MONTHYEARML21140A3142021-05-20020 May 2021 Notice of Public Meeting - Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Power Plants (Bv, CC, FP, Gn, Hc, Lm, NMP, Pb, SAL, & Sq) Project stage: Request ML21140A3242021-05-20020 May 2021 R. E. Ginna Nuclear Power Plant - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b Project stage: Request ML21141A0092021-05-20020 May 2021 R. E. Ginna Nuclear Power Plant - Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Project stage: Request ML21172A2702021-06-22022 June 2021 E-Mail Acceptance of Application - Risk Informed Completion Times in Accordance with TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Project stage: Acceptance Review ML21172A2692021-06-22022 June 2021 E Mail Acceptance of Application to Adopt 10 CFR 50.69, _Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors (Epid_ L-2021-LLA-0092) Project stage: Acceptance Review ML21222A1142021-08-25025 August 2021 R. E. Ginna Nuclear Power Plant - Audit Plan in Support of Review of License Amendment Request Regarding TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B and 10 CFR 50.69, Risk Informed Categoriza Project stage: Other ML21287A0062021-10-14014 October 2021 Supplemental Information No.1 for R.E. Ginna Nuclear Power Plant to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 and 10 CFR 50.69, - Risk-Informed Categorization and Treatment of Structu Project stage: Supplement ML22118B1432022-04-28028 April 2022 Supplemental Information No. 2 for R.E. Ginna Nuclear Power Plant to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b Project stage: Supplement ML22146A1042022-05-26026 May 2022 R. E. Ginna Nuclear Power Plant, Supplemental Information to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Project stage: Supplement ML22124A3162022-05-27027 May 2022 Summary of Combined Regulatory Audit in Support of Risk Informed Completion Times in Technical Specifications LAR and to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Project stage: Approval ML22160A4112022-06-0909 June 2022 Supplemental Information for R.E. Ginna Nuclear Power Plant to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 Project stage: Supplement ML22119A0942022-06-21021 June 2022 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 150 Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B Project stage: Approval ML22094A1072022-06-22022 June 2022 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 151 Adopt 10 CFR 50.69, 'Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Project stage: Approval 2022-04-28
[Table View] |
Similar Documents at Ginna |
---|
Category:Letter
MONTHYEARIR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 ML24026A0112024-01-26026 January 2024 R. E. Ginna Nuclear Power Plant, Relief Request Associated with Inservice Testing of B Auxiliary Feedwater Pump IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 ML23348A0992023-12-15015 December 2023 R. E. Ginna Nuclear Power Plant Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0029 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23347A0092023-12-13013 December 2023 Annual Commitment Change Notification ML23346A0142023-12-12012 December 2023 LLC - Senior Reactor and Reactor Operator Initial License Examinations ML23341A1252023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements ML23321A1392023-11-17017 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information and Request for Additional Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 ML23292A0282023-10-19019 October 2023 LLC - Notification of Conduct of a Fire Protection Team Inspection RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23258A1382023-09-18018 September 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000244/2023010 IR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23235A1722023-08-23023 August 2023 Re. Ginna Nuclear Power Plant, Transmittal of 2023 Owner'S Activity Report IR 05000244/20234012023-08-15015 August 2023 LLC - Material Control and Accounting Program Inspection Report 05000244/2023401 (Cover Letter Only) IR 05000244/20230022023-08-0303 August 2023 LLC - Integrated Inspection Report 05000244/2023002 ML23191A0592023-07-21021 July 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 155 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 IR 05000244/20234022023-07-19019 July 2023 R. E. Ginna Nuclear Power Plant - Security Baseline Inspection Report 05000244/2023402 (Cover Letter Only) RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-050, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube.2023-05-22022 May 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube. ML23135A0412023-05-15015 May 2023 2022 Annual Radioactive Effluent Release Report and 2022 Annual Radiological Environmental Operating Report ML23121A0482023-05-0101 May 2023 R. E. Ginna Nuclear Power Plant Core Operating Limits Report Cycle 44, Revision 0 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI IR 05000244/20230012023-04-26026 April 2023 LLC - Integrated Inspection Report 05000244/2023001 ML23100A0302023-04-10010 April 2023 2023 10 CFR 50.46 Annual Report ML23114A1152023-03-29029 March 2023 Electronic Reporting of Exposure Data for 2022 RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23075A0872023-03-15015 March 2023 R. E. Ginna Nuclear Power Plant - Project Manager Assignment ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000244/20220062023-03-0101 March 2023 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2022006) ML22364A0242023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant Issuance of Amendments Nos. 231, 231, 232, 232, and 154 Regarding Adoption of TSTF-246 ML23060A1622023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant, Supplemental Information - Proposed Alternatives Related to the Steam Generators RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 ML23005A1762023-02-23023 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 153 Revise Technical Specifications (TS) for the Spent Fuel Pool Charcoal System and Two (2) TS Administrative Changes ML23005A1222023-02-22022 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No 152 Adopt TSTF-315-Revise Technical Specification 3.1.8, Physics Tests Exceptions - Mode 2 RS-23-040, Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators2023-02-21021 February 2023 Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators ML22287A0692023-02-0808 February 2023 R. E. Ginna Station - Forward Fit Analysis (Epids L-2022-LRR-0074, 0076, 0079, 0091, 0092, 0093 and 0094) ML23031A2992023-02-0707 February 2023 R. E. Ginna Nuclear Power Plant - Withdrawal of an Amendment Request ML23010A0112023-02-0101 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Relief Request Associated with Inservice Testing of Refueling Water Storage Tank Outlet Value RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 IR 05000244/20223012023-01-20020 January 2023 Initial Operator Licensing Examination Report 05000244/2022301 IR 05000244/20220122023-01-12012 January 2023 LLC - Design Basis Assurance Inspection (Teams) Inspection Report 05000244/2022012 ML22362A0382022-12-28028 December 2022 R. E. Ginna Nuclear Power Plant - Letter to Withdraw Application to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML22348A2062022-12-14014 December 2022 Re. Ginna Nuclear Power Plant - Annual Commitment Change Notification RS-22-123, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator2022-12-0707 December 2022 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator 2024-02-05
[Table view] |
Text
200 Exelon Way Kennett Square, PA 19348 www.constellation.com 10 CFR 50.90 May 26, 2022 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 R. E. Ginna Nuclear Power Plant Renewed Facility Operating License No. DPR-18 NRC Docket No. 50-244
Subject:
Supplemental Information for R.E. Ginna Nuclear Power Plant to Adopt 10 CFR 50.69, Risk-Informed categorization and treatment of structures, systems and components for nuclear power reactors.
References:
- 1. Letter from D. Gudger (Exelon Generation Company, LLC) to U.S. Nuclear Regulatory Commission, Application to Adopt 10 CFR 50.69, Risk-Informed categorization and treatment of structures, systems and components for nuclear power reactors, dated May 20, 2021 (ML21141A009)
- 2. Letter from D. Gudger (Exelon Generation Company, LLC) to U.S. Nuclear Regulatory Commission, Supplemental Information No. 1 for R.E. Ginna Nuclear Power Plant to Adopt TSTF-505, 'Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b', Revision 2 and 10 CFR 50.69, Risk-Informed categorization and treatment of structures, systems and components for nuclear power reactors. dated October 14, 2021 (ML21287A006)
This letter is a supplement to Reference 1. Exelon Generation Company, LLC (Exelon) proposed an amendment to change the R. E. Ginna Nuclear Power Plant (Ginna) Technical Specification (TS). The proposed amendment would modify the licensing basis in accordance with the application to adopt 10 CFR 50.69, Risk-Informed categorization and treatment of structures, systems and components for nuclear power reactors, (ADAMS Accession No. ML21141A009). By letter dated October 14, 2021 (Reference 2), Exelon provided supplemental information to the proposed amendment (Reference 1). Attachment 3 of Reference 2 provides a suggested license condition. This letter provides clarification on the proposed license condition and supersedes what was provided in Attachment 3 of Reference 2.
U.S. Nuclear Regulatory Commission Supplemental Information for 10 CFR 50.69 Docket No. 50-244 May 26, 2022 Page 2 Constellation Energy Generation, LLC (CEG) has reviewed the information supporting a finding of no significant hazards consideration and the environmental consideration provided to the NRC in Reference 1. The responses provided in this letter do not affect the bases for concluding that the proposed license amendment does not involve a significant hazards consideration. Furthermore, the responses provided in this letter do not affect the bases for concluding that neither an environmental impact statement nor an environmental assessment needs to be prepared in connection with the proposed amendment.
There are no commitments contained in this response.
In accordance with 10 CFR 50.91, "Notice for public comment; State consultation,"
paragraph (b), EGC is notifying the State of New York of this application for license amendment by transmitting a copy of this letter and its attachments to the designated State Official.
Should you have any questions concerning this letter, please contact Jessie Hodge at (610) 765-5532.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 26th day of May 2022.
Respectfully, David T. Gudger Senior Manager - Licensing Constellation Energy Generation, LLC Attachments: 1. License Condition Information cc: USNRC Region I, Regional Administrator w/ attachments USNRC Senior Resident Inspector, Ginna "
USNRC Project Manager, Ginna "
A. L. Peterson, NYSERDA "
ATTACHMENT 1 License Amendment Request R. E. Ginna Nuclear Power Plant Renewed Facility Operating License No. DPR-18 Docket No. 50-244 License Condition Information
Supplemental Information for Attachment 1 10 CFR 50.69 Page 1 of 1 Docket No. 50-244 Constellation proposes the addition of the following condition to the renewed operating license of Ginna to document the NRCs approval of the use 10 CFR 50.69.
Constellation Energy Generation, LLC is approved to implement 10 CFR 50.69 using the processes for categorization of Risk-Informed Safety Class (RISC)-1, RISC-2, RISC-3, and RISC-4 Structures, Systems, and Components (SSCs) using:
Probabilistic Risk Assessment (PRA) models to evaluate risk associated with internal events, including internal flooding, and internal fire; the shutdown safety assessment process to assess shutdown risk; the Arkansas Nuclear One, Unit 2 (ANO-2) passive categorization method to assess passive component risk for Class 2 and Class 3 and non-Class SSCs and their associated supports; the results of the non-PRA evaluations that are based on the IPEEE Screening Assessment for External Hazards updated using the external hazard screening significance process identified in ASME/ANS PRA Standard RA-Sa-2009 for other external hazards except seismic; and the alternative seismic approach as described in Exelon's submittal letter dated
[May 20, 2021], and all its subsequent associated supplements as specified in License Amendment No. [XXX] dated [DATE].
Constellation Energy Generation, LLC will complete the implementation items listed in Attachment 7 of Exelon Letter to the NRC dated May 20, 2021, prior to implementation of 10 CFR 50.69. All issues identified in the attachment will be addressed and any associated changes will be made, focused-scope peer reviews will be performed on changes that are PRA upgrades as defined in the PRA standard (ASME/ANS RA-Sa -2009, as endorsed by RG 1.200, Revision 2), and any findings will be resolved and reflected in the PRA of record prior to the implementation of 10 CFR 50.69.
Prior NRC approval, under 10 CFR 50.90, is required for a change to the categorization process specified above (e.g., change from a seismic margins approach to a seismic probabilistic risk assessment approach).