Inspection/Activity Plan - Edwin I. Hatch Nuclear Plant, 03/01/2003 - 03/31/2004
ML030660005
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 03/04/2003
From:
NRC/RGN-II/DRP/RPB2
To:
Shared Package
ML030660003 List:
References
IR-03-001
Download: ML030660005 (1)


Text

Page 1 of 1 Hatch 03/04/2003 07:49:49 Inspection / Activity Plan Report 22 03/01/2003 - 03/31/2004 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type PS-RP - RADIATION PROTECTION 3 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 03/03/2003 03/07/2003 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 03/03/2003 03/07/2003 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 03/03/2003 03/07/2003 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 03/03/2003 03/07/2003 Baseline Inspections EB2-ISI - INSERVICE INSPECTION-U2 2 2 IP 7111108G Inservice Inspection Activities - BWR 03/04/2003 03/08/2003 Baseline Inspections PS-RP - RADIATION PROTECTION 3 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 03/17/2003 03/21/2003 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 03/17/2003 03/21/2003 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 03/17/2003 03/21/2003 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 03/17/2003 03/21/2003 Baseline Inspections PS-SEC - SECURITY - TI/ICM 3 1, 2 IP 2515/148 Inspection of Nuclear Reactor Safeguards - Interim Compensatory Measures 05/12/2003 05/16/2003 Safety Issues EB1-TFP - TFP - PRE-INSPECTION VISIT 4 1, 2 IP 7111105T Fire Protection 06/16/2003 06/20/2003 Baseline Inspections EB1-FP - TRIENNIAL FIRE PROTECTION INSP 3 1, 2 IP 7111105T Fire Protection 07/07/2003 07/11/2003 Baseline Inspections 1, 2 IP 7111105T Fire Protection 07/21/2003 07/25/2003 Baseline Inspections BR2-FP - FLOOD PROTECTION 1 1, 2 IP 7111106 Flood Protection Measures 08/04/2003 08/08/2003 Baseline Inspections BR2-PIR - PROBLEM IDENTIFICATION AND RESOLUTION 3 1, 2 IP 71152B Identification and Resolution of Problems 08/11/2003 08/15/2003 Baseline Inspections 1, 2 IP 71152B Identification and Resolution of Problems 08/25/2003 08/29/2003 Baseline Inspections OL EP - EMERGENCY EXERCISE 2 1, 2 IP 7111401 Exercise Evaluation 08/18/2003 08/22/2003 Baseline Inspections 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 08/18/2003 08/22/2003 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 08/18/2003 08/22/2003 Baseline Inspections EB2-HS - HEAT SINK 1 1, 2 IP 7111107B Heat Sink Performance 10/13/2003 10/17/2003 Baseline Inspections PS-RP - RADIATION PROTECTION @ ENV LAB 1 1, 2 IP 7112203 Radiological Environmental Monitoring Program 11/19/2003 11/21/2003 Baseline Inspections EB2-ISI - INSERVICE INSPECTION-U1 1 1 IP 7111108G Inservice Inspection Activities - BWR 03/08/2004 03/12/2004 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.