ML072000281 | 13 July 2007 | Dominion Nuclear Connecticut Gerald Bichof | License Amendment Request - Stretch Power Uprate - Supplemental Information | Supplement |
ML072000386 | 13 July 2007 | Dominion Dominion Nuclear Connecticut Gerald Bichof | License Amendment Request, Stretch Power Uprate | Request |
ML072670216 | 15 October 2007 | Chernoff H NRC/NRR/ADRO/DORL/LPLI-2 | Stretch Power Uprate Acceptance Review | Acceptance Review |
ML072700545 | 18 October 2007 | John Lamb NRC/NRR/ADRO/DORL/LPLI-2 | Westinghouse Electric Company LLC Request for Withholding Information from Public Disclosure Regarding Letter (CAW-07-2296), Subject: NEU-07-128 P-Attachment, Millstone Nuclear Power Station Unit 2 Stretch Power Uprate Program Supplemental | Withholding Request Acceptance |
ML072960179 | 29 October 2007 | John Lamb NRC/NRR/ADRO/DORL/LPLI-2 | Request for Additional Information, Stretch Power Uprate Amendment Request | RAI |
ML073230976 | 19 November 2007 | Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request | Response to RAI |
ML073170665 | 26 November 2007 | John Lamb NRC/NRR/ADRO/DORL/LPLI-2 | Request for Additional Information on Instrumentation and Controls and Fire Protection Regarding Stretch Power Uprate Amendment Request | RAI |
ML073480240 | 13 December 2007 | Dominion Nuclear Connecticut Gerald Bichof | Supplemental Information for License Amendment Request Stretch Power Uprate | Supplement |
ML073370384 | 14 December 2007 | John Lamb NRC/NRR/ADRO/DORL/LPLI-2 | Request for Additional Information on the Stretch Power Uprate Amendment Request | RAI |
ML073250081 | 14 December 2007 | John Lamb NRC/NRR/ADRO/DORL/LPLI-2 | Westinghouse Electric Company LLC Request for Withholding Information from Public Disclosure Regarding Letter (CAW-07-2252), Subject: WCAP-16271-P, Millstone Unit 3 Spent Fuel Pool Criticality Safety Analysis, March 2007 (Proprietary), Date | Withholding Request Acceptance |
ML073520051 | 17 December 2007 | Dominion Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request | Response to RAI |
ML080100600 | 10 January 2008 | Dominion Nuclear Connecticut Hartz L | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Questions EEEB-07-0049 Through EEEB-07-0057 | Response to RAI |
ML080100611 | 10 January 2008 | Dominion Dominion Nuclear Connecticut Hartz L | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Question CPNB-07-0048 | Response to RAI |
ML080100604 | 10 January 2008 | Dominion Nuclear Connecticut Hartz L | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Question AADB-07-0012 | Response to RAI |
ML080100606 | 10 January 2008 | Dominion Dominion Nuclear Connecticut Hartz L | Response to Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Questions SCVB-07-0058 and SCVB-07-0059 | Response to RAI |
ML080580476 | 11 January 2008 | Dominion Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Questions SRXB-07-0013 Through SRXB-07-0047 | Response to RAI |
ML080170495 | 11 January 2008 | Dominion Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Question EMCB-07-0070 | Response to RAI |
ML080140077 | 11 January 2008 | Dominion Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request, Response to Questions SBPB-07-0082 Through SBPB-07-0087 | Response to RAI |
ML080110695 | 11 January 2008 | Dominion Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request, Response to Questions CSGB-07-0010 and CSGB-07-0011 | Response to RAI |
ML080140570 | 14 January 2008 | Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Questions EMCB-07-0060 Through EMCB-07-0069 and EMCB-07-0071 Through EMCB-07-0081 | Response to RAI |
ML080220506 | 18 January 2008 | Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Question EICB-07-0106 | Response to RAI |
ML080220527 | 18 January 2008 | Dominion Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Question SBPB-07-0105 | Response to RAI |
ML080220530 | 18 January 2008 | Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Questions SCVB-07-0091 Through SCVB-07-0104 | Response to RAI |
ML080220541 | 18 January 2008 | Dominion Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Questions SRXB-07-0088 Through SRXB-07-0090 | Response to RAI |
ML080280375 | 18 January 2008 | Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request, Response to Question AADB-07-0107 | Response to RAI |
ML080320308 | 31 January 2008 | Dominion Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Question EMCB-07-0070 | Response to RAI |
ML080560392 | 25 February 2008 | Dominion Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request, Supplemental Response to Question EMCB-07-0072 | Supplement |
ML080560615 | 25 February 2008 | Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Revised and Supplemental Responses to Questions AFPB-07-0007 & AFPB-07-0008 | Supplement |
ML080710391 | 10 March 2008 | Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Question SCVB-07-0091 | Response to RAI |
ML080710377 | 10 March 2008 | Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Response to Question AADB-07-0107 | Response to RAI |
ML080350132 | 13 March 2008 | John Lamb NRC/NRR/ADRO/DORL/LPLI-2 | Request for Withholding Information from Public Disclosure Regarding Millstone Power Station, Unit 3 | Withholding Request Acceptance |
ML080840527 | 17 March 2008 | Nancy Burton Connecticut Coalition Against Millstone | Nancy Burton Petition to Intervene and Request for Hearing | Request |
ML080850894 | 25 March 2008 | Dominion Nuclear Connecticut Hartz L | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Supplemental Response to Question EEEB-07-0052 | Supplement |
ML080880268 | 27 March 2008 | Dominion Nuclear Connecticut Hartz L | Supplemental Information Regarding Stretch Power Uprate License Amendment Request | Supplement |
ML080460620 | 28 March 2008 | Chernoff H NRC/NRR/ADRO/DORL/LPLI-2 | Potential Schedule Change for Proposed Stretch Power Uprate License Amendment Request | Other |
ML081430014 | 4 April 2008 | Dominion Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Supplemental Response to Question EMCB-07-0072 | Supplement |
ML081080024 | 23 April 2008 | John Lamb NRC/NRR/ADRO/DORL/LPLI-2 | Request for Additional Information, Stretch Power Uprate Amendment Request | RAI |
ML081150679 | 24 April 2008 | Dominion Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Supplemental Information, Rod Withdrawal at Power Event | Supplement |
ML081200643 | 29 April 2008 | Dominion Nuclear Connecticut Gerald Bichof | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Revised Response to Questions EEEB-07-0052, EEEB-07-0054 and EEEB-07-0055 | Response to RAI |
ML081360625 | 15 May 2008 | Dominion Dominion Nuclear Connecticut Hartz L | Response to Request for Additional Information Regarding Stretch Power Uprate License Amendment Request Revised Response to Follow-ups EEEB-08-0108 Through EEEB08-0113 to Question EEEB-07-0052 | Response to RAI |
ML081420443 | 20 May 2008 | Dominion Dominion Nuclear Connecticut Gerald Bichof | Supplemental Information Regarding Stretch Power Uprate License Amendment Request Miscellaneous Updates to the License Amendment Request | Supplement |
ML081420824 | 21 May 2008 | Dominion Dominion Nuclear Connecticut Gerald Bichof | Stretch Power Uprate License Amendment Request Additional Information in Connection with the NRC Audit Held on May 13, 2008 in Rockville, Maryland | Request |
ML080870457 | 29 May 2008 | John Lamb NRC/NRR/ADRO/DORL/LPLI-2 | Draft Environmental Assessment and Finding of No Significant Impact for Proposed Stretch Power Uprate | Draft Other |
ML081750222 | 16 June 2008 | Nancy Burton Connecticut Coalition Against Millstone | Notice of Appeal | Request |
ML081930274 | 10 July 2008 | Dominion Dominion Nuclear Connecticut Gerald Bichof | Stretch Power Uprate License Amendment Request DNC Comments on Draft Safety Evaluation - Stretch Power Uprate | Draft Request |
ML081930757 | 11 July 2008 | John Lamb NRC/NRR/ADRO/DORL/LPLI-2 | Follow-up to Dominion Nuclear Connecticut, Inc. Letter, Dated July 10, 2008, Regarding the Draft Safety Evaluation - Stretch Power Uprate | Draft Approval |
ML081990112 | 16 July 2008 | Dominion Dominion Nuclear Connecticut Gerald Bichof | Stretch Power Uprate License Amendment Request - Supplement to DNC Comments on Draft Safety Evaluation - Stretch Power Uprate | |
ML081930070 | 30 July 2008 | John Lamb NRC/NRR/ADRO/DORL/LPLI-2 | Final Environmental Assessment and Finding of No Significant Impact for Proposed Stretch Power Uprate | Other |
ML081610585 | 12 August 2008 | John Lamb NRC/NRR/ADRO/DORL/LPLI-2 | License Amendment, Stretch Power Uprate | Other |
ML082250418 | 12 August 2008 | NRC/NRR/ADRO/DORL/LPLI-2 | Stretch Power Uprate, Tec Specs to Amd 242 | Acceptance Review |