Similar Documents at Salem |
---|
Category:E-Mail
MONTHYEARML24277A0812024-10-0303 October 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon Collected on 10/02/2024 ML24269A0362024-09-24024 September 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 9/24/2024 ML24248A0452024-09-0303 September 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 9/3/2024 ML24229A0422024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Implement Optimized ZIRLO Fuel Rod Cladding ML24229A0432024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Exemption from 10 CFR 50.46 and 10 CFR 50 Appendix K to Allow the Use of Optimized ZIRLO Fuel Rod Cladding ML24228A1942024-08-14014 August 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form for a Live - Atlantic Sturgeon 8/14/2024 ML24227A5092024-08-14014 August 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 8/13/2024 ML24250A0562024-07-11011 July 2024 PSEG to NMFS, Regarding Processing of Fin Clips ML24219A2472024-07-0909 July 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Shortnose Sturgeon 7/9/2024 ML24123A0522024-05-0101 May 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - One Deceased Sturgeon 4/30/2024 ML24106A0542024-04-12012 April 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - One Alive Atlantic Sturgeon 4/12/2024 ML24101A2192024-04-0909 April 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 4/8/24 ML24093A1222024-04-0101 April 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - One Atlantic Sturgeon 4/1/2024 ML24075A1862024-03-14014 March 2024 NRR E-mail Capture - (External_Sender) Biological Opinion Gar 2020-02842 - PSEG Salem and Hope Creek Generating Station Annual Incidental Take Report - 2023 ML24060A0492024-02-28028 February 2024 NRR E-mail Capture - Final Exhb RAI for Hope Creek, Salem 1 and 2 Amendment to Modify Exclusion Area Boundary ML24030A8432024-01-30030 January 2024 NRR E-mail Capture - (External_Sender) 2023 PSEG Sturgeon Pit Tag Data ML24016A1612024-01-10010 January 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms - Two Atlantic Sturgeon 1/9/2024 ML24002A7222023-12-29029 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - 2023 Annual Report - Inspection of the Circulating Water Intake Structure (Cwis) Trash Rack Bars ML24002A7242023-12-28028 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - Sturgeon 12/28/2023 ML23355A2732023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) PSEG Response to Questions Associated with Supplement to Salem-Hope Creek Eab Reduction LAR ML24002A7252023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Shortnose Sturgeon 12/21/23 ML23346A0962023-12-0606 December 2023 NRR E-mail Capture - Reminder - Final Report - Completion of Required Additional Protocol (AP) Information in Accordance with the U.S. - IAEA Treaty Obligations ML23311A0792023-11-0101 November 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Atlantic Sturgeon Collected on 10/31/2023 ML23277A0482023-10-0404 October 2023 NRR E-mail Capture - 10/4/2023 Email: Acceptance Review - Hope Creek and Salem 1 and 2 - LAR to Modify Exclusion Area Boundary ML23277A0732023-09-29029 September 2023 NRR E-mail Capture - (External_Sender) 9/29/2023 Email from PSEG: Supplement to Proposed Amendment to PSEG Master Decommissioning Trust Amendment ML23226A0702023-08-11011 August 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form for Sturgeon Collected on 8/10/2023 ML23226A0732023-08-10010 August 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Submittal of Necropsy Reports Regarding Sea Turtles Collected on 06/12/2022 ML23201A0132023-07-20020 July 2023 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML23172A0982023-06-21021 June 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 06/20/2022 ML23164A2062023-06-13013 June 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 06/12/2023 ML23163A0442023-06-0606 June 2023 NRR E-mail Capture - (External_Sender) Biological Opinion GAR-2020-02842; FIN Clip Analysis Facilities ML24250A0572023-06-0606 June 2023 PSEG to NMFS, Request for Sturgeon Fin Clip Analysis Facilities ML23153A1552023-06-0202 June 2023 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 6/1/2023 ML23151A6582023-05-31031 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms Sturgeon 5/30/2023 ML23137A2632023-05-17017 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms Sturgeon 5/16/2023 ML23135A0102023-05-11011 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Sturgeon 5/11/2023 ML23136B2832023-05-0404 May 2023 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 5/3/2023 ML23122A1982023-05-0202 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms for Atlantic Sturgeon 5/1/2023 ML23122A1672023-05-0202 May 2023 NRR E-mail Capture - Acceptance Review - Hope Creek and Salem 1 and 2 - Revise TS to Delete TS Section 5.5 - Meteorological Tower Location ML23117A2722023-04-17017 April 2023 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 04/14/2023 ML23079A0032023-03-17017 March 2023 NRR E-mail Capture - Hope Creek, Salem 1 and 2 - Evacuation Time Estimate Review ML23065A0452023-02-23023 February 2023 NRR E-mail Capture - (External_Sender) Salem & Hope Creek Generating STATIONS-ANNUAL Incidental Take REPORT-STATION & REMP ML23033A0302023-02-0808 February 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Sturgeon 1/24/2023 ML23010A2882023-01-10010 January 2023 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 01/09/2023 ML23003A2412023-01-0303 January 2023 NRR E-mail Capture - Final Nvib RAI - Salem Unit 2 Relief Request S2-I4R-211, Fourth Inservice Inspection (ISI) Interval Limited Examinations ML22357A0102022-12-21021 December 2022 NRR E-mail Capture - Final Nphp RAI - Salem Unit 2 Relief Request S2-I4R-211, Fourth Inservice Inspection (ISI) Interval Limited Examinations ML23003A2402022-12-21021 December 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form for Atlantic Sturgeon Collected on 12/20/2022 ML23003A2392022-12-20020 December 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms for Atlantic Sturgeons Collected 12/19/2022 ML22333A9022022-11-29029 November 2022 NRR E-mail Capture - Final Iolb RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22291A3702022-10-18018 October 2022 NRR E-mail Capture - Acceptance Review - Salem 2 - Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations (L-2022-LLR-0066) 2024-09-03
[Table view] |
Text
From: Cary, Richard H. <Richard.Cary@pseg.com>
Sent: Wednesday, August 11, 2021 9:09 AM To: incidental.take@noaa.gov; EndangeredSpecies Resource Cc: Neilan, Brian
Subject:
[External_Sender] Salem Generating Station - Incidental Take Report: Kemp's Ridley Sea Turtle 08/10/2021 Attachments: Sea turtle Incidental Take Report 8-10-21.pdf Attached is the Incidental Take Report for a deceased Kemps ridley sea turtle collected on 08/10/2021 from the Salem Generating Station during routine raking of the cooling water intake trash bars. The specimen is in cold storage and awaiting transport to the NJ Marine Mammal Stranding Center for potential necropsy. This incidental take is authorized under Biological Opinion NER-2010-6581.
Thanks, and please let me know if you have any questions or need additional information.
Richard Cary Environmental Compliance & Program Manager PSEG Nuclear Environmental Affairs O: 856-339-1487 The information contained in this e-mail, including any attachment(s), is intended solely for use by the named addressee(s). If you are not the intended recipient, or a person designated as responsible for delivering such messages to the intended recipient, you are not authorized to disclose, copy, distribute or retain this message, in whole or in part, without written authorization from PSEG. This e-mail may contain proprietary, confidential or privileged information. If you have received this message in error, please notify the sender immediately. This notice is included in all e-mail messages leaving PSEG. Thank you for your cooperation.
Hearing Identifier: NRR_DRMA Email Number: 1311 Mail Envelope Properties (c4d5b57685c048c08573069dfee309db)
Subject:
[External_Sender] Salem Generating Station - Incidental Take Report: Kemp's Ridley Sea Turtle 08/10/2021 Sent Date: 8/11/2021 9:08:52 AM Received Date: 8/11/2021 9:09:49 AM From: Cary, Richard H.
Created By: Richard.Cary@pseg.com Recipients:
"Neilan, Brian" <Brian.Neilan@dep.nj.gov>
Tracking Status: None "incidental.take@noaa.gov" <incidental.take@noaa.gov>
Tracking Status: None "EndangeredSpecies Resource" <EndangeredSpecies.Resource@nrc.gov>
Tracking Status: None Post Office: pseg.com Files Size Date & Time MESSAGE 1253 8/11/2021 9:09:49 AM Sea turtle Incidental Take Report 8-10-21.pdf 513227 Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
APPENDIX B - Part 1 (Sea Turtle)
Incident Report Sea Turtle Take - PSEG Salem Generating Station Photographs should be taken and the following information should be collected from all turtles and sturgeon (alive and dead) found in association with Salem. Please submit all turtle necropsy results (including sex and stomach contents) to NMFS upon receipt.
Observer's full name: Stephen Whitford (ECSI)
Reporters full name: Stephen Whitford (ECSI)
Species Identification (Key attached): Kemps ridley (Lepidochelys kempii)
Site of Impingement (Unit 1 or 2, CWS or DWS, Bay #, etc.): CWIS, Unit 1, 12A intake bay Date animal observed: 08-10-21 Time animal observed: 08:30 AM Date animal collected: 08-10-21 Time animal collected: 08:25 AM Date rehab facility contacted: 08-10-21 Time rehab facility contacted: 09:00 AM Date animal delivered to facility: NA Time animal delivered to facility: NA Marine Mammal Stranding Center (MMSC) was contacted in regards to their interest in taking possession of the turtle. Due to staff being unavailable to complete the pick-up at this time, they requested that the specimen be placed in cold storage. An arraignment to pick-up the specimen will be made at a later date.
Environmental conditions at time of observation (i.e., tidal stage, weather):
Salinity: 6.0ppt Sky condition: partly cloudy Tide: Flood 1 (90.0ft.) Air temp. 24.0°C Wave height: slight Wind - SW Date and time of last inspection of screen: 08/10/21 @ 06:51 AM Water temperature (°C) at site and time of observation: 26.0°C Number of pumps operating at time of observation: 12 Circulators in operation Average percent of power generating capacity achieved per unit at time of observation: Unit 1-99.8 % / Unit 2-100.1%
Average percent of power generating capacity achieved per unit over the 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> previous to observation: Unit 1-99.8 %
/ Unit 2-100.0%
Sea Turtle Information: (please designate cm/m or inches)
Fate of animal (circle one): dead alive Condition of animal (include comments on injuries, whether the turtle is healthy or emaciated, general behavior while at Salem. During routine trash rack cleaning, Salem Yard Crew personnel retrieved a deceased Kemps ridley sea turtle from Salem Unit 1, 12A circulator intake bay. Salem Unit Control and PSEG Nuclear Environmental Affairs personnel were notified. After contacting PSEG Nuclear Environmental Affairs (NEA) personnel, Environmental Consulting Services Inc. (ECSI) personnel verified species identification and began processing of the specimen. An exact cause of death remains unknown, as no obvious indication of external damage was observed.
Carapace length - Curved: 28.5cm Straight: 25.4cm Carapace width - Curved: 28.5cm Straight: 26.0cm Existing tags? YES / NO Please record all tag numbers. Tag # _____________________
Photograph attached: YES / NO 1
APPENDIX B, continued (Incident Report of Sea Turtle Take)
Draw wounds, abnormalities, tag locations on diagram and briefly describe below.
Description of animal:
At the time of observation at 08:30AM, the specimen did not reveal any evidence of external damage, and it appeared to be in good condition. However, the specimen did not show movement, and its eyes appeared to be in a dried-out condition, indicating that it was likely no longer living. External tags were not observed, and an internal PIT tag was not indicated.
All information should be sent to the following address:
National Marine Fisheries Service, Northeast Region Protected Resources Division Attention: Section 7 Coordinator 55 Great Republic Drive Gloucester, MA 01930 Phone: (978) 281-9328 FAX: (978) 281-9394 2
Salem SGS Incidental Take Report - Sea Turtle Attachment 1 Dorsal view of a Kemps ridley sea turtle, as it appeared after retrieval from Salem CWIS intake on 08-10-2021 by Salem Yard crew personnel during routine trash rack cleaning. No obvious damage was observed, however the specimen did not elicit a reflex response after gentle stimulation (08/10/2021).
A dorsolateral view of the left side of the head. No indication of damage was observed to the head, flippers or to the lower extremities (08/10/2021).
3
Salem SGS Incidental Report-Sea Turtle Attachment 1 A ventral view showing the condition of the plastron. No injuries or obvious damage was observed (08/10/2021).
In addition to the characteristic round body appearance, the existence of distinct pores near the margins of each of the inframarginal scutes, on the right and left side of the plastron (located within the red circle in photo) were identified, verifying the specimen as a Kemps ridley [08/10/2021].
4