MONTHYEARRS-24-073, Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations – Additional Information Supporting Request to Withhold Security-Related Information2024-07-31031 July 2024 Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations – Additional Information Supporting Request to Withhold Security-Related Information RS-24-063, Response to Request for Additional Information for 10 CFR 50.55a Request No. I5R-222024-06-14014 June 2024 Response to Request for Additional Information for 10 CFR 50.55a Request No. I5R-22 RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations RS-24-058, Regarding Subsequent License Renewal Environmental Review2024-06-0505 June 2024 Regarding Subsequent License Renewal Environmental Review RS-24-056, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2024-05-28028 May 2024 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report RS-24-052, 2023 Annual Radiological Environmental Operating Report2024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report RS-24-047, 2023 Annual Radioactive Effluent Release Report2024-05-0101 May 2024 2023 Annual Radioactive Effluent Release Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests RS-24-021, Response to Request for Additional Information for 10 CFR 50.55a Request No. I5R-222024-04-0202 April 2024 Response to Request for Additional Information for 10 CFR 50.55a Request No. I5R-22 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report RS-24-023, Report on Status of Decommissioning Funding.2024-03-22022 March 2024 Report on Status of Decommissioning Funding. RS-24-016, Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations2024-03-14014 March 2024 Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations RS-24-022, Response to Request for Additional Information by the Office of Nuclear Material Safeguards and Safety to Support Review of a Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.2142024-03-0808 March 2024 Response to Request for Additional Information by the Office of Nuclear Material Safeguards and Safety to Support Review of a Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 RS-24-017, Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Dresden Nuclear Power Station – Holtec MPC-68MCBS2024-02-23023 February 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Dresden Nuclear Power Station – Holtec MPC-68MCBS RS-23-121, Sixth Ten-Year Interval Inservice Testing Program2023-11-30030 November 2023 Sixth Ten-Year Interval Inservice Testing Program RS-23-122, Amendment No. 15 to Indemnity Agreement No. B-592023-11-29029 November 2023 Amendment No. 15 to Indemnity Agreement No. B-59 RS-23-119, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information RS-23-116, Supplemental Information in Response to Order Consenting to License Transfers and Approval of Conforming License Amendments2023-11-0808 November 2023 Supplemental Information in Response to Order Consenting to License Transfers and Approval of Conforming License Amendments RS-23-107, Relief Request I5R-22, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2023-11-0808 November 2023 Relief Request I5R-22, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval RS-23-102, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-16016 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-071, Application to Adopt TSTF-564, Safety Limit MCPR2023-08-30030 August 2023 Application to Adopt TSTF-564, Safety Limit MCPR RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor RS-23-078, Supplement to License Amendment Request to Revise Technical Specification 3.1.4, Control Rod Scram Times2023-06-16016 June 2023 Supplement to License Amendment Request to Revise Technical Specification 3.1.4, Control Rod Scram Times RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling RS-23-070, Supplement to License Amendment Request Regarding Transition to GNF3 Fuel2023-05-16016 May 2023 Supplement to License Amendment Request Regarding Transition to GNF3 Fuel RS-23-057, Supplement to License Amendment Request Regarding Transition to GNF3 Fuel2023-04-17017 April 2023 Supplement to License Amendment Request Regarding Transition to GNF3 Fuel RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-23-041, Response to Request for Additional Information for Alternative Request RV-23H2023-03-14014 March 2023 Response to Request for Additional Information for Alternative Request RV-23H RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 RS-23-004, Response to Request for Additional Information Regarding Transition to GNF3 Fuel License Amendment Request2023-01-23023 January 2023 Response to Request for Additional Information Regarding Transition to GNF3 Fuel License Amendment Request RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2022-11-30030 November 2022 Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI RS-22-121, Notice of Intent to Pursue Subsequent License Renewal Applications2022-11-0909 November 2022 Notice of Intent to Pursue Subsequent License Renewal Applications RS-22-117, Response to Request for Additional Information License Amendment Request Regarding New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies2022-11-0303 November 2022 Response to Request for Additional Information License Amendment Request Regarding New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies RS-22-116, Submittal of Relief Requests Associated with the Sixth Inservice Testing Interval2022-11-0101 November 2022 Submittal of Relief Requests Associated with the Sixth Inservice Testing Interval RS-22-113, Updated ISFSI Decommissioning Funding Plan for Zion Nuclear Power Station2022-10-26026 October 2022 Updated ISFSI Decommissioning Funding Plan for Zion Nuclear Power Station RS-22-115, Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors2022-10-19019 October 2022 Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-22-092, Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration2022-10-0303 October 2022 Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration RS-22-066, License Amendment Request to Revise Technical Specification 3.1.4, Control Rod Scram Times2022-08-25025 August 2022 License Amendment Request to Revise Technical Specification 3.1.4, Control Rod Scram Times RS-22-065, License Amendment Request Regarding Transition to GNF3 Fuel2022-08-18018 August 2022 License Amendment Request Regarding Transition to GNF3 Fuel RS-22-093, Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans2022-08-18018 August 2022 Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans RS-22-101, Response to Request for Additional Information Related to Relief Request I6R-01 Associated with the Sixth Inservice Inspection Interval2022-08-10010 August 2022 Response to Request for Additional Information Related to Relief Request I6R-01 Associated with the Sixth Inservice Inspection Interval RS-22-099, Submittal of Upcoming Sixth Inservice Inspection Interval Relief Requests I6R-09 and I6R-102022-07-19019 July 2022 Submittal of Upcoming Sixth Inservice Inspection Interval Relief Requests I6R-09 and I6R-10 RS-22-082, Defueled Safety Analysis Report Update, Revision 112022-06-22022 June 2022 Defueled Safety Analysis Report Update, Revision 11 RS-22-080, Withdrawal and Proposed Alternative I6R-08 Associated with Code Case N-921 for Sixth Inservice Inspection Intervals2022-06-0909 June 2022 Withdrawal and Proposed Alternative I6R-08 Associated with Code Case N-921 for Sixth Inservice Inspection Intervals RS-22-064, License Amendment Request Regarding New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies with Proposed Change to Technical Specifications Section 4.3.12022-06-0808 June 2022 License Amendment Request Regarding New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies with Proposed Change to Technical Specifications Section 4.3.1 2024-07-31
[Table view] |
Text
An Exelon Company ArnerCen Erleryy Company, LLC www exeloncorp.com Nuclear txelon Generation 4300 Winfield Koad 4300 Winfieid Road Warrenville, lL 60555 Warrenville, 11. 60555 10 CFR 50.75(f)(1)
March 28,2008 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Dresden Nuclear Power Station, Unit 1 Renewed Facility Operating License Nos. DPR-2 NRC Docket Nos. 50-10 Oyster Creek Generating Station Facility Operating License No. DPR-16 NRC Docket No. 50-219 Peach Bottom Atomic Power Station, Unit 1 Facility Operating License No. DPR-12 NRC Docket Nos. 50-171 Zion Nuclear Power Station, Units 1 and 2 Facility Operating License Nos. DPR-39 and DPR-48 NRC Docket Nos. 50-295 and 50-304
Subject:
Report on Status of Decommissioning Funding for Reactors
References:
- 1) Pennsylvania Public Utility Commission Order, in the matter of Pennsylvania Public Utility Commission, Office of Consumer Advocate, and Eric Joseph Epstein v. PECO Energy Company, Docket No. R-00038102, adopted September 5,2003
- 2) Letter from J. McNulty (Pennsylvania Public Utility Commission) to B. D. Crowe (Philadelphia Electric Company), "Pennsylvania Public Utility Commission v. PECO Energy Company," dated December 31,2007 In accordance with 10 CFR 50.75, "Reporting and recordkeeping for decommissioning planning," paragraph (f)(l), we are submitting a report on the status of decommissioning funding for the reactors owned by Exelon Generation Company, LLC (EGC) and AmerGen Energy Company, LLC (AmerGen).
March 28,2008 U. S. Nuclear Regulatory Commission Page 2 contains the amount of decommissioning funds estimated to be required for the permanently shutdown reactors based on site-specific decommissioning cost estimates. These decommissioning cost estimates do not include the costs of dismantling non-radiologicalsystems and structures or the costs of managing and storing spent fuel on-site. Attachment 2 contains the amount of decommissioning funding accumulated through December 31, 2007. Attachment 3 contains a schedule of annual amounts to be collected through the final year as indicated. Additional information regarding assumptions used for decommissioning cost escalation rates and trust fund earnings rates, and the method of providing financial assurance is included below. With respect to each of the above units, there are no contracts relied upon pursuant to 10 CFR 50.75(e)(l)(v), nor have there been any material changes to the trust agreements. Additional information regarding assumptions used for decommissioning cost escalation rates and trust fund earnings rates and the method of providing financial assurance is included below.
For Dresden Nuclear Power Station and Oyster Creek Nuclear Generating Station, a 2.0% annual real rate of return is being assumed on the decommissioning trust funds.
Financial assurance for decommissioning continues to be provided by the prepayment method, coupled with an external trust fund, in accordance with 10 CFR 50.75(e)(l)(i).
For Peach Bottom Atomic Power Station, Unit 1, the rate of escalation assumed in decommissioning costs is approximately 3.5% (gross domestic product deflator) and the rate of earnings assumed for the decommissioning funds is 6.5% (Reference 1). As documented in Reference 2, the Pennsylvania Public Utility Commission approved a revision to the annual amount to be collected for Peach Bottom Atomic Power Station, Unit 1, to $2.280 million to reflect changes in the estimated cost of decommissioning and in the period of collection. Financial assurance for decommissioning this reactor is provided by the external sinking fund method in accordance with 10 CFR 50.75(e)(l)(ii).
The funding mechanism being used as the source of revenues for the external sinking fund is a "non-by-passable charge."
There are no regulatory commitments contained within this letter. Should you have any questions about this letter, please contact Michelle Yun at (630) 657-2818.
Manager, Licensing : Amount of Decommissioning Funds Estimated to be Required : Amount of Decommissioning Funds Accumulated through December 31, 2007 : Schedule of the Annual Amounts Remaining to be Collected
ATTACHMENT 1 AMOUNT OF DECOMMISSIONING FUNDS ESTIMATED TO BE REQUIRED~~)
Reactor $, in millions Dresden Nuclear Power Station, Unit 1 223.8 Oyster Creek Nuclear Generating Station 501.4'3' Peach Bottom Atomic Power Station, Unit 1 166.2 Zion Nuclear Power Station, Unit 1 310.2 Zion Nuclear Power Station, Unit 2 309.9 (1) The amount of decommissioning funds for the permanently shutdown reactors is based upon site-specific decommissioning cost estimates and is reported in beginning of year 2008 dollars.
(2) This amount reflects the radiological-only funds required for those units utilizing site-specific decommissioning cost estimates reported in beginning of year 2008 dollars.
(3) The site-specific, radiological-only, Delayed DECON preliminary cost estimate for Oyster Creek is $657.8 million before adjusting for growth of the trust funds through the decommissioning period.
ATTACHMENT 2 AMOUNT OF DECOMMISSIONING FUNDS ACCUMULATED THROUGH DECEMBER 31,2007"'
Reactor $, in millions Dresden Nuclear Power Station, Unit 1 275.6 Oyster Creek Nuclear Generating Station 650.8 Peach Bottom Atomic Power Station, Unit 1 42.7 Zion Nuclear Power Station, Unit 1 286.5 Zion Nuclear Power Station, Unit 2 (1) This amount reflects the radiological-only funds available for those units utilizing site-specific decommissioning cost estimates.
ATTACHMENT 3 SCHEDULE OF THE ANNUAL AMOUNTS REMAINING TO BE COLLECTED Annual Amount Final Year Reactor $, in thousands of Collection Dresden Nuclear Power Station, Unit 1 0 NIA Oyster Creek Nuclear Generating Station 0 NIA Peach Bottom Atomic Power Station, Unit 1 2,280 2034 Zion Nuclear Power Station, Unit 1 0 NIA Zion Nuclear Power Station, Unit 2 0 NIA