August 2003 - Pilot Project 5 Work Product Plan
ML20104A931
Person / Time
Issue date: 04/13/2020
From:
Office of Nuclear Material Safety and Safeguards
To:
Lukes K
References
Download: ML20104A931 (4)


Text

WORK PRODUCT PLAN National Materials Program-Pilot Project No. 5 Revised Inspection Manual Chapter (IMC) 2800, Materials Inspection Program Target Date Completion Date Product Process (Revised to)

January 2002 January 2002

  • Phase II Recommendations Action Plan
  • IMNS approved Action Plan for Revised IMC 2800
  • RGB Memo to DNMS Directors RE
  • Recruitment Memo for Writing Team Appointed WT members and PRT (WT) and Pink/Red Team (PRT)
  • DNMS comments to RGB to proceed to revise IMC 2800 February 2002 February 2002
  • Charter for WT and PRT to describe the
  • WT teleconference.

project objective, scope, organization and

  • WT Kick-off meeting in Rockville operations, members, schedule, and level
  • WT developed draft Charter of effort.
  • PRT/WT teleconference, discussed draft Charter April 2002 April 2002
  • Temporary Instruction (TI)
  • PRT/WT teleconference, approved
  • Revised IMC 2800 (TI, Attachment A) Charter with comments incorporated
  • Training for regional inspectors
  • WT meeting in Rockville, drafted TI and revised IMC 2800 and developed training session for inspectors.
  • Pilot Chair provided TI and revised IMC 2800 to RGB to post in the NRC Inspection Manual on the web
  • WT provided TI training to Regional inspectors.
  • TI implementation initiated by regional inspectors.
  • WT teleconferences about logistics for TI implementation; developed template for revised inspection procedures (IPs),

Page 2 of 4 Target Date Completion Date Product Process (Revised to)

May 2002 May 2002

  • CRCPD Annual Meeting session
  • WT member from OAS/CRCPD prepared presentation and poster presentation and presented information about the TI and invited the States to participate in the Pilot Program.

June 2002 June 2001

  • NMSS Newsletter Article about the TI
  • Pilot Chair drafted NMSS Newsletter article about the TI.

October 2002 October 2002

  • IMNS revised medical IPs to be
  • WT revised the TI to accommodate the medical IPs and revised IMC 2800.
  • WT completed mid-pilot analysis
  • Pilot Chair provided revised TI, IMC 2800, and 5 revised medical IPs to RGB to post in the NRC Inspection Manual on the web January 2003 January 2003
  • WT revised 7 non-medical IPs to be
  • IMC 2800, revision 02 implemented under the TI.
  • 7 revised non-medical IPs
  • PRT/WT teleconference discussed non-
  • Refresher training for regional inspectors medical IPs.
  • Revise Charter for the NMP-PP
  • Pilot Chair provided revised TI, IMC 2800, and 7 revised non-medical IPs to RGB to post in the NRC Inspection Manual on the web.
  • WT provided refresher training to Regional inspectors.
  • WT and PRT approved revised Charter with comments incorporated.

Page 3 of 4 Target Date Completion Date Product Process (Revised to)

March 2003 June 2003

  • Work Product Plan to STP for NMP-PP
  • Pilot Chair developed Work Product Plan (June 2003) No. 5 from Charter; STP obtains concurrence

IMC 2800 revision 02, and 12 routine IPs

  • STP posted work products to NMP web page for review and comment by Agreement States.

July 2003 July 2003

  • draft Final Analysis of TI
  • WT meeting in Rockville (7/14-18) to
  • draft Final Version of IMC 2800 resolve comments and prepare draft final
  • 7 revised non-medical IPs versions.
  • draft Success Measures Report for
  • PRT/WT teleconference (7/16) to discuss NMP-PP No. 5 progress and unresolved issues.

August 2003

  • Final Versions of work products
  • PRT review and comment
  • PRT/WT teleconference to discuss comments
  • WT incorporates comments September 2003
  • Final Versions of work products with
  • PRT approves final versions comments incorporated October 2003
  • Final Versions posted in NRC Inspection
  • Pilot Chair provides final versions to RGB Manual on the web to post in the NRC Inspection Manual on the web
  • OAS annual meeting
  • Chair to provide update to IMNS for presentation January 2004 01/14
  • Progress report to STP
  • Chair updates NMP-PP Team Leader 01/23
  • Draft Progress report to Chairs
  • Chair reviews draft Progress Report 01/29
  • Comments due to STP
  • Chair provide comments to Team Leader

Page 4 of 4 Target Date Completion Date Product Process (Revised to)

February 2004 02/02

  • Chair provides to STP, NRC offices, and CRCPD OAS, CRCPD for review and comment 02/18
  • Chair updates NMP-PP Team Leader OAS, and CRCPD March 2004 03/15
  • Chairs complete reviews of draft versions
  • Pilot Chair to participate in, provide input 03/19
  • Concurrence on Progress Report due to to, and review a progress report which is STP due to the Commission on March 31, 03/24
  • Submit Progress Report to EDO 2004 03/31
  • Submit Progress Report to the Commission April 2004
  • Final NMP-PP report of work products
  • NMP-PP Team Leader and Chairs June 15, 2004
  • draft final report to the Commission
  • end comment period for draft final report August 31, 2004
  • final report to the Commission
  • STP incorporates comments September 30,
  • final report to the Commission
  • final report to the Commission
  • STP Director concurs and submits final 11/05 report to EDO
  • EDO concurs and submits final report to 11/12 the Commission