NL-03-1654, Cycle 21 Core Operating Limits Report (Colr), Revision 1

From kanterella
Revision as of 16:16, 21 March 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Cycle 21 Core Operating Limits Report (Colr), Revision 1
ML032240035
Person / Time
Site: Hatch Southern Nuclear icon.png
Issue date: 08/07/2003
From: Sumner H
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-03-1654
Download: ML032240035 (35)


Text

H.L Sumner, Jr. Southern Nuclear Vice President Operating Company, Inc.

Hatch Project Post Office Box 1295 Birmingham, Alabama 35201 Tel 205.992.7279 SOUTHERNAM August 7, 2003 COMPANY Energy to Serve Your World '

DocketNo.: 50-321 NL-03-1654 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Edwin I. Hatch Nuclear Plant Unit 1 Cycle 2lCore Operating Limits Report (COLR). Revision I Ladies and Gentlemen:

In accordance with Technical Specification 5.6.5, Southern Nuclear Operating Company hereby submits the Edwin 1.Hatch Nuclear Plant Unit I Cycle 21 Core Operating Limits Report, Revision 1.

This letter contains no NRC commitments. If you have any questions, please advise.

Sincerely, H. L. Sumner, Jr.

HLS/IL/daj

Enclosures:

Unit 1 Cycle 21 Core Operating Limits Report, Revision 1 cc: Southern Nuclear Operating Company Mr. J. D. Woodard, Executive Vice President Mr. G. R. Frederick, General Manager - Plant Hatch Document Services RTYPE: CHA02.004 U. S. Nuclear Regulatory Commission Mr. L. A. Reyes, Regional Administrator Mr. S. D. Bloom, NRR Project Manager - Hatch Mr. D. S. Simpkins, Senior Resident Inspector - Hatch (fDt

SOUTHERN NUCLEAR OPERATING COMPANY EDWIN I. HATCH NUCLEAR PLANT Unit I Cycle 21 CORE OPERATING LIMITS REPORT Revision I Southern Nuclear Operating Company Post Office Box 1295 Birmingham, Alabama 35201

Edwin I. Hatch Nuclear Plant Unit I Cycle 21 Core Operating Limits Report TABLE OF CONTENTS Section Title Pane 1.0 Introduction 1 2.0 APLHGR Limits 2 3.0 MCPR Operating Limits 14 4.0 PBDA Amplitude Setpoint 28 5.0 References 29 i Revision 1

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report TABLES Table No. Title Page 2-1 APLHGR Operating Flexibility Options 3 3-1A MCPR Operating Flexibility Options for 16 Cycle Exposures BOC to EOC-2100 3-1 B MCPR Operating Flexibility Options for 17 Cycle Exposures EOC-21 00 to EEOC ii Revision 1

Plant Hatch Unit I Cycle 21 Core Operating Limits Report FIGURES Figure No. Title Paae 2-1 Flow-Dependent APLHGR Multiplier 4 (MAPFACF) versus Core Flow 2-2A Power-Dependent APLHGR Multiplier 5 (MAPFACp) versus Core Power (Bypass Valves Operable and Pressure Regulator Operable) 2-2B Power-Dependent APLHGR Multiplier 6 (MAPFACp) versus Core Power (Bypass Valves Inoperable and Pressure Regulator Operable) 2-2C Power-Dependent APLHGR Multiplier 7 (MAPFACp) versus Core Power (Pressure Regulator Inoperable) 2-3 APLHGR Limit versus Average Planar Exposure 8 (GE14-PIODNAB399-16GZ-IOOT-150-T-2517) 2-4 APLHGR Limit versus Average Planar Exposure 9 (GE13-P9HTB378-6G5.O/6G4.0/1G2.0-IOOT-146-7) 2-5 APLHGR Limit versus Average Planar Exposure 10 (GE13-P9HTB378-6G5.016G4.0-IOOT-146-T) 2-6 APLHGR Limit versus Average Planar Exposure 11 (GE14-PIODNAB398-15GZ-IOOT-150-T-2518) 2-7 APLHGR Limit versus Average Planar Exposure 12 (GE13-P9DTB378-6G5.0/6G4.0-IOOT-146-T-2411) 2-8 APLHGR Limit versus Average Planar Exposure 13 (GE13-P9DTB378-6G5.0/6G4.0/1G2.0-IOOT-146-T) iii Revision I

Plant Hatch Unit I Cycle 21 Core Operating Limits Report FIGURES (Continued)

Figure No. Title Page 3-1A Power-Dependent MCPR Limit (MCPRp) versus 18 Core Power from 25% to 28% of Rated Core Power (Bypass Valves Operable) 3-1B Power-Dependent MCPR Limit (MCPRp) versus 19 Core Power from 25% to 28% of Rated Core Power (Bypass Valves Inoperable) 3-2 Flow-Dependent MCPR Limit (MCPRF) versus 20 Core Flow 3-3A Power-Dependent MCPR Multiplier (Kp) versus 21 Core Power (Pressure Regulator Operable) 3-31 Power-Dependent MCPR Multiplier (Kp) versus 22 Core Power (Pressure Regulator Inoperable) 34A MCPR Limits versus Average Scram Time 23 (BOC to EOC-2100 with EOC-RPT System Operable and Bypass Valves Operable) 3-41 MCPR Limits versus Average Scram Time 24 (BOC to EOC-2100 with EOC-RPT System Inoperable and Bypass Valves Operable) 3-4C MCPR Limits versus Average Scram Time 25 (BOC to EEOC with EOC-RPT System Operable and Bypass Valves Inoperable) 3-4D MCPR Limits versus Average Scram Time 26 (EOC-2100 to EEOC with EOC-RPT System Operable and Bypass Valves Operable) 3-4E MCPR Limits versus Average Scram Time 27 (EOC-2100 to EEOC with EOC-RPT System Inoperable and Bypass Valves Operable) iv Revision 1

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report

1.0 INTRODUCTION

The Core Operating Limits Report (COLR) for Plant Hatch Unit I Cycle 21 is prepared In accordance with the requirements of Technical Specification 5.6.5.

The core operating limits presented herein were developed using NRC-approved methods (Reference 1). Results from the reload analyses for the fuel in Unit I Cycle 21 are documented in References 2, 3, and 4. Results from the most recent cycle independent analyses are documented in Reference 5. Revised APLHGR limits for GE13 fuel are documented in References 6 and 7.

The following core operating limits are included in this report:

a. Average Planar Linear Heat Generation Rate (APLHGR) - Technical Specification 3.2.1.
b. Minimum Critical Power Ratio (MCPR) - Technical Specification 3.2.2.
c. Maximum allowable scram setpoints for the Period Based Detection Algorithm (PBDA) in the Oscillation Power Range Monitor (OPRM) system.

From a fuel thermal limits perspective, the following limitations are placed on Unit 1 operation with equipment out of service.

Equipment I Condition Limitation EOC-RPT Out of Service AND Not analyzed Turbine Bypass Valves Inoperable Simultaneously Single-Loop Operation (SLO)

  • s 2000 MWt a s 56% Core Flow Also included in this report are the maximum allowable scram setpoints for the Period Based Detection Algorithm (PBDA) in the Oscillation Power Range Monitor (OPRM).

1 Revision 1

Plant Hatch Unit I Cycle 21 Core Operating Limits Report 2.0 APLHGR LIMITS (Technical Specification 3.2.1)

The APLHGR limit for each fuel assembly is the applicable rated-power, rated-flow APLHGR limit taken from Figures 2-3 through 2-8, multiplied by the smaller of either

a. The flow-dependent multiplier, MAPFACF, from Figure 2-1, or
b. The power-dependent multiplier, MAPFACp, as determined by Table 2-1.

Since every assembly in the core contains more than one enriched lattice, GESTAR-I1 (Reference 1)requires that the appropriate APLHGR limit from Figures 2-3 through Figures 2-8 be applied to every axial location in the fuel assembly, when APLHGR values are hand-calculated. The limits shown in those figures are the values for the most limiting enriched lattice in each fuel bundle as a function of average planar exposure.

When APLHGR values are determined by the process computer, the lattice type-dependent APLHGR limits are used. Under these conditions, some axial locations may have APLHGR values exceeding the values shown in the figures.

2 Revision 1

Plant Hatch Unit I Cycle 21 Core Operating Limits Report Table 2-1 APLHGR Operating Flexibility Options Cycle Average Bypass P,-ressure- MAPFACp Exposure Valves :Regulator Curve BOC to Operable Operable Figure 2-2A EEOC BOC to Inoperable Operable Figure 2-2B EEOC BOC Operable to or Inoperable Figure 2-2C EEOC Inoperable 3 Revision 1

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report W

Core Flow (% of Rated)

MAPFACF = Minimum [1.0, (A+B*F), MAPMULT]

Maximum Core Flow (% of Rated) A 00B67 107.0 0.4574 __ 0.006758 MAPMULT = 1.0 for F > 61.0 0.86 for Fs61.0 F = Percent of Rated Core Flow FIGURE 2-1 Flow-Dependent APLHGR Multiplier (MAPFACF) versus Core Flow 4 Revision 1

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report 0.9

-0

-I---

. S0%CORE FLOW(TL a.0.7 -l 10.8' ffi 0.5 . {

  • 6 0% CORE Fl 0.4  ! I :i:i 25 28 30 35 40 Core Power (%of Rated)

MAPFACp = A - B (Po-P)

Operating Conditions Values of Variables P F Fuel Type SLOITLO A B Po 25!5 P < 28 Fs 60 GE13114 SLOJTLO 0.603 0 28 25 s P <28 F > 60 GE13/14 SLO/TLO 0.560 0 28 28! P < 61.72 All GE13f14 SLOITLO 1.00 0.005224 100 61.72!5 P < 71.28 All GE13 SLO)rLO 1.00 0.005224 100 61.72!5 P <71.28 All GE14 TLO 1.00 0.005224 100 71.28! P All GE13114 TLO 1.00 0.005224 100 71.28!s P All GE13 SLO 0.85 0.000 100 61.72!s P All GE14 SLO 0.80 0.000 100 P = Percent of Rated Core Power F = Percent of Rated Core Flow FIGURE 2-2A Power-Dependent APLHGR Multiplier (MAPFACp) versus Core Power (Bypass Valves Operable andPressureRegulator Operable) 5 Revision 1

Plant Hatch Unit I Cycle 21 Core Operating Limits Report t1

~0. - - : 0 . __  : lTW LOOP OPERATION (TLO)

I-

0.

E O S6O% CORE FLOW (TLO and SLO)

U.

S. 0.7 _/l I C -G GEUS..

4S.

c.

0.8 f1314 _L st -- ; jil ;L W-g S I j l t;60%CORE FLOW (TLO and SLO)

OA 25

- i I, 28 30 35 40 I I_-_---- -__1_II_

45 50 55 60 65 70 Core Power (%of Rated) 75 so 85 90 95 WO MAPFACp = A - B (Po-P)

Operating Conditions l Values of Variables P F FuelType SLOITLO A B PO 25sP < 28 F!560 GE13/14 SLOITLO 0.588 0.01167 28 25:s P < 28 F>60 GE13114 SLOrTLO 0.450 0.00967 28 28 s P <61.72 All GE13/14 SLOITLO 1.00 0.005224 100 61.72 5 P <71.28 All GE13 SLOITLO 1.00 0.005224 100 61.72 S P < 71.28 All GE14 TLO 1.00 0.005224 100 71.28!9 P All GE1 3114 TLO 1.00 0.005224 100 71.28 5 P All GE13 SLO 0.85 0.000 100 61.72 s P All GE14 SLO 0.80 0.000 100 P = Percent of Rated Core Power F = Percent of Rated Core Flow FIGURE 2-2B Power-Dependent APLHGR Multiplier (MAPFACp) versus Core Power (Bypass Valves Inoperableand PressureRegulatorOperable) 6 Revision 1

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report

-~to - _ _

0.2 0.7 -

0.6 a.OA 25 30 35 40 45 50 55 6o 65 70 75 so 85 90 95 oo Core Power (%of Rated)

MAPFACp = A - B (Po-P)

O ratin Conditions Values of Variables Fe F Fuel Type SLOITLO A B Po 25 s P < 40 All GE13J14 SLO/TLO 0.49 0.00580 40 40 s P < 100 All GE13114 SLOrLO I 1.00 0.0085 100 P = Percent of Rated Core Power F = Percent of Rated Core Flow FIGURE 2-2C Power-Dependent APLHGR Multiplier (MAPFACp) versus Core Power (Pressure RegulatorInoperable) 7 Revision 1

Plant Hatch Unit I Cycle 21 Core Operating Limits Report Average Planar APLHGR 17-Exposure Limit 0.00 9.59 0.20 9.66 1.00 79.,78 2.00 9.94 3.00 10.06 4.00 10.19 5.00 10.28 6.00 10.38 7.00 10.48 E 8.00 10.58 9.00 10.68 10.00 10.78 a.

11.00 10.89 12.00 10.91 13.00 10.93 14.00 10.95 15.00 10.97 17.00 10.94 20.00 10.80 25.00 10.44 30.00 10.05 DI - - 1' . I I I , I I . I I I 0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0 55.0 60.0 65.0 35.00 9.59 40.00 9.07 Average Planar Exposure (GWdIST) 45.00 8.54 50.00 7.99 55.00 6.16 NOTE: THIS IS THE APLHGR LIMIT FOR THE 57.45 4.92 MOST LIMITING LATTICE AS A FUNCTION OF AVERAGE PLANAR EXPOSURE.

FIGURE 2-3 APLHGR Limit versus Average Planar Exposure (Bundle Type: GE14-PIODNAB399-16GZ-IOOT-150-T-2517) 8 Revision 1

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report Average Planar APLHGR 14.0 Exposure Umit 0.00 10.51 13.0i -  :  : - _  :  :..

0.20 10.57 1.00 10.73 1Z.0 ___ UNACCEPTABLE 2.00 10.97 OPERATION 3.00 11.24 4.00 11.48 5.00 11.73 g 6.00 11.92 7.00 12.06 E 8.00 12.21 E 9.00 12.36 ACCEPTABLE -

10.00 12.47 1.0 OPERATION __

12.50 12.67 a.

15.00 12.57 0-

.. - - - I__ > < ____ _____-_

7.0--

17.50 12.36 20.00 12.14 6.0- -

24.40 11.80 4.0 _ _ __ _ = . __ \

25.00 11.76 4.0 30.00 11.38 35.00 10.70 40.00 10.04 0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0 55.0 60.0 45.00 9.38 50.00 8.72 Average Planar Exposure (GWdIST) 55.00 7.12 56.70 6.50 57.53 6.19 NOTE: THIS IS THE APLHGR LIMIT FOR THE MOST LIMITING LATTICE AS A FUNCTION OF AVERAGE PLANAR EXPOSURE.

FIGURE 2-4 APLHGR LlmIt versus Average Planar Exposure (Bundle Type: GE13-P9HTB378-6G5.0J6G4.O/1G2.0-IOOT-146-T) 9 Revision 1

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report Average Planar APLHGR 14.0 Expsure Limit 0.00 10.64 13.0 -

0.20 10.70 UNACCEPTABLE 1.00 10.85 12.0 OPERATION 2.00 11.06 3.00 11.30 11.0 4.00 11.51

- 4 5.00 11.75 6.00 11.92 10.0 7.00 12.06 E

E 9.0 8.00 12.21 9.00 12.35 . 0 ACCEPTABLE 10.00 12.49 6 .0 - OPERATION - -

12.50 12.69 I-C ~

15.00 12.59 7.0 17.50 12.38 20.00 12.16 6.0 24.40 11.82 25.00 11.78 5.0 30.00 11.40 32.66 11.04 35.00 10.72 4.0 0.iD I 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0 55.0 60.0 40.00 10.06 1 45.00 9.40 Averago Planar Exposure (GWd/ST) 50.00 8.74 55.00 7.14 56.70 6.52 NOTE: THIS IS THE APLHGR LIMIT FOR THE 57.54 6.21 MOST LIMITING LATTICE AS A FUNCTION OF AVERAGE PLANAR EXPOSURE.

FIGURE 2-5 APLHGR Limit versus Average Planar Exposure (Bundle Type: GE13-P9HTB378-6G5.016G4.0-IOOT-146-T) 10 Revision 1

Plant Hatch Unit I Cycle 21 Core Operating Limits Report Average Planar APLHGFR Exposure Limit 0.00 9.72 0.20 9.79 1.00 9.89 2.00 10.01 3.00 10.13 4.00 10.22 5.00 10.31 6.00 10.41 0.0 - _ _ _ _

7.00 10.50 8.00 10.60 9.00 10.00 11.00 10.70 10.80 I 10.92 r

0 7.0 l l I:

ll ACCEPTABLE OPERATION L 12.00 10.94 13.00 10.96 - 6.0- - -

14.00 10.98 15.00 10.99 17.00 10.96 20.00 10.81 25.00 10.44 4 .0 30.00 10.05 - - - - - - - - -

o0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0 55.0 60.0 35.00 9.59 40.00 9.07 Average Planar Exposure (GWd/Sr) 45.00 8.54 50.00 7.99 55.00 6.17 NOTE: THIS IS THE APLHGR LIMIT FOR THE 57.47 4.92 MOST LIMITING LATTICE AS A FUNCTION OF AVERAGE PLANAR EXPOSURE.

FIGURE 2-6 APLHGR Limit versus Average Planar Exposure (Bundle Type: GE14-PIODNAB398-15GZ-IOOT-150-T-2518) 11 Revision 1

I .*

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report Average Planar APLHGR 14.0WI,_-

Exposure Limit 0.00 10.83 13.0 _ - l l l ,

0.20 10.89 UNACCEPTABLE 1.00 11.04 12.0 OPERATION 2.00 11.25 3.00 11.48 4.00 11.73 5.00 11.96 9 6.00 12.14 E 7.00 12.28 2!

E 8.00 12.42 .j 9.00 12.57 w 0

10.00 12.71 3i 8.0 OPERATION -

IL 12.50 12.69 C 15.00 12.50 7.0_

17.50 12.31 20.00 12.13 6.0 - - - - - __T_ _ _1__1 24.40 11.81 25.00 11.77 6.0 30.00 111.34 32.66 35.00 10.99 10.69 4.0_ IL . . LL. .LLI .

40.00 45.00 10.04 9.40 I D0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 Average Planar Exposure (GWdlST) 45.0 50.0 65.0 60.0 50.00 8.74 55.00 7.14 56.70 6.51 NOTE: THIS IS THE APLHGR LIMIT FOR THE 57.54 6.20 MOST LIMITING LATTICE AS A FUNCTION OF AVERAGE PLANAR EXPOSURE.

FIGURE 2-7 APLHGR Umit versus Average Planar Exposure (Bundle Type: GE13-P9DTB378-6G5.0/6G4.0-IOOT-146-T-2411) 12 Revision I

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report Average Planar APLHGR 14.0 _.. _ .__

Exposure Limit 0.00 10.64 13.0 i::t:.

0.20 10.71 UNACCEPTABLE 1.00 10.88 12.0 ___ SOPERATION f

2.00 11.12 3.00 11.39 l1.0  ; _ .  : . _

4.00 11.67 5.00 11.93 6.00 12.14 7.00 12.28 E

8.00 12.42 9.00 12.58 C, ACCEPTABLE 10.00 12.71 8.0 OPERATION 12.50 12.69 15.00 12.50 7.0-17.50 12.31 20.00 12.13 A n i . . , . -..  : _ _ _'__

24.40 11.81 25.00 30.00 32.66 35.00 11.77 11.33 10.99 10.68 4.0 I. .I'E

___~~~~~~~

_ I:

_] _: I_

, YI

_ ~I_~

- -i I 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0 55.0 60.0 40.00 10.04 45.00 9.40 Average Planar Exposure (GWdlST) 50.00 8.74 55.00 7.13 56.70 6.50 NOTE: THIS IS THE APLHGR LIMIT FOR THE 57.53 6.20 MOST LIMITING LATTICE AS A FUNCTION OF AVERAGE PLANAR EXPOSURE.

FIGURE 2-8 ALPHGR Limit versus Average Planar Exposure (Bundle Type: GE13-P9DTB378-6G5.016G4.O/1G2.0-IOOT-146-7) 13 Revision 1

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report 3.0 MCPR OPERATING LIMITS (Technical Specification 3.2.2)

The MCPR operating limit (OLMCPR) for each fuel type is a function of core power, core flow, average scram time, number of operating recirculation loops, operability of the EOC-RPT system, operability of the turbine bypass valve system, and whether both pressure regulators are operable.

With both recirculation pumps in operation (TLO), the OLMCPR for each fuel type is determined as follows:

a. For 25% < power < 28%, the power-dependent MCPR limit, MCPRp, as determined by Table 3-1A or 3-1 B.
b. For power a 28%, the OLMCPR is the greater of either:
1) The flow-dependent MCPR limit, MCPRF, from Figure 3-2, or
2) The product of the power-dependent multiplier, Kp, and the rated-power, rated-flow MCPR limit as determined by Table 3-1A or 3-1B.

With only one recirculation pump in operation (SLO), the OLMCPR for each fuel type is the TLO OLMCPR plus 0.02.

These limits apply to all modes of operation with intermittent feedwater temperature reduction, as well as operation with normal feedwater temperatures.

In figures 3-4A through 34E, Option A scram time MCPR limits correspond to r =

1.0, where Tis determined from scram time measurements performed In accordance with Technical Specifications Surveillance Requirements 3.1.4.1 and 3.1.4.2. Option B values correspond to r = 0.0. For scram times between Option A and Option B, the MCPR limit for each fuel corresponds tox. If? has not been determined, Option A limits are to be used. Refer to Table 3-IA or 3-lB to determine the applicable set of fuel-type dependent curves.

14 Revision 1

Plant Hatch Unit I Cycle 21 Core Operating Limits Report The average scram time of the control rods, a, is defined as:

Tave - TB X =0, or , whichever is greater.

TA - TB where: TA = 1.08 sec (Technical Specification 3.1.4, Table 3.1.4-1, scram time limit to notch 36).

TB = P+ 1.65

  • a N EN, where: i = 0.822 sec (mean scram time used in the transient analysis).

a = 0.018 sec (standard deviation of p).

n X Nit, Tave x ZNi l=1 where: n = number of surveillance tests performed to date in the cycle.

Ni = number of active control rods measured in the ith surveillance test.

Ti = average scram time to notch 36 of all rods in the ith surveillance test.

N. = total number of active rods measured in Technical Specifications Surveillance Requirement 3.1.4.1.

15 Revision 1

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report TABLE 3-1A MCPR Operating Flexibility Options for Cycle Exposures BOC to EOC-2100 Turbine Pressure - Rated-Power, EOC-RPT Regulator oMCPRp MBypassValve Rated-Flow

--System ; :;X -:System - System

-) :- r-q; -Curve Kp Curve MCPR Limits Operable Operable Operable Figure 3-1A Figure 3-3A Figure 3-4A Operable Operable Inoperable Figure 3-1A Figure 3-38 Figure 34A Inoperable Operable Operable Figure 3-1A Figure 3-3A Figure 3-4B Inoperable Operable Inoperable Figure 3-1A 3-31 Figure 3-413 Operable Inoperable Operable Figure 3-1B Figure 3-3A Figure 3-4C Operable rabl Inoperable Figure 3-lB Figure 3-3B Figure 3-4C BOC = Beginning of Cycle EOC = End of Cycle EEOC = Extended End of Cycle 16 Revision 1

Plant Hatch Unit 1Cycle 21 Core Operating Limits Report TABLE 3-1B MCPR Operating Flexibility Options for Cycle Exposures EOC-21 00 to EEOC Turbine Pressure Rated-Power, EOC-RPT Bypass Valve Regulator MCPRP Rated-Flow System y Syst Curve Kp Curve MCPR Limits Operable Operable Operable Figure 3-1A Figure 3-3A Figure 3-4D Operable Operable Inoperable Figure 3-1A Figure 3-3B Figure 3-4D Inoperable Operable Operable Figure 3-1A Figure 3-3A Figure 3-4E Inoperable Operable Inoperable Figure 3-lA Figure 3-3B Figure 3-4E Operable Inoperable Operable Figure 3-1B Figure 3-3A Figure 34C Operable Inoperable Inoperable Figure 3-1B Figure 3-3B Figure 34C BOC = Beginning of Cycle EOC = End of Cycle EEOC = Extended End of Cycle 17 Revision I

Plant Hatch Unit I Cycle 21 Core Operating Limits Report 22 D.

E 2A a.

ICi 22 25 26 27 28 Core Power (%of Rated)

MCPRp = A + B (28-P)

F A I B I

  • 60% l 2.15 1 0 l

> 60% 2.5 0.03 P = Percent of Rated Core Thermal Power F = Percent of Rated Core Flow FIGURE 3-1A Power-Dependent MCPR Limit (MCPRp) versus Core Power From 25% to 28% of Rated Core Power (Bypass Valves Operable)

Is Revision I

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report 3.8 It 3.

E 32 32 2.

3.0 2.6 2.6 2A 2.2 25 26 27 28 Core Power (%of Rated)

MCPRp = A + B (28-P)

WLL A B II11 1>60% I 2.40 3.32 7r_0.070 0.1167 i P = Percent of Rated Core Thermal Power F = Percent of Rated Core Flow FIGURE 3-1B Power-Dependent MCPR Limit (MCPRp) versus Core Power From 25% to 28% of Rated Core Power (Bypass Valves Inoperable) 19 Revision I

Unit Plant I Cycle 21-Hatch Plant Hatch Unit I Cycle 21 Core Operating Limits Report 15 t t4 . _ _ \__X ___

E .,

112 =_ _ =- __

30 40 50 60 70 so go Core Row (%of Rated)

MCPRF = Maximum [1.20, (A

  • F + B)J Maximum Core I Flow (% of Rated) A B 107.0 -0.00586 1.697 F = Percent of Rated Core Flow FIGURE 3-2 Flow-Dependent MCPR Limit (MCPRF) versus Core Flow 20 Revision I

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report 18 - - - -

17 le S. 16 -A- -

~14 --

13.

to - - I - I I---

28 32 36 40 48 52 568 60 64 68 72 76 80 84 88 92 96 M0 Core Power (%of Rated)

Kp = A + B*(Po-P)

P l A l B l Po l 28 s P < 45 1.28 0.01340 45 45 s P < 60 1.15 I 0.00867 60 I 60:sP 1.00 0.00375 100 P = Percent of Rated Core Power FIGURE 3-3A Power-Dependent MCPR Multiplier (Kp) versus Core Power (Pressure RegulatorOperable) 21 Revision 1

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report Y'17 - _

a. i EU It35 28 32 36 40 44 48 52 86 60 84 68 72 76 80 84 88 92 96 DO Core Power (%of Rated)

Kp = A + B*(Po-P)

I P I A I B I PO 28SP<100 I 1.00 I 0.010 I 100 l P = Percent of Rated Core Power FIGURE 3-3B Power-Dependent MCPR Multiplier (Kp) versus Core Power (PressureRegulatorInoperable) 22 Revision 1

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report lUG -

138 0I4 2t3:

0.0 0.1 02 03 OA 05 0.E 0.7 0.8 0.9 to Tau Tau GE14 l GE3 I 1.0

°° 1.37 11' 34 1 1.28 1.28 d FIGURE 3-4A MCPR Limits versus Average Scram Time (BOC to EOC-2100 with EOC-RPT System Operable and Bypass Valves Operable) 23 Revision 1

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report a142 a.

U a ima OD 0.1 02 O0 OA 0.5 O 0.7 0.8 0. to Tau Tau GE14 I GE13 I 1.0 1.49 7 1.37 0.0 1.38 1 1.32 d FIGURE 3-4B MCPR Limits versus Average Scram Time (BOC to EOC-2100 with EOC-RPT System Inoperable and Bypass Valves Operable) 24 Revision 1

Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report r4]___

1.42 U2 E138 3U6

.34 132 0.0 0.1 02 03 CA 0. O 0.7 0A 0.9 to Tau Tau GE14 I GE13 I 1.0 I1.46 1 1.37 0.0 1.43 1 1.34 d FIGURE 3-4C MCPR Limits versus Average Scram Time (BOC to EEOC with EOC-RPT System Operable and Bypass Valves Inoperable) 25 Revision 1

-t Plant Hatch Unit I Cycle 21 Core Operating Limits Report 144 142 140 t38 E

E 034 132 130 128 0.0 0.1 02 03 OA 0.5 0.6 0.7 0.8 0S to Tau Tau GE14 GE13 1.0 l 1.42 l 1.33 0.0 1.39 1.30 FIGURE 3-4D MCPR Limits versus Average Scram Time (EOC-2 100 to EEOC with EOC-RPT System Operable andBypass Valves Operable) 26 Revision I

Plant Hatch Unit I Cycle 21 Core Operating Limits Report 160 _ _ _ _ _ _ _ _ _ _ _

158 1542_

1L50 E

148 0.

E 144 -_

142 _ _ _ _ _ _ _ _

140-138 0.0 0.1 02 03 CA 0.5 0.6 0.7 0.8 0S to Tau Tau GE14 GE13 1.0 1.62 1.42 0.0 1.45 1.34 FIGURE 3-4E MCPR Limits versus Average Scram Time (EOC-2100 to EEOC with EOC-RPT System Inoperable and Bypass Valves Operable) 27 Revision I

- w Plant Hatch Unit 1 Cycle 21 Core Operating Limits Report 4.0 PBDA AMPLITUDE SETPOINT The amplitude trip setpoint in the Period Based Detection Algorithm in the OPRM system shall not exceed the values reported in the Table below. This applies to instruments 1C51 K615 A, B, C, and D. These are the nominal trip setpoint values, not the allowable values. Projected Figure of Merit (FOM) value(s) throughout the cycle will be supplied by the Hatch Core Analysis Group. The values in this table are based on GE13 fuel, since it has lower OLMCPRs than the GE14 fuel.

FOM FOM 1.28 < OLMCPR 1.30

> s < 1.30 < 1.34 21.34 0.0 92.1 1.11 1.12 1.13 92.1 96.9 1.10 1.10 1.11 96.9 102.4 1.08 1.09 1.10 102.4 108.0 1.07 1.08 1.09 28 Revision I

- h Plant Hatch Unit 1Cycle 21 Core Operating Limits Report

5.0 REFERENCES

1. GE/GNF Report 'General Electric Standard Application for Reactor Fuel,"

NEDE-2401 I-P-A-14, June 2000, and the US Supplement, NEDE-2401 1-P-A-14-US, June 2000.

2. GNF Report 0000-0002-7058-SRLR, Revision 0, "Supplemental Reload Licensing Report for Edwin I. Hatch Nuclear Power Plant Unit 1, Reload 20 Cycle 21," March 2002.
3. SNC Letter CAH-NF-2370, "Hatch-I Cycle 21 Pressure Regulator Out-of-Service ARTS Limits," E. B. Gibson to K. S. Folk, April 8, 2002.
4. SNC Letter CAH-NF-2371, "GE14 Low Power ARTS Below PBYP With Bypass Valves Inoperable," W. R. Mertz to K. S. Folk, April 8, 2002.
5. GE Report GE-NE-0000-0001-3737-01 P, "GE14 Fuel Design Cycle-Independent Analyses for Hatch Units 1 and 2, March 2002.
6. GNF Letter VRU-03-005, V. Ruiz-Ugalde to E. B. Gibson, "Hatch 1 and 2 Improved MPLHGR Limits", June 26,2003.
7. GNF Letter EWG-S-03-01 1, E. W. Gibbs to E. B. Gibson, "Hatch-1 Bundle 2255 Improved MAPLHGRs', July 17, 2003.

29 Revision 1