITURES $500 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder TDOT $200 $200 $100 $0 $0 $0 $500 $0 TOTAL FUNDS $500 XII - 5

Project: Outdoor Pool Renovation Project Type: Capital Program: Recreation and Parks Responsible Department: Recreation and Parks Project Origination: 2005 Project Status: New Project Budgeted:

Project Completion: 0 Commission Status:

Description The outdoor pool is approaching the end of useful life and will soon be in need of a complete renovation. The aging bath houses and other infrastructure will be included in the pool's complete renovation with either extensive updates or complete replacement as well.

Status The outdoor pool was completely renovated in 1993. FY2018 improvements included repairs to the gutters and weak spots in the pool shell. At this time, it was discovered that there was significant deterioration in the pool shell, including deterioration of the reinforcing steel in the concrete. The reparation contractor advised the City of Oak Ridge of pool life expectancy and estimated a five to seven (5-7) year useful life remaining for the pool. This aligns with the thirty-year design life of the pool (1993 complete pool renovation).

Justification The outdoor pool is an iconic facility in the City of Oak Ridge, due both to the historical significance in the City's development and the sheer size and capacity. Failure of the pool shell will render the facility unusable and will require closure of pool and surrounding structures.

Complies with Policies: F-1, L-16, P-12, PK-3, and Q-6 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Renovate Outdoor Pool $0 $0 $0 $0 $0 $4,500 $4,500 $0 Design & Engineering $0 $0 $500 $0 $0 $0 $500 $0

$0 $0 $0 $0 $0 $0 $0 $0

$0 $0 $0 $0 $0 $0 $0 $0 TOTAL EXPENDITURES $5,000 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund $0 $0 $500 $0 $0 $4,500 $5,000 $0 TOTAL FUNDS $5,000 XII - 6

Project: Rowing Improvements Project Type: Capital Program: Recreation and Parks Responsible Department: Recreation and Parks Project Origination: 2005 Project Status: Ongoing Project Budgeted:

Project Completion: Commission Status:

Description The rowing venue on Melton Hill Lake would be upgraded to include expansion of the existing boathouse and parking improvements for regatta participants.

Status The rowing venue has hosted numerous national rowing events and regional regattas.

The dredging was completed in early 2004. Course improvements were made in FY 2007. Widening of the course was completed in FY 2017.

Justification Rowing events have contributed to the quality of life in Oak Ridge. The events have brought visitors and tax revenue to the City. Enhancing the existing course will increase the opportunity to attract national and international events to the City.

Complies with Policies: F-1, F-14, L-16, P-12, PK-4, and Q-6 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Parking Improvements $0 $200 $0 $0 $0 $0 $200 $0 TOTAL EXPENDITURES $200 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund $0 $200 $0 $0 $0 $0 $200 $0 TOTAL FUNDS $200 XII - 7

Project: Solway Park Project Type: Capital Program: Recreation and Parks Responsible Department: Recreation and Parks Project Origination: 2005 Project Status: Ongoing Project Budgeted:

Project Completion: 0 Commission Status:

Description A Master Plan will be developed in FY2023. The proposed project includes the installation of a picnic shelter, picnic tables, landscaping, the development of an open space/multi-use area, re-routing the traffic flow, and the installation of playground equipment. Rerouting of traffic flow to align with the Master Plan is proposed for FY2026.

Status The park area, a previous TVA park site, was deeded to the City with a recreational restriction from TVA. Past improvements include paving of the gravel roadway at the central park site, the installation of traffic control barriers, security lighting at the west boat launch site, boat dock renovations, and erosion control planting. FY 2001 included the construction of a handicap accessible fishing pier and handicap parking adjacent to the pier, in which TVA and TWRA contributed $60,000 toward the project, which was 70% of the total cost.

Justification No major improvements have been funded at the site other than the paving of the existing gravel roadway, the installation of security lighting at the boat launch site and in conjunction with TVA TWRA a handicapped accessible fishing pier and parking. With the development of Parcel A and already heavy use of the area, the basic improvements and upgrading of the area are needed as the site will become a focal point for the southeast section of the City.

This project will move into earlier fiscal years concurrent with building expansion in adjacent residential neighborhoods including Park Meade and Centennial.

Complies with Policies: E-5, F-1, P-3, PK-2, PK-3, Q-6 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Master Plan $0 $0 $40 $0 $0 $0 $40 $0 Re-routing Traffic Flow and $0 $0 $0 $0 $0 $200 $200 $0 Parking TOTAL EXPENDITURES $240 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund $0 $0 $40 $0 $0 $200 $240 $0 TOTAL FUNDS $240 XII - 8

Recreation and Parks Placeholder Projects

Capital Improvements Program - Capital Summary of Placeholder Projects By Responsible Department - ($000's)

Project Placeholder Recreation and Parks Bobby Hopkins Baseball Field $350 Melton Lake Park $450 Neighborhood Park with Designated Areas for Skateboarding & Rollerblading $220 Pinewood Park $250 Westwood Park $340 Wolfe Creek Park $270 Recreation and Parks TOTAL: $1,880 TOTAL CAPITAL IMPROVEMENTS PROGRAM $1,880 XII - 9

Project: Bobby Hopkins Baseball Field Project Type: Capital Program: Recreation and Parks Responsible Department: Recreation and Parks Project Origination: 2014 Project Status: Placeholder Project Budgeted:

Project Completion: 0 Commission Status: New Description Proposed upgrades to Bobby Hopkins Baseball Field include indoor batting facility, warm-up areas, covered grand stands and restrooms/concessions.

Status Justification Complies with Policies: F-1, P-12, PK-3, PK9 and Q-6 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Facility Improvements $0 $0 $0 $0 $0 $0 $0 $350 TOTAL EXPENDITURES $0 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Private $0 $0 $0 $0 $0 $0 $0 $350 TOTAL FUNDS $0 XII - 10

Project: Melton Lake Park Project Type: Capital Program: Recreation and Parks Responsible Department: Recreation and Parks Project Origination: 2016 Project Status: Placeholder Project Budgeted:

Project Completion: 0 Commission Status:

Description The improvements proposed will continue the development of the Melton Lake Park waterfront. The Melton Lake Park Waterfront Plan provides a guide to upgrade existing facilities and construct additional amenities.

Status Improvements completed in FY 1990 include the installation of rip-rap along Melton Lake Drive and the planting of trees throughout the park.

FY 1991 enhancements include the construction of a parking lot and a picnic shelter, the installation of playground equipment, split rail fencing and benches in the park. During FY 1993 a recreational volleyball court was constructed. During FY 1998 a walking trail was constructed from Amanda Drive to Rivers Run and in FY 2001 the walking trail was continued from Amanda Drive to Elza Park located on the east end of the Oak Ridge Turnpike. In FY 2002 the walking trail was extended from Rivers Run to Edgemoor Road, play equipment was upgraded to meet ASTM and CPSC safety standards and ADA requirements, trash receptacles and screening for portable toilets were installed, and in 2007 rip-rap was installed along the shoreline. In FY 2012 the trail was extended from Melton Lake Drive to Solway Park. The waterfront pavilion was completed in FY 2013, and in FY 2014 the old restaurant was renovated to provide restrooms and equipment rental space. Split rail fencing was also replaced with pressure treated diamond rail fencing.

Justification With the completion of four phases of the greenway and other facilities in the park, there has been a significant increase in the overall usage of the park. User safety and accessibility have been enhanced by the upgrades to play equipment, and opportunities for a broad range of recreational activities in the park have been increased.

Complies with Policies: F-1, L-16, P-12, PK-3, and Q-6 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Splash Pad $0 $0 $0 $0 $0 $0 $0 $300 Parking Lot Expansion $0 $0 $0 $0 $0 $0 $0 $150 TOTAL EXPENDITURES $0 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund $0 $0 $0 $0 $0 $0 $0 $450 TOTAL FUNDS $0 XII - 11

Project: Neighborhood Park with Designated Areas for Skateboarding & Rolle Project Type: Capital Program: Recreation and Parks Responsible Department: Recreation and Parks Project Origination: 2005 Project Status: Placeholder Project Budgeted:

Project Completion: 0 Commission Status:

Description The proposed project envisions the development of a multipurpose skateboard/rollerblade area at Carl Yearwood Park. Proposed improvements include the construction of a skatepark facility.

Status Members of the skateboarding community have expressed the need for an area to be designated for the use of skateboarding and rollerblading.

This interest was expressed to members of City Council as well as members of the Youth Advisory Board.

Justification The proposed project envisions the development of a park area with multi-purpose use. As the sport grows and additional facilities are justified, a skate park will be constructed. The development of a professionally designed and approved skate park would increase economic development by drawing persons from outside the Oak Ridge community.

Complies with Policies: F-1, F-14, L-16, P-12, PK-4, and Q-6 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder A/E $0 $0 $0 $0 $0 $0 $0 $40 Skatepark $0 $0 $0 $0 $0 $0 $0 $180 TOTAL EXPENDITURES $0 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund $0 $0 $0 $0 $0 $0 $0 $220 TOTAL FUNDS $0 XII - 12

Project: Pinewood Park Project Type: Capital Program: Recreation and Parks Responsible Department: Recreation and Parks Project Origination: 2005 Project Status: Placeholder Project Budgeted:

Project Completion: 0 Commission Status:

Description The proposed project will improve and expand the Pinewood Park facility. Improvements include additional site work, landscaping, and restroom/concessions.

Status Prior work included paving of the gravel parking lot, installation of softball field lights, clearing and filling of adjacent property into a soccer field.

Justification The park does not have permanent restrooms or concession area.

Complies with Policies: F-1, P-12, PK-3, and Q-6 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Restrooms/Concessions $0 $0 $0 $0 $0 $0 $0 $250 TOTAL EXPENDITURES $0 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund $0 $0 $0 $0 $0 $0 $0 $250 TOTAL FUNDS $0 XII - 13

Project: Westwood Park Project Type: Capital Program: Recreation and Parks Responsible Department: Recreation and Parks Project Origination: 0 Project Status: Placeholder Project Budgeted:

Project Completion: 0 Commission Status:

Description The proposed project will begin the development of Westwood Park. The park will be a neighborhood park primarily serving the Westwood area and West Outer Drive area. Meetings will be scheduled with neighborhood residents to discuss development and specific needs. In conjunction with other neighborhood parks, the installation of benches and play equipment is planned. Improvements include the construction of a picnic shelter, volleyball court, and security lighting.

Status The proposed site is presently undeveloped. In 1996 a license agreement was approved from DOE for the proposed park located at the intersection of Wisconsin and Whippoorwill.

Justification This park will be developed as a passive recreation area and will provide limited parking for the North Boundary Greenway.

Complies with Policies: F-1, P-12, PK-3, and Q-6 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Site Development $0 $0 $0 $0 $0 $0 $0 $100 Play Equipment/Benches $0 $0 $0 $0 $0 $0 $0 $120 Picnic Shelter/Tables $0 $0 $0 $0 $0 $0 $0 $80 Lighting/Volleyball Court $0 $0 $0 $0 $0 $0 $0 $40 TOTAL EXPENDITURES $0 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund $0 $0 $0 $0 $0 $0 $0 $340 TOTAL FUNDS $0 XII - 14

Project: Wolfe Creek Park Project Type: Capital Program: General Responsible Department: Recreation and Parks Project Origination: 2008 Project Status: Placeholder Project Budgeted:

Project Completion: 0 Commission Status:

Description The proposed project envisions the development of a neighborhood park as part of the Wolfe Creek residential area.

Status The area will be developed as a neighborhood park after substantial input for the surrounding residential parcel. Initial development could include play equipment, open turf area and passive play areas.

Justification The Comprehensive Plan outlines a plan for the development and renovation of a neighborhood park system that would be within walking distance of every neighborhood in Oak Ridge.

Complies with Policies: F-1, L-16, P-12, PK-4 & Q-6 Expenditure Allocation ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Play Equipment $0 $0 $0 $0 $0 $0 $0 $120 Site Work $0 $0 $0 $0 $0 $0 $0 $150 TOTAL EXPENDITURES $0 Source of Funds ($000s) FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Placeholder Capital Projects Fund $0 $0 $0 $0 $0 $0 $0 $270 TOTAL FUNDS $0 XII - 15

Maintenance Reports Capital Improvements Program - Maintenance Summary of Programs - ($000's)

Responsible Department FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Board of Education $1,600 $225 $225 $425 $225 $250 $2,950 Electric $1,205 $1,000 $925 $925 $925 $835 $5,815 Public Works $2,625 $3,297 $3,389 $3,985 $2,801 $3,943 $20,040 Recreation and Parks $810 $780 $700 $450 $530 $490 $3,760 TOTAL CAPITAL IMPROVEMENTS PROGRAM $6,240 $5,302 $5,239 $5,785 $4,481 $5,518 $32,565 XIII - 1

Capital Improvements Program - Maintenance Summary of Projects By Responsible Department - ($000's)

Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Board of Education Blankenship Bleacher Renovation $500 $0 $0 $0 $0 $0 $500 District wide paving, sidewalk, and carpet replacement $150 $150 $150 $150 $150 $150 $900 Middle School Locker Replacement $0 $0 $0 $200 $0 $0 $200 Repair Ben Martin Track $450 $0 $0 $0 $0 $0 $450 Replace Districtwide Vehicles and Heavy Equipment $75 $75 $75 $75 $75 $100 $475 Replace JMS Bleachers $300 $0 $0 $0 $0 $0 $300 Replace Willow Brook Walk-In Freezer $125 $0 $0 $0 $0 $0 $125 Board of Education TOTAL: $1,600 $225 $225 $425 $225 $250 $2,950 Electric Routine Expansion, Maintenance, Replacement and $820 $640 $585 $585 $585 $585 $3,800 Minor Additions Traffic Signal, Public and Private Light Maintenance, $285 $260 $240 $240 $240 $150 $1,415 and Improvements Transmission System Maintenance $100 $100 $100 $100 $100 $100 $600 Electric TOTAL: $1,205 $1,000 $925 $925 $925 $835 $5,815 Public Works Capital Maintenance-Unspecified $50 $52 $53 $55 $56 $58 $324 EPA Phase II Municipal Separate Storm Sewer System $300 $300 $300 $300 $300 $300 $1,800 Program (MS4)

Sidewalk Improvements / ADA Compliance $100 $100 $100 $100 $100 $100 $600 Street Resurfacing $1,000 $1,100 $1,200 $1,300 $1,400 $1,500 $7,500 Wastewater Pump Station Replacement/Upgrades $415 $1,035 $535 $1,070 $285 $1,325 $4,665

  • duplicate XIII - 2

Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Water Booster Stations Upgrades $130 $130 $130 $130 $130 $130 $780 Water Distribution System and Tank/Reservoir $630 $580 $1,071 $1,030 $530 $530 $4,371 Rehabilitation Public Works TOTAL: $2,625 $3,297 $3,389 $3,985 $2,801 $3,943 $20,040 Recreation and Parks Blankenship Turf Replacement $55 $55 $55 $55 $55 $55 $330 Bleacher Replacement $0 $0 $150 $0 $0 $50 $200 Briarcliff Park $0 $0 $0 $0 $0 $120 $120 Centennial Golf Course $0 $30 $0 $30 $0 $30 $90 Civic Center Gym Floor Replacement $0 $250 $0 $0 $0 $0 $250 Fencing Replacement $35 $0 $35 $0 $35 $0 $105 Greenway Paving Rehab $0 $35 $0 $35 $0 $35 $105 Indoor Swimming Pool $80 $0 $0 $0 $0 $0 $80 Light Fixture Replacement at Ball Fields & Park $200 $200 $200 $300 $200 $200 $1,300 Facilities Melton Lake Park Playground $0 $0 $120 $0 $0 $0 $120 Outdoor Pavilion $400 $0 $0 $0 $0 $0 $400 Parking Lot Construction/Rehab $0 $30 $0 $30 $0 $0 $60 Scarboro Center Gym Floor Replacement $0 $0 $100 $0 $0 $0 $100 Solway Park $0 $180 $0 $0 $200 $0 $380 Tennis Court Refinishing $40 $0 $40 $0 $40 $0 $120 Recreation and Parks TOTAL: $810 $780 $700 $450 $530 $490 $3,760 TOTAL CAPITAL IMPROVEMENTS PROGRAM $6,240 $5,302 $5,239 $5,785 $4,481 $5,518 $32,565

  • duplicate XIII - 3

Capital Improvements Program - Maintenance Summary of Projects By Funding - ($000's)

Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Parking Lot Construction/Rehab $0 $30 $0 $30 $0 $0 $60 TOTAL: $0 $30 $0 $30 $0 $0 $60 Capirtal Projects Fund Replace Willow Brook Walk-In Freezer $125 $0 $0 $0 $0 $0 $125 Capirtal Projects Fund TOTAL: $125 $0 $0 $0 $0 $0 $125 Capital Project Funds Repair Ben Martin Track $450 $0 $0 $0 $0 $0 $450 Capital Project Funds TOTAL: $450 $0 $0 $0 $0 $0 $450 Capital Projects Fund Blankenship Bleacher Renovation $500 $0 $0 $0 $0 $0 $500 Blankenship Turf Replacement $55 $55 $55 $55 $55 $55 $330 Bleacher Replacement $0 $0 $150 $0 $0 $50 $200 Briarcliff Park $0 $0 $0 $0 $0 $120 $120 Capital Maintenance-Unspecified $50 $52 $53 $55 $56 $58 $324 Centennial Golf Course $0 $30 $0 $30 $0 $30 $90 Civic Center Gym Floor Replacement $0 $250 $0 $0 $0 $0 $250 District wide paving, sidewalk, and carpet replacement $150 $150 $150 $150 $150 $150 $900 EPA Phase II Municipal Separate Storm Sewer System Pr $300 $300 $300 $300 $300 $300 $1,800 Fencing Replacement $35 $0 $35 $0 $35 $0 $105 Greenway Paving Rehab $0 $35 $0 $35 $0 $35 $105 Indoor Swimming Pool $80 $0 $0 $0 $0 $0 $80

  • duplicate XIII - 4

Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Light Fixture Replacement at Ball Fields & Park Facilities $200 $200 $200 $300 $200 $200 $1,300 Melton Lake Park Playground $0 $0 $120 $0 $0 $0 $120 Middle School Locker Replacement $0 $0 $0 $200 $0 $0 $200 Outdoor Pavilion $400 $0 $0 $0 $0 $0 $400 Replace JMS Bleachers $300 $0 $0 $0 $0 $0 $300 Scarboro Center Gym Floor Replacement $0 $0 $100 $0 $0 $0 $100 Sidewalk Improvements / ADA Compliance $100 $100 $100 $100 $100 $100 $600 Solway Park $0 $180 $0 $0 $200 $0 $380 Tennis Court Refinishing $40 $0 $40 $0 $40 $0 $120 Capital Projects Fund TOTAL: $2,210 $1,352 $1,303 $1,225 $1,136 $1,098 $8,324 Capital Projects Funds Replace Districtwide Vehicles and Heavy Equipment $75 $75 $75 $75 $75 $100 $475 Capital Projects Funds TOTAL: $75 $75 $75 $75 $75 $100 $475 Electric Fund Routine Expansion, Maintenance, Replacement and Min $820 $640 $585 $585 $585 $585 $3,800 Traffic Signal, Public and Private Light Maintenance, and $285 $260 $240 $240 $240 $150 $1,415 Transmission System Maintenance $100 $100 $100 $100 $100 $100 $600 Electric Fund TOTAL: $1,205 $1,000 $925 $925 $925 $835 $5,815 State Street Aid Fund Street Resurfacing $1,000 $1,100 $1,200 $1,300 $1,400 $1,500 $7,500 State Street Aid Fund TOTAL: $1,000 $1,100 $1,200 $1,300 $1,400 $1,500 $7,500 Waterworks Fund Wastewater Pump Station Replacement/Upgrades $415 $1,035 $535 $1,070 $285 $1,325 $4,665 Water Booster Stations Upgrades $130 $130 $130 $130 $130 $130 $780 Water Distribution System and Tank/Reservoir Rehabilit $630 $580 $1,071 $1,030 $530 $530 $4,371

  • duplicate XIII - 5

Project FY2022 FY2023 FY2024 FY2025 FY2026 FY2027 Total Waterworks Fund TOTAL: $1,175 $1,745 $1,736 $2,230 $945 $1,985 $9,816 TOTAL CAPITAL IMPROVEMENTS PROGRAM $6,240 $5,302 $5,239 $5,785 $4,481 $5,518 $32,565

  • duplicate XIII - 6