IR 05000313/2021006

From kanterella
Revision as of 17:48, 8 March 2022 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Annual Assessment Letter for Arkansas Nuclear One, Units 1 & 2 (Report 05000313/2021006 and 05000368/2021006)
ML22053A344
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 03/02/2022
From: Ami Agrawal
NRC/RGN-IV/DORS/PBD
To: Sullivan J
Entergy Operations
References
IR 2021006
Download: ML22053A344 (8)


Text

March 2, 2022

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR ARKANSAS NUCLEAR ONE - UNITS 1 AND 2 (REPORT 05000313/2021006 AND 05000368/2021006)

Dear Mr. Sullivan:

The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Arkansas Nuclear One, Units 1 and 2, reviewing performance indicators (PIs),

inspection results, and enforcement actions from January 1, 2021 through December 31, 2021.

This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.

The NRC determined the performance at Arkansas Nuclear One, Units 1 and 2 during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e.,

Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2023.

The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In response to the COVID-19 public health emergency (PHE), the NRC adjusted inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. While the PHE continues, overall conditions throughout the country support performance of our inspection and oversight activities to return to normal onsite presence by our resident and region-based inspectors and completion of nominal baseline inspection samples. We continue to monitor site-specific conditions and as discussed in our November 2, 2021 memo, Implementation of Inspection Programs Following Re-Entry from the Public Health Emergency for the Reactor Safety Program (ML21295A302), it may be necessary to alter how and when we perform our inspection and oversight activities as we balance the importance of protecting the health and safety of our staff with the need to conduct effective oversight that supports the NRCs critical safety mission. For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.

The Regional Administrator has approved the staffs plan to conduct Inspection Procedure 71003, Post-Approval Site Inspection for License Renewal, at your facility as indicated in the enclosed inspection plan.

Inspection procedure (IP) 71111.21N.03 is included in the inspection plan as a placeholder for your next Design Basis Assurance Inspection (Programs), which will be focused on Commercial Grade Dedication. The inspection procedure will be developed and made publicly available before these inspections begin.

On March 12, 2018, the NRC issued a Confirmatory Order (ADAMS Accession No.

ML18072A191) (EA-17-132 and EA-17-153) to the Entergy fleet. On January 14, 2022, the NRC issued Inspection Report 05000416/2021010, which documented the completion of a follow-up inspection of Entergys implementation of actions required by the Confirmatory Order (ML22011A099). The inspection documented in that report represents the final completion of the NRCs planned follow-up inspection activities for the Confirmatory Order, and no additional inspections are included in the enclosed inspection plan.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at 817-200-1491 with any questions you have regarding this letter.

Sincerely,

/RA/

Ami N. Agrawal, Chief Project Branch D Division of Operating Reactor Safety Docket Nos. 05000313 and 05000368 License Nos. DPR-51 and NPF-6 Enclosure:

Inspection Plan

ML22053A344 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:

By: PJV Yes No Publicly Available Sensitive NRC-002 OFFICE SPE: DORS/C C: DORS/D NAME PVossmar AAgrawal SIGNATURE /RA/ /RA/

DATE 2/23/22 02/23/2022

Site Inspection Activity Plan 07200013 - ANO 01/01/2022 - 12/31/2023 Unit Start End Activity CAC Title Staff Count ANO ISFSI Triennial Loading Inspection (1 week in April)(Part 72) 2 1 4/1/2022 4/30/2022 IP 60855 001001 Operation Of An ISFSI Prepared on 2/22/2022 12:16:42 PM 1 of 4

Site Inspection Activity Plan Arkansas Nuclear One 01/01/2022 - 12/31/2023 Unit Start End Activity CAC Title Staff Count Phase 4 71003 Inspection 2 1 1/23/2022 1/29/2022 IP 71003 000687 Post-Approval Site Inspection for License Renewal Fire Protection Inspection - ANO 3 2 1/24/2022 2/4/2022 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)

2 2/14/2022 2/18/2022 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)

Security Protective Strategy .05 2 2 1/24/2022 1/27/2022 IP 71130.05 000737 Protective Strategy Evaluation ANO UNIT 1 2022 INITIAL EXAM 5 1 2/27/2022 3/5/2022 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1 4/3/2022 4/9/2022 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)

ANO ISFSI Triennial Loading Inspection (Part 50) Feeder for Residents 2 2 4/1/2022 4/2/2022 IP 60855 001001 Operation Of An ISFSI 10 CFR 50.59 Inspection - 17T - Arkansas Nuclear 3 2 5/16/2022 5/20/2022 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments Security Training/Equip Maint .07 and .04 2 2 5/16/2022 5/20/2022 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 2 5/16/2022 5/20/2022 IP 71130.07 000739 Security Training ANO UNIT 2 2022 BRQ 3 2 6/26/2022 7/2/2022 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance RP 5,8 - ANO 2 2 6/27/2022 7/1/2022 IP 71124.05 000729 Radiation Monitoring Instrumentation 2 6/27/2022 7/1/2022 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation EP 2022 Biennial Exercise & PI Inspection - ANO 4 2 8/8/2022 8/12/2022 IP 71114.01 000716 Exercise Evaluation 2 8/8/2022 8/12/2022 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 2 8/8/2022 8/12/2022 IP 71151 001397 Performance Indicator Verification Heat Exchanger/Sink Performance Inspection - 07T - Arkansas Nuclear 2 2 8/22/2022 8/26/2022 IP 71111.07T 000700 Heat Exchanger/Sink Performance Target Set Inspection -ANO 3 2 8/29/2022 9/16/2022 IP 71130.14 000743 Review of Power Reactor Target Sets Security Access Control .02 1 Prepared on 2/22/2022 12:16:42 PM 2 of 4

Site Inspection Activity Plan 2 9/12/2022 9/16/2022 IP 71130.02 000734 Access Control 2 9/12/2022 9/16/2022 IP 71130.09 001656 Security Plan Changes 2 9/12/2022 9/16/2022 IP 71151 001338 Performance Indicator Verification Inservice Inspection 1RF30 - ANO 1 1 10/10/2022 10/21/2022 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

RP 1,3,PI - ANO 2 2 10/17/2022 10/21/2022 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls Design Bases Assurance Inspection (Program) - 21N - Arkansas Nuclear 3 2 1/1/2023 6/30/2023 IP 71111.21N.03 Design Bases Assurance Inspections (Programs) 2023 (Commercial Grade Dedication)

Cyber Security Inspection - ANO 4 2 2/6/2023 2/9/2023 IP 71130.10 000741 Cybersecurity ANO UNIT 2 2023 INITIAL EXAM 4 2 1/29/2023 2/4/2023 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

2 3/5/2023 3/11/2023 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)

RP 1,4,PI - 2 2 3/27/2023 3/31/2023 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 2 3/27/2023 3/31/2023 IP 71124.04 000728 Occupational Dose Assessment Security Access Authorization .01 - Access Control .02 + PIV + Plan Change .09 2 2 6/5/2023 6/9/2023 IP 71130.01 000733 Access Authorization 2 6/5/2023 6/9/2023 IP 71130.02 000734 Access Control 2 6/5/2023 6/9/2023 IP 71130.09 001656 Security Plan Changes 2 6/5/2023 6/9/2023 IP 71151 001338 Performance Indicator Verification RP 6,7 2 2 6/12/2023 6/16/2023 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 2 6/12/2023 6/16/2023 IP 71124.07 000731 Radiological Environmental Monitoring Program ANO UNIT 1 2023 BRQ 3 1 7/9/2023 7/15/2023 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance ANO Biennial PI&R 4 2 8/7/2023 8/11/2023 IP 71152B 000747 Problem Identification and Resolution 2 8/21/2023 8/25/2023 IP 71152B 000747 Problem Identification and Resolution EP 2023 Program Inspection - ANO 1 2 8/28/2023 9/1/2023 IP 71114.02 000717 Alert and Notification System Testing 2 8/28/2023 9/1/2023 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 2 8/28/2023 9/1/2023 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 2 8/28/2023 9/1/2023 IP 71114.05 000720 Maintenance of Emergency Preparedness Prepared on 2/22/2022 12:16:42 PM 3 of 4

Site Inspection Activity Plan 2 8/28/2023 9/1/2023 IP 71151 001397 Performance Indicator Verification FORCE-ON-FORCE PLANNING AND EXERCISE - ANO 4 2 11/13/2023 11/17/2023 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 2 12/11/2023 12/15/2023 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Security FFD .08 1 2 11/13/2023 11/17/2023 IP 71130.08 000740 Fitness For Duty Program MC&A - 1 2 11/27/2023 12/1/2023 IP 71130.11 000742 Material Control and Accounting (MC&A)

Prepared on 2/22/2022 12:16:42 PM 4 of 4