MONTHYEARML24290A1572024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds (L-2024-LLR-0047) ML24290A1552024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley, Hatch, and Vogtle 1 and 2 - Proposed Alternative Request for Code Case N-572 ML24289A2002024-10-15015 October 2024 NRR E-mail Capture - for Your Action - RAI - Proposed License Amendment Request (LAR) for Vogtle Electric Generating Plant, Units 3 and 4 TS 3.7.6 Action E and SR 3.7.6.5 (L-2024-LLA-0083) ML24261B9282024-09-17017 September 2024 NRR E-mail Capture - for Your Action Discussion Points - Steam Generator Tube Inspection Call with SNC Regarding Vogtle, Unit 3 ML24250A1132024-09-0303 September 2024 Inspection Report 2024004 Radiation Safety Baseline Inspection Information Request ML24247A0092024-09-0303 September 2024 NRR E-mail Capture - Fyi - Revised Estimated Completion Date - Vogtle 3 and 4 - UFSAR Scheduler Exemption Request ML24250A1922024-08-29029 August 2024 Amendment Nos. 223/206 (1) - Email ML24232A0052024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - LAR and Exemption Request to Remove Tier 1 and Tier 2 Requirements for Vogtle 3 and 4 ML24253A0722024-08-15015 August 2024 Perspectives on Proposed Removal of Tier 1 and Tier 2 Requirements ML24225A0062024-08-0909 August 2024 NRR E-mail Capture - Acceptance Review - Vogtle 3 and 4 - LAR Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves), Action a and SR 3.7.6.6 (L-2024-LLA-0101) ML24206A0252024-07-20020 July 2024 NRR E-mail Capture - for Your Comments - State of Georgia - Vogtle Unit 1 - Emergency License Amendment Request for Technical Specification 3.7.9 ML24199A1592024-07-17017 July 2024 NRR E-mail Capture - Request for Additional Information - Vogtle 3 and 4 - Exemption for the Requirements in 10 CFR 50.71 Pertaining to the Submittal of Updated Final Safety Analysis Report ML24198A1672024-07-16016 July 2024 NRR E-mail Capture - Acceptance Review Vogtle 3 and 4 - License Amendment Request Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Surveillance Requirement L-2024-LLA-0083 ML24197A1572024-07-15015 July 2024 NRR E-mail Capture - Acceptance Review - Farley and Vogtle 1 and 2, LAR - TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML24197A0172024-07-12012 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds ML24194A0032024-07-11011 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley, Hatch, and Vogtle 1 and 2 - Alternative Request for Code Case N-572 ML24180A0012024-06-26026 June 2024 NRR E-mail Capture - Acceptance Review Farley 1 and 2 and Vogtle 1 and 2 - Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) (L-2024-LLR-0041) ML24170A9362024-06-18018 June 2024 NRR E-mail Capture - Fyi - Change to Estimated Completion Date for the SNC Fleet Physical Barrier Exemptions (L-2023-LLE-0018 and L-2023-LLE-0021) ML24178A3422024-05-16016 May 2024 NRR E-mail Capture - Request for Call - Proposed Vogtle 3 & 4 Tier 1 and Tier 2 Exemptions and LAR ML24120A0262024-04-29029 April 2024 COL Docs - FW Vogtle Electric Generating Plant, Unit 4 - Project Manager Reassignment ML24120A0462024-04-29029 April 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24119A0012024-04-28028 April 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24108A0132024-04-16016 April 2024 NRR E-mail Capture - (External_Sender) Responses from Wednesday 4/10/2024 Call with Southern Nuclear Operating Co. Vogtle 3&4 Licensing Actions ML24107A9322024-04-15015 April 2024 Document Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection Report 2024-02 ML24107A7292024-04-15015 April 2024 Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection - Inspection Report 2024-02 ML24106A0522024-04-12012 April 2024 NRR E-mail Capture - Acceptance Review - Vogtle 1 and 2 - Emergency Diesel Generator (EDG) Voltage and Frequency License Amendment Request (LAR) (L-2024-LLA-0031) ML24100A7842024-04-0909 April 2024 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Vogtle, Units 3 and 4 - Alternative Request for Explosively Actuated Valves (L-2023-LLR-0016) ML24099A0372024-04-0505 April 2024 NRR E-mail Capture - Acceptance Review - Vogtle Unit 3, License Amendment Request (LAR) Technical Specification (TS) 5.5.13, Ventilation Filter Testing Program (VFTP) - L-2024-LLA-0043 ML24095A2412024-04-0404 April 2024 NRR E-mail Capture - Acceptance Review for the Exemption Request Regarding the Final Safety Analysis Report Update Schedule at Vogtle, Units 3 and 4 ML24072A3982024-03-12012 March 2024 NRR E-mail Capture - for Your Action - Second Round Request for Additional Information (RAI) - Vogtle, Unit 1 - SG Tube Inspection Report - 1R24 (L-2023-LRO-0067) ML24061A2372024-03-0101 March 2024 SNC Email Dated March 1, 2024, Regarding SNC Response to NRC Letter for Vogtle 3 & 4 RES Info ML24057A0872024-02-23023 February 2024 NRR E-mail Capture - Acceptance Review - Alternative Request for Explosively Actuated Valves at Vogtle, Units 3 and 4 ML24046A1352024-02-15015 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Initial Criticality and Low-Power Testing ML24039A0882024-02-0808 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A1122024-02-0808 February 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A1922024-02-0808 February 2024 COL Docs - Correction - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24031A0502024-01-31031 January 2024 COL Docs - FW Erroneous Description of Tier 2 Change Process in Construction Lessons-Learned Report ML24017A1122024-01-17017 January 2024 NRR E-mail Capture - Request for Access to Cyber Security Data - Vogtle, Units 3 and 4 ML23360A0042023-12-23023 December 2023 NRR E-mail Capture - Fyi - Office of Nuclear Regulatory Research (RES) Requests for Vogtle 3 & 4 ML23348A0782023-12-13013 December 2023 NRR E-mail Capture - Voluntary Request for Closed Meeting Regarding Cyber Security Assessments at Vogtle, Units 3 and 4 ML23342A0802023-12-0808 December 2023 NRR E-mail Capture - Request for Additional Information (RAI) - Vogtle, Unit 1 - Review of SG Tube Inspection Report for Refueling Outage 24 (L-2023-LRO-0067) ML23331A9992023-11-27027 November 2023 COL Docs - Re Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23331A9492023-11-26026 November 2023 Email Dated November 26, 2023, from Bo Pham to SNC and NRC - Vogtle Seismic Hazard Report ML23331A9622023-11-22022 November 2023 Email Dated November 22, 2023, from SNC to NRC - Vogtle Seismic Hazard Report ML23326A2802023-11-22022 November 2023 COL Docs - Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23320A0342023-11-16016 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Company’S License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23320A2372023-11-0808 November 2023 NRR E-mail Capture - (External_Sender) Proposed LAR Regarding the Ultimate Heat Sink at Vogtle, Units 1 and 2 ML23312A2632023-11-0808 November 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Monday, November 13, 2023 - Vogtle Units 3&4, LAR-22-002, TS 3.8.3, Inverters - Operating Completion Time Extension ML23311A1512023-11-0707 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Company’S License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23304A2272023-10-31031 October 2023 NRR E-mail Capture - Request for State of Georgia Comment by 5pm Monday, Nov. 6, 2023 - License Amendment Request for Vogtle Unit 4 - to Remove Combined License Appendix C 2024-09-03
[Table view] |
Text
Vogtle PEmails From: Hoellman, Jordan Sent: Tuesday, July 17, 2018 2:53 PM To: Vogtle PEmails
Subject:
SNC Comments on Proposed License Condition for Critical Sections Attachments: RAI LAR-17-037 Updated Feedback from Public Call (7-16).pdf Please see SNCs comments and revisions to the updated version of the proposed license condition for Critical Sections for discussion at a future public meeting. The text that is changed from the version provided last Thursday (7/12/2018) is highlighted in yellow, and a discussion of the basis for each change is provided in italicized text below each change.
1
Hearing Identifier: Vogtle_COL_Docs_Public Email Number: 327 Mail Envelope Properties (SN6PR0901MB23662C4357F14C436C201EB8D55C0)
Subject:
SNC Comments on Proposed License Condition for Critical Sections Sent Date: 7/17/2018 2:53:24 PM Received Date: 7/17/2018 2:53:28 PM From: Hoellman, Jordan Created By: Jordan.Hoellman2@nrc.gov Recipients:
"Vogtle PEmails" <Vogtle.PEmails@nrc.gov>
Tracking Status: None Post Office: SN6PR0901MB2366.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 381 7/17/2018 2:53:28 PM RAI LAR-17-037 Updated Feedback from Public Call (7-16).pdf 245485 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
Feedback from Public Call re: RAI LAR-17-037-2 Criterion 1 would remain as originally proposed in LAR-17-037 (except that construction would be changed to structural, as per and earlier SEB comment):
- 1. Involve design methodology or construction structural construction materials that deviate from a code or standard credited in the plant-specific DCD for establishing the criteria for the design or construction of a structure, system, or component (SSC) important to safety, Basis for change: Initially, this said construction materials, but we changed it to structural materials to accommodate the SEB aspects of materials; however, since structural materials will be addressed in the new sub-criterion below, Criterion 1 should be returned to refer to construction material.
A new criterion (2 or 7) would be added as follows:
Proposed (SNC) wording:
x Involve analysis methods or design methodology analytical or design methods, including design codes, analytical assumptions, or structural materials, that deviate from those credited in the plant-specific DCD for critical sections, Basis for change: Staff indicated the use of one term (i.e., either methods or methodology) would be preferable. We opted to go with the combined phrase, analytical or design methods, in response to this comment.
x Result in a change to the design of the steel faceplates, internal trusses, tie bars, or headed studs of the steel-concrete (SC) module walls in the Nuclear Island or Shield Building (excluding attachments or appurtenances), including SC-to-reinforced concrete (RC) connections, Basis for change: Staff indicated the parenthetical text (excluding attachments or appurtenances) was too broad, and could allow the attachment of anything to the walls. So, instead of trying to defining what should be addressed in this exclusion, we felt it would be more straight-forward to define what constitutes the SC module walls. The constituents of these wall are steel faceplates, internal trusses, tie bars, and headed studs. So, we suggest rewording this sub-criterion to include these items.
x Result in a change to the demand to capacity ratio (area of steel provided to that specified in the plant-specific DCD) of a critical section of the structure that when analyzed using local demand and actual steel values exceeds the ratio values stated in or calculated from UFSAR Section 3.8 and Appendix 3H Tables Tier 2* values for the applicable structural member, Basis for no change: Staff indicated wording that would be considered acceptable could be found in a bullet in the summary of the June 7-8 audit. We considered the text in this bullet, and determined that the D/C ratio definition provided in this bullet does not provide SNC any of the flexibility requested by this sub-criterion. We were not certain of exactly why the staff objected to the wording provided by SNC in this bullet. If the objection was based on the use of the term local in this sub-criterion, we would like to discuss how we addressed the use of this term in our draft RAI response dated 6/12/18. If there is some other concern, we would also like to discuss that to better understand the staffs concern.