MONTHYEARDCL-24-075, Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, “Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React2024-08-0808 August 2024 Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, “Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React DCL-24-070, License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2024-07-31031 July 2024 License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies DCL-24-071, Core Operating Limits Report for Unit 2 Cycle 252024-07-22022 July 2024 Core Operating Limits Report for Unit 2 Cycle 25 DCL-2024-523, Submittal of Report on Discharge Self-Monitoring2024-07-18018 July 2024 Submittal of Report on Discharge Self-Monitoring DCL-2024-527, Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant2024-07-0101 July 2024 Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant DCL-24-066, Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL2024-06-27027 June 2024 Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL DCL-24-052, Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report2024-05-16016 May 2024 Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report DCL-24-051, One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage2024-05-0808 May 2024 One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage DCL-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Radiological Environmental Operating Report DCL-24-047, 2023 Annual Non-radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Non-radiological Environmental Operating Report DCL-24-048, O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 20232024-04-30030 April 2024 O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 2023 DCL-24-027, 2023 Annual Radioactive Effluent Release Report2024-04-28028 April 2024 2023 Annual Radioactive Effluent Release Report DCL-24-045, Annual Report of Occupational Radiation Exposure for 20232024-04-24024 April 2024 Annual Report of Occupational Radiation Exposure for 2023 DCL-24-042, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-04-17017 April 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations DCL-24-022, Notification of Changes to Decommissioning Schedule2024-04-0202 April 2024 Notification of Changes to Decommissioning Schedule DCL-24-023, Revised Certification of Permanent Cessation of Power Operations2024-04-0202 April 2024 Revised Certification of Permanent Cessation of Power Operations DCL-24-031, Decommissioning Funding Report2024-03-27027 March 2024 Decommissioning Funding Report DCL-24-032, 2024 Annual Statement of Insurance for Pacific Gas and Electric Company’S Diablo Canyon Power Plant2024-03-27027 March 2024 2024 Annual Statement of Insurance for Pacific Gas and Electric Company’S Diablo Canyon Power Plant DCL-24-028, Request for Enforcement Discretion Regarding Compliance with Technical Specification 3.0.3, Limiting Condition for Operation Applicability2024-03-21021 March 2024 Request for Enforcement Discretion Regarding Compliance with Technical Specification 3.0.3, Limiting Condition for Operation Applicability DCL-24-018, License Amendment Request 24-01 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)2024-02-28028 February 2024 License Amendment Request 24-01 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) DCL-2024-507, 2023 Annual Report on Discharge Self-Monitoring2024-02-27027 February 2024 2023 Annual Report on Discharge Self-Monitoring DCL-24-020, Nuclear Material Transaction Report for New Fuel2024-02-21021 February 2024 Nuclear Material Transaction Report for New Fuel DCL-24-014, Owners Activity Report for Unit 1 Twenty-Fourth Refueling Outage2024-02-12012 February 2024 Owners Activity Report for Unit 1 Twenty-Fourth Refueling Outage DCL-24-013, Nuclear Material Transaction Report for New Fuel2024-02-0707 February 2024 Nuclear Material Transaction Report for New Fuel DCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel DCL-2024-502, 2023 Annual Sea Turtle Report for Diablo Canyon Power Plant (DCPP)2024-01-25025 January 2024 2023 Annual Sea Turtle Report for Diablo Canyon Power Plant (DCPP) DCL-2024-501, Sea Turtle Stranding Report (Green Sea Turtle)2024-01-24024 January 2024 Sea Turtle Stranding Report (Green Sea Turtle) DCL-2024-500, Transmittal of the 4th Quarter of 2023 Report on Discharge Self-Monitoring2024-01-18018 January 2024 Transmittal of the 4th Quarter of 2023 Report on Discharge Self-Monitoring DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System DCL-23-092, Material Status Report for the Period Ending August 31, 20232023-09-28028 September 2023 Material Status Report for the Period Ending August 31, 2023 DCL-23-077, License Amendment Request 23-02 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-27027 September 2023 License Amendment Request 23-02 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors DCL-23-083, Upcoming Meeting with Nuclear Security and Incident Response Staff2023-09-13013 September 2023 Upcoming Meeting with Nuclear Security and Incident Response Staff DCL-23-078, Nuclear Material Transaction Report for New Fuel2023-09-0606 September 2023 Nuclear Material Transaction Report for New Fuel DCL-23-070, Withdrawal of Request Regarding Senior Reactor Operator License Application2023-08-16016 August 2023 Withdrawal of Request Regarding Senior Reactor Operator License Application DCL-23-068, Nuclear Material Transaction Report for New Fuel2023-08-0909 August 2023 Nuclear Material Transaction Report for New Fuel DCL-23-066, Nuclear Material Transaction Report for New Fuel2023-08-0303 August 2023 Nuclear Material Transaction Report for New Fuel DCL-23-065, Letter DCL-23-065 Request That Exam Material Be Withheld from Public Disclosure2023-07-27027 July 2023 Letter DCL-23-065 Request That Exam Material Be Withheld from Public Disclosure DCL-23-064, Nuclear Material Transaction Report for New Fuel2023-07-26026 July 2023 Nuclear Material Transaction Report for New Fuel DCL-23-054, License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-07-13013 July 2023 License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b 2024-08-08
[Table view] |
Text
Pacific Gas and Electric Company Edward D. Halpin Diablo Canyon Power Plant Senior Vice President Mail Code 104/6 Nuclear Generation & Chief Nuclear Officer P. O. Box 56 Avila Beach, CA 93424 805.545.4100 October 25,2012 E-Mail: E1H8@pge.com PG&E Letter DCL-12-106 U.S. Nuclear Regulatory Commission 10 CFR 50.4 ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Pacific Gas and Electric Company's Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
References:
- 1. NRC Order Number EA-12-051, Order Modifying Licenses with Regard to Requirements of Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012
- 2. NRC Interim Staff Guidance JLD-ISG-2012-03, Compliance with Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, Revision 0, dated August 29, 2012
Dear Commissioners and Staff:
On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued an order (Reference 1) to Pacific Gas and Electric Company (PG&E). Reference 1 was immediately effective and directs PG&E to have a reliable indication of the water level in associated spent fuel storage pools. Specific requirements are outlined in of Reference 1.
Reference 1 requires submission of an initial status report 60 days following issuance of the final interim staff guidance. The final interim staff guidance (Referen,ce 2) was issued August 30, 2012.
The purpose of this letter is to provide the initial status report pursuant to Section IV, Condition C.2, of Reference 1 within 60 days following issuance of Reference 2.
This report confirms PG&E has received Reference 2 and is in the process of evaluating the guidance for the purpose of providing a reliable indication of the water level in associated spent fuel storage pools as described in Attachment 2 of Reference 1.
During this reporting period, PG&E has been identifying resources and initiating project plans including development of milestones, to ensure compliance with Reference 1.
A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway
Document Control Desk PG&E Letter DCL-12-1 06 October 25,2012 Page 2 For the next 6 months, PG&E plans to develop and submit the overall integrated plan.
At this time, PG&E has not encountered technical difficulties that could affect its ability to provide the February 28,2013, submittal.
Project milestones scheduled through completion of installation and testing:
- 1) A project milestones schedule will be provided with the overall integrated plan by February 28,2013.
- 2) Implementation of the order will be completed for Unit 1 prior to startup from Unit 1 refueling outage 19 (Fall 2015).
- 3) Implementation of the order will be completed for Unit 2 prior to startup from Unit 2 refueling outage 19 (Spring 2016).
PG&E is making regulatory commitments (as defined by NEI 99-04) in the Enclosure of this letter. This letter includes no revisions to existing regulatory commitments.
If you have any questions, or require additional information, please contact Mr. Terence L. Grebel at (805) 545-4160.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on October 25,2012.
Sincerely,
?~,~--
Edward D. Halpin Senior Vice President - Chief Nuclear Officer ckf6/SAPN 50465912 Enclosure cc: Diablo Distribution cc:/enc: Elmo E. Collins, NRC Region IV Steven R. Jones, NRC, NRR/DSS/SBPB Eric J. Leeds, NRC Director, Office of Nuclear Reactor Regulation Laura H. Micewski, NRC, Senior Resident Inspector Blake A. Purnell, NRC, NRR/JLD/PMB Lisa M. Regner, NRC, NRR/JLD/PMB Joseph M. Sebrosky, NRR Project Manager A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway
Enclosure PG&E Letter DCL-12-106 Regulatory Commitments PG&E is making the following regulatory commitments (as defined by NEI 99-04) in this submittal:
Commitment Due Date For the next 6 months, PG&E plans to develop and submit the February 28, 2013 overall integrated plan.
A project milestones schedule will be provided with the overall February 28, 2013 integrated plan by February 28, 2013.
Implementation of the order will be completed for Unit 1 prior Fall 2015 to startup from Unit 1 refueling outage 19 (Fall 2015).
Implementation of the order will be completed for Unit 2 prior Spring 2016 to startup from Unit 2 refueling outage 19 (Spring 2016).