MONTHYEARIR 05000261/20240042024-10-0303 October 2024 Document Request for Robinson Nuclear Plant - Radiation Protection Inspection - Inspection Report 05000261/2024004 ML24179A1292024-06-24024 June 2024 Acceptance Review for LAR to Revise TS to Adopt TSTF-234-A, Revision 1 ML24164A0052024-06-11011 June 2024 NRR E-mail Capture - Request for Additional Information Regarding Dukes February 15, 2024, Relief Request RA-23-0300 for Robinson ML24079A3062024-03-19019 March 2024 NRR E-mail Capture - Acceptance Review Results for Robinson - Proposed Relief Request RA-23-0300 ML24002A7382024-01-0202 January 2024 NRR E-mail Capture - Request for Additional Information Regarding Dukes August 20, 2023, License Amendment Request for Robinson, Unit 2 ML23262B4502023-09-19019 September 2023 NRR E-mail Capture - H. B. Robinson Steam Electric Plant, Unit 2 - Acceptance of License Amendment Request to Exclude the Dynamic Effects of Specific Postulated Pipe Ruptures Based on Leak-Before-Break Methodology ML23220A2342023-08-0808 August 2023 NRR E-mail Capture - Robinson, Unit 2 - Acceptance Review Results for Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule ML23172A0132023-06-20020 June 2023 Duke Fleet - Correction to June 2, 2023, Request for Additional Information Proposed License Amendment Request to Revise Restrictive Surveillance Requirement Frequencies ML23153A1892023-06-0202 June 2023 Duke Fleet - Request for Additional Information Proposed License Amendment Request to Revise Restrictive Surveillance Requirement Frequencies ML23151A3482023-05-30030 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23142A2732023-05-22022 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) ML23131A4192023-05-10010 May 2023 003 Radiation Safety Baseline Inspection Information Request ML23124A1212023-05-0404 May 2023 Acceptance of Requested Licensing Action Duke Fleet Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23073A2282023-03-13013 March 2023 Duke Fleet- Adoption of TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements - Acceptance Review ML23058A0562023-02-27027 February 2023 Acceptance of Amendment to Revise Surveillance Frequencies for RCS Pressure Isolation Valve Operational Leakage Testing and Reactor Trip System Instrumentation ML23048A1512023-02-16016 February 2023 Acceptance Review - Proposed Alternative for Steam Generator Welds (L-2023-LLR-0003) ML23011A0152023-01-11011 January 2023 NRR E-mail Capture - Request for Additional Information to Dukes Request for Robinson to Add Feedwater Isolation Function to TS 3.3.2 and Remove Obsolete Content from TSs 2.1.1.1 and 5.6.5.b ML22285A1552022-10-12012 October 2022 NRR E-mail Capture - H. B. Robinson, Unit 2 - Acceptance of License Amendment Request Regarding the Addition of Feedwater Isolation Function to TS 3.3.2 and Removal of Obsolete Content from TS 2.1.1.1 and TS 5.6.5.b ML22222A1082022-08-10010 August 2022 NRR E-mail Capture - Request for Additional Information Regarding Dukes Request to Remove 4.160 Kv Bus 2 from Surveillance Requirement 3.8.1.16 ML22146A3652022-05-25025 May 2022 Acceptance of Requested Licensing Action License Amendment Request for Application to Revise Surveillance Requirement 3.8.1.16 ML22115A1412022-04-25025 April 2022 NRR E-mail Capture - Duke Common EOF Relocation - Request for Addition Information ML22112A1482022-04-22022 April 2022 Correction_H. B. Robinson Steam Electric Plant, Unit 2 - Request for Additional Information Regarding Supplemental Response to Generic Letter 2004-02 ML22080A0042022-03-18018 March 2022 Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML22038A1572022-02-0707 February 2022 NRR E-mail Capture - Duke Energy Fleet - Acceptance of License Amendment Request Regarding Adoption of TSTF-541, Revision 2 ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML22012A3662022-01-12012 January 2022 Acceptance of Requested Licensing Action License Amendment Re2uest for Application to Revise Technical Specification to Adopt TSTF-577, Revised Frequencies for Steam Generating Tube Inspections ML22005A0872022-01-0505 January 2022 Acceptance of Requested Licensing Action Correction to Non-Conservative Technical Specifications Figure 3.4.3-2, Pressure/Temperature Limit Cooldown Curves ML21361A0122021-12-23023 December 2021 NRR E-mail Capture - Accepted for Review - Duke Energy Fleet License Amendment Request to Relocate Emergency Operations Facility ML21295A2992021-10-22022 October 2021 Document Request for Robinson Nuclear Plant - Radiation Protection Inspection - Inspection Report 2021004 ML21286A6612021-10-13013 October 2021 Acceptance for Review of Proposed Alternative ISI-05-017 for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML21119A2272021-04-29029 April 2021 NRR E-mail Capture - Robinson Relief Request Acceptance Review Results; IST-RR-9, EPID: L-2021-LLR-0024 ML21116A2592021-04-26026 April 2021 NRR E-mail Capture - Robinson Relief Request Acceptance Review Results; IST-RR-8, EPID: L-2021-LLR-0023 ML21116A2582021-04-26026 April 2021 NRR E-mail Capture - Robinson Relief Request Acceptance Review Results; IST-RR-3, EPID: L-2021-LLR-0020 ML21113A1312021-04-23023 April 2021 NRR E-mail Capture - Robinson Relief Request Acceptance Review Results; IST-RR-5, EPID: L-2021-LLR-0021 ML21110A1462021-04-20020 April 2021 NRR E-mail Capture - Robinson Relief Request Acceptance Review Results: IST-RR-7, EPID: L-2021-LLR-0022 ML21049A2632021-02-0404 February 2021 NRR E-mail Capture - Request for Additional Information - Duke Energy Fleet License Amendment Request to Revise Emergency Plan ML20353A1302020-12-18018 December 2020 2021 Hbr 50.59 Info Request - E-mail Request- Upcoming 50.59 Inspection (IP71111.17T)- Week of March 1-5, 2021 ML20323A4072020-11-18018 November 2020 NRR E-mail Capture - Request for Additional Information - Brunswick License Exemption Request from 10CFR73 Annual Force on Force Exercise Requirements (EPIC L-2020-LLE-0180) ML20297A3102020-10-13013 October 2020 NRR E-mail Capture - Acceptance Review - Duke Fleet - RA-20-0191 - Request to Use a Provision of a Later Edition of the ASME B&PV Code, Section XI - IWA-5120, IWA-5213, IWA-5241, IWA-5242, and IWA-5250 (L-2020-LLR-0126) ML20297A3082020-10-0707 October 2020 NRR E-mail Capture - Acceptance Review - Duke Fleet - RA-20-0263 - Request to Use a Provision of a Later Edition of the ASME B&PV Code, Section XI for Repair/Replacement (L-2020-LLR-0124) ML20297A3092020-10-0606 October 2020 NRR E-mail Capture - Acceptance Review - Duke Fleet - RA-20-0262 - Request to Use a Provision of a Later Edition of the ASME B&PV Code, Section XI - IWA-4540(b) (L-2020-LLR-0125) ML20063M1942020-02-21021 February 2020 NRR E-mail Capture - Accepted for Review - Robinson Unit 2 One-Time Pressure Relief Valve Test Frequency Extension EPID: L-2020-LLR-0019 ML20085F9312020-02-20020 February 2020 SPRA - Spr Audit Questions - 2nd Batch ML20049A0342020-02-16016 February 2020 NRR E-mail Capture - Accepted for Review - Robinson Unit 2 to Correct Administrative Renewed Facility Operating License Error in the 50.69 LAR EPID: L-2020-LLL-0000 ML20063L4562020-02-0404 February 2020 NRR E-mail Capture - RAI - Robinson Relief Req Rx Vessel Cold Leg Nozzle Dissimilar Meter Butt Weld Inspection Interval EPID L-2019-LLR-0072 ML20087N6632020-02-0303 February 2020 SPRA - Spr Audit Questions Redacted ML20027C2042020-01-27027 January 2020 Audit Documents Needed for the Robinson Seismic Probabilistic Risk Assessment Review - FLEX and HRA References ML20015A1892020-01-13013 January 2020 Audit Documents Needed for the Robinson SPRA Review - Fragility Analysis ML20009C0922020-01-0808 January 2020 Audit Documents Needed for the Robinson SPRA Review - Seismic Hazard Analysis ML19365A0482019-12-30030 December 2019 Request for Eportal Access for Audit Review of the Robinson SPRA Supporting Documents 2024-06-24
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24164A0052024-06-11011 June 2024 NRR E-mail Capture - Request for Additional Information Regarding Dukes February 15, 2024, Relief Request RA-23-0300 for Robinson ML24002A7382024-01-0202 January 2024 NRR E-mail Capture - Request for Additional Information Regarding Dukes August 20, 2023, License Amendment Request for Robinson, Unit 2 ML23235A0552023-08-23023 August 2023 – Notification of an Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000261/2023010) and Request for Information (RFI) ML23151A3482023-05-30030 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23142A2732023-05-22022 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) ML23047A4512023-02-21021 February 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000261/2023402 ML23011A0152023-01-11011 January 2023 NRR E-mail Capture - Request for Additional Information to Dukes Request for Robinson to Add Feedwater Isolation Function to TS 3.3.2 and Remove Obsolete Content from TSs 2.1.1.1 and 5.6.5.b ML22222A1082022-08-10010 August 2022 NRR E-mail Capture - Request for Additional Information Regarding Dukes Request to Remove 4.160 Kv Bus 2 from Surveillance Requirement 3.8.1.16 ML22115A1412022-04-25025 April 2022 NRR E-mail Capture - Duke Common EOF Relocation - Request for Addition Information ML22112A1482022-04-22022 April 2022 Correction_H. B. Robinson Steam Electric Plant, Unit 2 - Request for Additional Information Regarding Supplemental Response to Generic Letter 2004-02 ML22080A0042022-03-18018 March 2022 Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML21049A2632021-02-0404 February 2021 NRR E-mail Capture - Request for Additional Information - Duke Energy Fleet License Amendment Request to Revise Emergency Plan ML20353A1312020-12-18018 December 2020 2021 Hbr 50.59 Info Request ML20323A4072020-11-18018 November 2020 NRR E-mail Capture - Request for Additional Information - Brunswick License Exemption Request from 10CFR73 Annual Force on Force Exercise Requirements (EPIC L-2020-LLE-0180) ML20191A2122020-07-0909 July 2020 012 FPTI Notification Letter ML20063L4562020-02-0404 February 2020 NRR E-mail Capture - RAI - Robinson Relief Req Rx Vessel Cold Leg Nozzle Dissimilar Meter Butt Weld Inspection Interval EPID L-2019-LLR-0072 ML20022A1942020-01-22022 January 2020 Emergency Preparedness Program Inspection Request for Information ML19365A0462019-12-18018 December 2019 Audit Documents Needed for the Robinson SPRA Review ML19288A2942019-10-15015 October 2019 NRR E-mail Capture - RAIs for Robinson Revision to RPV Surveillance Program Withdrawal Schedule ML19288A2462019-09-26026 September 2019 Request for Additional Information Regarding Change to Surveillance Requirement 3.8.2.1 H.B. Robinson Unit No. 2 ML19283A0372019-09-26026 September 2019 Draft Requests for Additional Information for H.B. Robinson LAR to Revise TS 3.8.2, AC Sources - Shutdown, SR 3.8.2.1 ML19072A0292019-03-13013 March 2019 50.69 LAR RAIs ML19011A1372019-01-10010 January 2019 NRR E-mail Capture - Duke Energy Fleet RAIs - Relief Request 18-GO-001 - Proposed Alternative for Depth Sizing Qualification Examination of Welds (L-2018-LLR-0117) ML19007A3422018-12-21021 December 2018 NRR E-mail Capture - Duke Energy Fleet Draft RAIs - Relief Request 18-GO-001 - Proposed Alternative for Depth Sizing Qualification Examination of Welds (L-2018-LLR-0117) ML18291A6442018-10-17017 October 2018 NRR E-mail Capture - Robinson RAIs - Duke Energy 10 CFR 50.46 Annual Report ML18288A0192018-10-12012 October 2018 NRR E-mail Capture - Robinson RAIs - LAR to Allow Implementation of the Provisions 10 CFR 50.69 (EPID L 2018-LLA-0095) and LAR to Adopt TSTF-425 ML18274A2632018-09-28028 September 2018 NRR E-mail Capture - Robinson Draft RAIs - LAR to Allow Implementation of the Provisions 10 CFR 50.69 (EPID L 2018-LLA-0095) and LAR to Adopt TSTF-425 ML18211A6042018-07-30030 July 2018 NRR E-mail Capture - Robinson Supplemental RAI - LAR to Revise TS to Add a 2nd Qualified Offsite Power Circuit and Revise UFSAR to Operate LTCs in Automatic Mode (CAC No. MG0276; L-2017-LLA-0308) ML18206B0612018-07-25025 July 2018 NRR E-mail Capture - Draft Robinson Supplemental RAI - LAR to Revise TS to Add a 2nd Qualified Offsite Power Circuit and Revise UFSAR to Operate LTCs in Automatic Mode (CAC No. MG0276; L 2017-LLA-0308) ML18116A1052018-04-25025 April 2018 NRR E-mail Capture - Harris/Robinson RAIs - Change Technical Specifications to Support Performance of Core Reload Design and Safety Analyses (L-2017-LLA-0356) ML18108A7602018-04-18018 April 2018 NRR E-mail Capture - Harris/Robinson Draft RAIs - Change Technical Specifications to Support Performance of Core Reload Design and Safety Analyses (L-2017-LLA-0356) ML18108A7592018-04-18018 April 2018 NRR E-mail Capture - Robinson RAIs - LAR to Revise TS to Add a 2nd Qualified Offsite Power Circuit and Revise UFSAR to Operate LTCs in Automatic Mode (CAC No. MG0276; L 2017-LLA-0308) ML18102B0812018-04-12012 April 2018 NRR E-mail Capture - Draft Robinson RAIs - LAR to Revise TS to Add a 2nd Qualified Offsite Power Circuit and Revise UFSAR to Operate LTCs in Automatic Mode (CAC No. MG0276; L 2017-LLA-0308) ML18074A0052018-03-15015 March 2018 Heat Sink Emailed Heat Sink RFI Request 2018 ML17345A8772017-12-11011 December 2017 NRR E-mail Capture - Harris and Robinson Supplemental RAI - LAR to Adopt DPC-NE-3009-P, Revision 0, Thermal-Hydraulic Models for Transient Analysis, (L-2016-LLA-0012) ML17339A0722017-12-0404 December 2017 NRR E-mail Capture - Subject: Harris and Robinson Draft Supplemental RAIs - LAR to Adopt DPC-NE-3009-P, Revision 0, Thermal-Hydraulic Models for Transient Analysis, (L-2016-LLA-0012) ML17248A0182017-08-31031 August 2017 NRR E-mail Capture - Robinson RAIs - Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles (MF9544) ML17235A2612017-08-22022 August 2017 NRR E-mail Capture - Robinson RAIs - Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles (MF9544) ML17192A4842017-07-11011 July 2017 NRR E-mail Capture - Duke Energy Fleet RAIs Alternative for Reactor Pressure Vessel Flange Threads Examination (MF9513 to MF9521) ML17114A0462017-04-21021 April 2017 Notification of Inspection and Request for Information ML16288A0782016-10-26026 October 2016 Shearon Harris Nuclear Power Plant, Unit 1, and H.B. Robinson Steam Electric Plant, Unit No. 2 - Redacted, Request for Additional Information Re: Request to Adopt DPC-NF-2010 and DPC-NF-2011 Nuclear Design Methodology (CAC Nos. MF7693 and MF7694) ML16130A5982016-05-0505 May 2016 Notification of Inspection and Request for Information ML16048A3492016-03-0202 March 2016 RAI Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants ML16019A0532016-02-0808 February 2016 Request for Additional Information Related to the Pressurized Water Reactors Internals Program Plan for Aging Management of Reactor Internals ML16026A0512016-01-25025 January 2016 Robinson EP RFI 2016-001 ML15344A0302015-12-17017 December 2015 Request for Additional Information Application to Revise Technical Specifications for Methodology Report DPC-NE-2005-P, Revision 5, Thermal Hydraulic Statistical Core Design Methodology (MF5872/MF5873) ML15215A6512015-08-10010 August 2015 Duke Energy Progress, Inc., for H. B. Robinson, Unit 2 and Shearon Harris, Unit 1, Request for Additional Information Regarding Application to Revise Technical Specifications for Methodology Report DPC-NE-2005-P, Revision 5 (TAC Nos. MF5872 ML15009A3352015-01-0808 January 2015 Requalification Program Inspection - H.B. Robinson Nuclear Plant RNP-RA/14-0118, Response to Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1, Seismic Re-Evaluations Related to Southeastern Catalog Changes2014-11-12012 November 2014 Response to Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1, Seismic Re-Evaluations Related to Southeastern Catalog Changes ML14268A5162014-10-23023 October 2014 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1, Seismic Re-evaluation Related to Southeastern Catalog Changes 2024-06-11
[Table view] |
Text
ML18074A005 H.B. Robinson Steam Electrical Plant Baseline Heat Sink Inspection Initial Information Request H.B. ROBINSON STEAM ELECTRIC PLANT - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION During the week of June 18 - 22, 2018, the Nuclear Regulatory Commission (NRC) will perform the baseline heat sink (HS) inspection. Experience has shown that this inspection is resource intensive both for the NRC inspectors and your staff. In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. These documents have been divided into two groups.
The first group (section A of the enclosure) identifies information to be provided prior to the inspection to ensure that the inspectors are adequately prepared. The second group (Section B of the enclosure) identifies the information the inspectors will need upon arrival at the site. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.
We discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Christine Caudell of your organization. Our inspection dates are subject to change based on your updated schedule of activities. If there are any questions about this inspection or the material requested, please contact the lead inspector, Al Butcavage, at (404) 997-4640 (Alexander.Butcavage@nrc.gov).
In accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Agency Rules of Practice and Procedure," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agency-wide Document Access and Management System (ADAMS).
PAPERWORK REDUCTION ACT STATEMENT This document does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget under control numbers 3150-0008, 3150-0011, 3150-0014, 3150-0044, and 3150-0135.
PUBLIC PROTECTION NOTIFICATION The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement, unless the requesting document displays a currently valid Office of Management and Budget control number.
Document Request List Licensee: H.B. Robinson Steam Electrical Plant Docket No.: 50-261 Inspection Dates: June 18 - 22, 2018 Entrance Meeting: June 18, 2018 Inspection Procedures: IP 71111.07, Heat Sink Performance dated 12/08/16 Inspector: Al Butcavage, Reactor Inspector A. Information Requested for the In-Office Preparation Week The following information should be sent to the Region II office in hard copy or electronic format (preferred), in care of Al Butcavage by 29 May 2018, to facilitate the selection of specific items that will be reviewed during the onsite inspection week. The inspector will select specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection week (Section B of this enclosure). We ask that the specific items selected from the lists be available and ready for review on the first day of inspection. *Please provide requested documentation electronically if possible. If requested documents are large and only hard copy formats are available, please inform the inspector, and provide subject documentation during the first day of the onsite inspection. If you have any questions regarding this information request, please call the inspector as soon as possible.
Heat Exchangers and Service Water Equipment
- 1. List of heat exchangers (HXs) or equipment cooled by service water (SW) directly or indirectly
- 2. Include the risk ranking from the site specific risk assessment for each listed HX
- 3. Detail whether any cleaning or inspection activities are planned during the proposed onsite inspection period for any of the listed HXs
- 4. For HXs directly cooled by SW, provide the testing, inspection, maintenance, and monitoring of biotic fouling and macro-fouling program documents
- 5. Detail the HX performance inspection methods for HXs that are inspected/cleaned
- 6. Response to Generic Letter 89-13 including any regulatory commitments made
- 7. Design Basis documents associated with the SW system
- 8. Design Basis documents associated with the Ultimate Heat Sink (UHS)
- 9. SW system flow diagrams Enclosure
2
- 10. Recent Health Reports associated with the SW System and systems that are cooled by SW
- 11. List of SW system related corrective action documents (with a brief description) which have received a Root Cause Analysis or an elevated severity level in the last three years
- 12. Recent Operating Experience Events (last three years)
- 13. List of applicable Codes and Industry Guidelines
- 14. List of findings and violations in the heat sink/heat exchanger performance area for the last three years
- 15. List of redundant or infrequently used HXs
- 16. Chemistry Program for safety-related HXs
- 17. Detail whether the UHS is above ground encapsulated by embankments, weirs or excavated side slopes; underwater weir or excavation; or forced draft cooling tower or spray pond
- 18. Provide a list of buried or inaccessible piping and the piping test program, inspection or monitoring program
- 19. List of safety-related and non-safety related valve interfaces
- 20. Most recent self-assessment reports performed on the UHS and SW systems B. Information to be provided on-site to the inspector at the entrance meeting June 18, 2018:
Heat Exchangers and Service Water Equipment The inspector will select two to four heat exchangers and/or heat sink samples as required by the inspection procedure during in-office preparation. The following items will be requested when the selections are made:
- 1. Updated list of System Engineers
- 2. List of any through-wall leaks including completed or planned corrective actions and structural evaluations
- 3. Provide a copy of the corrective actions and supporting documentation
- 4. For the HXs that have Visual and/or Eddy Current Testing performed, provide a copy of the written procedures used, examination records, examiner qualification records, and associated corrective action documents
- 5. Heat transfer calculations
- 6. Evaluations for the potential of water hammer
3
- 7. Documentation for controls and operational limits for excessive flow induced vibrations
- 8. Periodic flow test results at/or near maximum design flow
- 9. For an UHS that is encapsulated by embankments, weirs, or excavated side slopes, provide third party dam inspection results, and documentation showing that there is sufficient reservoir capacity
- 10. For an UHS that is an underwater weir or excavation, provide documentation demonstrating:
Periodic monitoring and trending of sediment build-up Sufficient reservoir capacity Considerations for adjacent non-seismic and/or non-safety related structures of possible degradation or blocking of safety-related flow paths due to severe weather or seismic events Performance monitoring of heat transfer capabilities Performance monitoring of UHS structural integrity SW flow balance test results Inspector Contact Information:
Al Butcavage Reactor Inspector 404-997-4640 Alexander.Butcavage@nrc.gov Mailing Address US NRC Region 2 Attn: Al Butcavage Marquis One Tower 245 Peachtree Center Avenue, NE Suite 1200 Atlanta, GA 30303
Egelstad, Donna From: Butcavage, Alexander Sent: Friday, March 09, 2018 1:14 PM To: Caudell, Christine Anna Cc: Bonser, Brian; Egelstad, Donna
Subject:
Heat Sink Inspection Request for Information Attachments: Robinson Heat Sink RFI 2018_ (002) AJB .pdf Ms. Caudell, Please find attached the NRC request for information for use during the upcoming Tri-Annual Heat Sink Inspection in accordance with IP 71111.07, Heat Sink Performance scheduled for 18-22 June, 2018.
Please confirm receipt of this request by return E-mail.
Thank You in advance for your help in compiling the requested information.
Al Butcavage USNRC R-II Alexander.Butcavage@nrc.gov x404-997-4640 1