E-Mail Acceptance of Application - Risk Informed Completion Times in Accordance with TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b,
ML21172A270
Person / Time
Site: Ginna Constellation icon.png
Issue date: 06/22/2021
From: V Sreenivas
NRC/NRR/DORL/LPL1
To: David Gudger, Hodge J
Exelon Generation Co LLC, Exelon Nuclear
Sreenivas V
References
EPID: L-2021-LLA-0091
Download: ML21172A270 (2)


Text

From: Sreenivas, V To: "Hodge, Jessie D:(Exelon Nuclear)"; "Gudger, David T:(Exelon Nuclear)"

Cc: Danna, James; Pascarelli, Robert; Carfang, Erin; Rosenberg, Stacey

Subject:

R.E.GINNA-Acceptance of Application - Risk Informed Completion Times in accordance with TSTF-505, Revision 2, "Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b,"(EPID: L-2021-LLA-0091)

Date: Tuesday, June 22, 2021 8:30:00 PM Attachments: image002.png By letter dated May 20, 2021, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML21140A324), Exelon Generation Company, LLC (Exelon, the licensee) submitted a license amendment request (LAR) for the R.E.

Ginna Nuclear Power Plant (Ginna). The proposed amendment would modify TS requirements to permit the use of Risk Informed Completion Times in accordance with TSTF-505, Revision 2, "Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b," (ADAMS Accession No. ML18183A493).

The purpose of this letter is to provide the results of the NRC staff's acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with 10 CFR 50.69, an amendment to the license (including the technical specifications) must fully describe the changes requested, and following, as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review, as compared to the detailed technical review, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified, despite completion of an adequate acceptance review.

You will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this request will take approximately 1370 hours0.0159 days <br />0.381 hours <br />0.00227 weeks <br />5.21285e-4 months <br /> to complete, excluding any contractor hours, if appropriate. The NRC staff expects to complete this review by June 22, 2022, 12 months from the date of this acceptance. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, and the contractor resources will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staff's initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRG in advance or in parallel with industry program initiatives or pilot applications.