ML082261396

From kanterella
Revision as of 14:59, 14 November 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Individual Notice of Issuance of Amendment to Facility Operating License and Final Determination of No Significant Hazards Consideration
ML082261396
Person / Time
Site: Millstone Dominion icon.png
Issue date: 08/13/2008
From: John Lamb
NRC/NRR/ADRO/DORL/LPLI-2
To: Christian D
Virginia Electric & Power Co (VEPCO)
Lamb John G./NRR/DORL, 415-3100
Shared Package
ML082261199 List:
References
TAC MD6070
Download: ML082261396 (6)


Text

August 13, 2008 Mr. David A. Christian President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

MILLSTONE POWER STATION, UNIT NO. 3 - INDIVIDUAL NOTICE OF ISSUANCE OF AMENDMENT TO FACILITY OPERATING LICENSE AND FINAL DETERMINATION OF NO SIGNIFICANT HAZARDS CONSIDERATION

Dear Mr. Christian:

The U.S. Nuclear Regulatory Commission (NRC) has forwarded the enclosed ANotice of Issuance of Amendment to Facility Operating License and Final Determination of No Significant Hazards Consideration, to the Office of the Federal Register for publication.

Amendment No. 242, dated August 12, 2008, to Facility Operating License No. NPF-49 issued to Dominion Nuclear Connecticut, increased the Millstone Power Station, Unit No. 3 maximum steady-state reactor core power level from the previous licensed thermal power level of 3,411 megawatts thermal to 3,650 megawatts thermal, which is an increase of approximately 7 percent. This issuance is based on your initial application for amendment dated July 12, 2007.

Notice of Issuance will be included as an Individual Notice of Issuance in the Federal Register and then repeated in the Commission's biweekly Federal Register notice.

If you have any questions, please contact me at 301-415-3100.

Sincerely,

/ra/

John G. Lamb, Senior Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-423

Enclosure:

Individual Notice of Issuance cc w/encl: See next page

Millstone Power Station, Unit No. 3 cc: Mr. Joseph Roy, Director of Operations Lillilan M. Cuoco, Esquire Massachusetts Municipal Wholesale Senior Counsel Electric Company Dominion Resources Services, Inc. Moody Street Building 475, 5th Floor P.O. Box 426 Rope Ferry Road Ludlow, MA 01056 Waterford, CT 06385 Mr. J. Alan Price Edward L. Wilds, Jr., Ph.D. Site Vice President Director, Division of Radiation Dominion Nuclear Connecticut, Inc.

Department of Environmental Protection Building 475, 5th Floor 79 Elm Street Rope Ferry Road Hartford, CT 06106-5127 Waterford, CT 06385 Regional Administrator, Region I Mr. Chris Funderburk U.S. Nuclear Regulatory Commission Director, Nuclear Licensing and 475 Allendale Road Operations Support King of Prussia, PA 19406 Dominion Resources Services, Inc.

5000 Dominion Boulevard First Selectmen Glen Allen, VA 23060-6711 Town of Waterford 15 Rope Ferry Road Mr. William D. Bartron Waterford, CT 06385 Licensing Supervisor Dominion Nuclear Connecticut, Inc.

Mr. J. W. "Bill" Sheehan Building 475, 5th Floor Co-Chair NEAC Rope Ferry Road 19 Laurel Crest Drive Waterford, CT 06385 Waterford, CT 06385 Mr. David A. Sommers Mr. Evan W. Woollacott Dominion Resources Services, Inc.

Co-Chair 5000 Dominion Boulevard Nuclear Energy Advisory Council Glen Allen, VA 23060-6711 128 Terry's Plain Road Simsbury, CT 06070 Mr. David A. Christian President and Chief Nuclear Officer Senior Resident Inspector Virginia Electric and Power Company Millstone Power Station Innsbrook Technical Center c/o U.S. Nuclear Regulatory Commission 5000 Dominion Boulevard P. O. Box 513 Glen Allen, VA 23060-6711 Niantic, CT 06357 Ms. Nancy Burton 147 Cross Highway Redding Ridge, CT 00870

August 13, 2008 Mr. David A. Christian President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

MILLSTONE POWER STATION, UNIT NO. 3 - INDIVIDUAL NOTICE OF ISSUANCE OF AMENDMENT TO FACILITY OPERATING LICENSE AND FINAL DETERMINATION OF NO SIGNIFICANT HAZARDS CONSIDERATION

Dear Mr. Christian:

The U.S. Nuclear Regulatory Commission (NRC) has forwarded the enclosed ANotice of Issuance of Amendment to Facility Operating License and Final Determination of No Significant Hazards Consideration, to the Office of the Federal Register for publication.

Amendment No. 242, dated August 12, 2008, to Facility Operating License No. NPF-49 issued to Dominion Nuclear Connecticut, increased the Millstone Power Station, Unit No. 3 maximum steady-state reactor core power level from the previous licensed thermal power level of 3,411 megawatts thermal to 3,650 megawatts thermal, which is an increase of approximately 7 percent. This issuance is based on your initial application for amendment dated July 12, 2007.

Notice of Issuance will be included as an Individual Notice of Issuance in the Federal Register and then repeated in the Commission's biweekly Federal Register notice.

If you have any questions, please contact me at 301-415-3100.

Sincerely,

/ra/

John G. Lamb, Senior Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-423

Enclosure:

Individual Notice of Issuance cc w/encl: See next page DISTRIBUTION:

PUBLIC Branch Reading RidsAcrsAcnw_MailCTR Resource RidsNrrDorlDpr Resource RidsNrrDorlLplI-2 Resource RidsNrrLAABaxter Resource RidsNrrPMJLamb Resource RidsOgcRp Resource RidsRgnIMailCenter Resource ADAMS Accession Nos.: PKG ML082261199 LTR ML082261396 FRN ML081640176 OFFICE NRR/LPLI-2/PM NRR/LPLI-2/LA NRR/LPLI-2/BC NRR/LPLI-2/PM NAME JLamb ABaxter HChernoff (GMiller for) JLamb DATE 08/13/08 08/13/08 08/13/08 08/13/08 OFFICIAL AGENCY RECORD