Request for Additional Information on Amendment Request Regarding one-time Extension of Containment Type a Test Interval
ML021430224
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 05/23/2002
From: Subbaratnam R
NRC/NRR/DLPM/LPD2
To: Moyer J
Carolina Power & Light Co
Subbaratnam R, NRR/DLPM, 415-1478
References
TAC MB4658
Download: ML021430224 (6)


Text

May 23, 2002 Mr. J. W. Moyer, Vice President Carolina Power & Light Company H. B. Robinson Steam Electric Plant, Unit No. 2 3581 West Entrance Road Hartsville, South Carolina 29550

SUBJECT:

H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 - REQUEST FOR ADDITIONAL INFORMATION (RAI) ON AMENDMENT REQUEST REGARDING ONE-TIME EXTENSION OF CONTAINMENT TYPE A TEST INTERVAL (TAC NO.

MB4658)

Dear Mr. Moyer:

By letter dated March 26, 2002, you submitted a request for a technical specifications change regarding a one-time extension of the containment type A test interval for the H. B. Robinson Steam Electric Plant, Unit No. 2. We reviewed the information that you have provided in the subject amendment request, but we need additional information to complete our review.

This request for information was discussed with Mr.Chuck Baucom and your staff on May 14, 2002, and a mutually agreeable schedule of within 30 days of receipt of this RAI was established for your response. The RAI is enclosed.

We will make every effort to meet your requested date of August 1, 2002, but that date may be impacted by the time required to process the RAI response. We appreciate your efforts for facilitating our review.

If you have any questions regarding this request, please contact me at (301) 415-1478.

Sincerely,

/RA/

Ram Subbaratnam, Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-261

Enclosure:

RAI cc w/encl: See next page

May 23, 2002 Mr. J. W. Moyer, Vice President Carolina Power & Light Company H. B. Robinson Steam Electric Plant, Unit No. 2 3581 West Entrance Road Hartsville, South Carolina 29550

SUBJECT:

H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 - REQUEST FOR ADDITIONAL INFORMATION (RAI) ON AMENDMENT REQUEST REGARDING ONE-TIME EXTENSION OF CONTAINMENT TYPE A TEST INTERVAL (TAC NO.

MB4658)

Dear Mr. Moyer:

By letter dated March 26, 2002, you submitted a request for a technical specifications change regarding a one-time extension of the containment type A test interval for the H. B. Robinson Steam Electric Plant, Unit No. 2. We reviewed the information that you have provided in the subject amendment request, but we need additional information to complete our review.

This request for information was discussed with Mr.Chuck Baucom and your staff on May 14, 2002, and a mutually agreeable schedule of within 30 days of receipt of this RAI was established for your response. The RAI is enclosed.

We will make every effort to meet your requested date of August 1, 2002, but that date may be impacted by the time required to process the RAI response. We appreciate your efforts for facilitating our review.

If you have any questions regarding this request, please contact me at (301) 415-1478.

Sincerely,

/RA/

Ram Subbaratnam, Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-261

Enclosure:

RAI cc w/encl: See next page DISTRIBUTION:

PUBLIC TKoshy RSubbaratnam EDunnington DTerao ACRS PDII-2 Rdg OGC MSnodderlyJIbarra RGoel BBonser, RII ADAMS ACCESS.NO.ML021430224 PM:PDII-S2 LA:PDII-S2 SC:PD II-S2 RSubbaratnam EDunnington TKoshy 5/22/02 5/22/02 5/22/02 Yes/No Yes/No Yes/No OFFICIAL RECORD COPY

REQUEST FOR ADDITIONAL INFORMATION ON AMENDMENT REQUEST REGARDING ONE-TIME EXTENSION OF CONTAINMENT TYPE A TEST INTERVAL FOR CAROLINA POWER & LIGHT COMPANY H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 (HBRSEP2)

DOCKET NO. 50-261

1. The stainless steel bellows were found to be susceptible to transgranular stress corrosion cracking, and the leakages through them are not readily detectable by Type B testing. If this issue applies to your containment, please explain how such behavior has been factored into the risk assessment and provide information regarding inspection and testing of the bellows at HBRSEP2.
2. Inspections of some reinforced and steel containment systems have found degradation on the uninspectable (embedded) side of the drywell steel shell and steel liner of the primary containment. These degradations cannot be found by visual examinations until they are through the thickness of the shell or liner, or when 100% of the uninspectable surfaces are examined by ultrasonic testing. Please indicate how potential leakages during core damage accidents are factored into the risk assessment related to the extension of the integrated leak rate testing. In the submittal, you stated that you have made measurements on a sample of liner panels. How were the remaining uninspected panels considered in the risk assessment? Calvert Cliffs Nuclear Power Plant recently provided information (ADAMS Accession No. ML020920100) in response to a similar request to address this issue. It would be desirable to consider the Calvert Cliffs Nuclear Power Plants response when amending the current submittal.

Mr. D. E. Young H. B. Robinson Steam Electric Carolina Power & Light Company Plant, Unit No. 2 cc:

Mr. William D. Johnson Mr. Mel Fry, Director Vice President and Corporate Secretary N.C. Department of Environment Carolina Power & Light Company and Natural Resources Post Office Box 1551 Division of Radiation Protection Raleigh, North Carolina 27602 3825 Barrett Dr.

Raleigh, North Carolina 27609-7721 Ms. Karen E. Long Assistant Attorney General Mr. Robert P. Gruber State of North Carolina Executive Director Post Office Box 629 Public Staff - NCUC Raleigh, North Carolina 27602 4326 Mail Service Center Raleigh, North Carolina 27699-4326 U.S. Nuclear Regulatory Commission Resident Inspectors Office Mr. Virgil R. Autry, Director H. B. Robinson Steam Electric Plant South Carolina Department of Health 2112 Old Camden Road Bureau of Land & Waste Management Hartsville, South Carolina 29550 Division of Radioactive Waste Management 2600 Bull Street Mr. T. D. Walt Columbia, South Carolina 29201 Plant General Manager Carolina Power & Light Company Mr. Terry C. Morton H. B. Robinson Steam Electric Plant, Unit No. 2 Manager 3581 West Entrance Road Performance Evaluation and Hartsville, SC 29550 Regulatory Affairs CPB 7 Carolina Power & Light Company Mr. J. W. Moyer Post Office Box 1551 Director of Site Operations Raleigh, North Carolina 27602-1551 Carolina Power & Light Company H. B. Robinson Steam Electric Plant, Unit No. 2 Mr. John H. ONeill, Jr.

3581 West Entrance Road Shaw, Pittman, Potts & Trowbridge Hartsville, South Carolina 29550 2300 N Street, NW.

Washington, DC 20037-1128 Public Service Commission State of South Carolina Post Office Drawer 11649 Columbia, South Carolina 29211 Mr. R. L. Warden Manager - Regulatory Affairs Carolina Power & Light Company Supervisor, Licensing/Regulatory Programs H. B. Robinson Steam Electric Plant, Carolina Power & Light Company Unit No. 2 H. B. Robinson Steam Electric Plant, 3581 West Entrance Road Unit No. 2 Hartsville, South Carolina 29550-0790 3581 West Entrance Road Hartsville, South Carolina 29550