7/11/13 Meeting Slides - Implementation of STAR Program and Replacement of the 2/3 Cycle Mtc Measurement
ML13197A095
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 07/11/2013
From:
Arizona Public Service Co
To:
Division of Operating Reactor Licensing
Rankin J
References
TAC MF1932, TAC MF1933, TAC MF1934
Download: ML13197A095 (23)


Text

Implementation of STAR Program and Replacement of the 2/3 Cycle MTC Measurement Pre-Submittal Presentation to the NRC Date: 07/11/2013

Purpose

  • Present and discuss with the NRC planned licensing changes

- Implementation of the Startup Testing Activity Reduction (STAR) Program at PVNGS

- Replacement of the 2/3 Cycle Moderator Temperature Coefficient (MTC) Measurement 2

Topics

  • Replacement of the 2/3 Cycle MTC Measurement
  • Licensing Approach
  • Conclusion and Discussion 3

STAR

  • Objectives

- Alternate method to validate core design

- Minimize the time the plant is in an abnormal configuration 4

STAR

  • Overview

- Approved by NRC in WCAP-16011-P-A

  • Participating plants only
  • Successfully implemented at 8 CE units

- Incorporated into Improved Standard TS

STAR

  • Overview

- Adds

  • Credits Pre-Operational Checks
  • New Beginning of Cycle (BOC) Hot Zero Power (HZP) MTC surveillance methodology
  • Applicability Requirements

- Replaces

  • BOC HZP Isothermal Temperature Coefficient (ITC) Measurement 6
  • CEA Worth Measurement

STAR

  • Current Methodology

- CEA worth measurement

  • Require operation outside the normal TS LCOs
  • Presents operational challenges

- Unit 3 LER 2012-001

- Unit 1 LER 2011-005

- Measure ITC at HZP with use of reactivity computer 7

STAR

  • Proposed Methodology

- Replacement of CEA Worth Measurements

  • Use applicability requirements
  • Replacement will reduce the occurrence of problems associated with testing and minimize time in abnormal operating configuration 8

STAR

  • Proposed Methodology (cont.)

- Alternate MTC verification

  • Adjust predicted HZP MTC based on measured Critical Boron
  • Increase availability of the control channels
  • Align PVNGS with Improved Standard TS 9

STAR

  • Applicability Requirements

- Found in Table 3-4 of WCAP-16011-P-A

- Compliance evaluated on a reload cycle-specific basis

- STAR only applied to cycles when compliance verified

- Maintain the effectiveness of the STAR Program in problem identification 10

STAR

  • Applicability Requirements (cont.)

- Core design methods have a defined set of uncertainties based on a benchmark of predictions to actual plant measurements

- Core, fuel, CEA design are similar to that of a benchmarked core

- Cycle specific predictions independently verified by

  • Comparison of 2 independent neutronics codes 11

STAR

  • Applicability Requirements (cont.)

- Implementation of CEA Lifetime Program

  • Limit CEA life within operation experience base

- Pre-operational checks verify core and CEA loading are consistent with design

- CEA Coupling checks performed during reactor restack

  • Many favorable PVNGS unique design feature 12

STAR

  • Benefits

- Minimize the time the plant is in an abnormal operating configuration

- Increase the availability of the control channels

- Operationally focused improvement 13

STAR

  • WCAP 16011-P-A approach

- Compare STAR Program to Generic Program

  • Identify set of core problems

- Design Predictions

- As-Built Core

- Test Performance 14

STAR

  • WCAP 16011-P-A approach (cont.)

- Concluded STAR Program is as effective in detecting the Problems as the Generic Program

- STAR is an NRC approved and implemented alternative to current testing methodology.

15

STAR

- Compared

  • Design differences between PVNGS and original participating plants
  • Differences in current PVNGS startup program and Generic Program
  • Operating Experience since original STAR

- NRC and INPO

- PVNGS

- Implementing plants 16

STAR

  • Results of Evaluations

- Contained in plant specific justification

- CASMO/SIMULATE as applied at PVNGS is acceptable for STAR

- The PVNGS STAR Program is as effective as the approved STAR Program and is an acceptable alternative to the current PVNGS startup testing program.

17

Replacement of 2/3 Cycle MTC Measurement

  • Objective

- To replace the 2/3 cycle MTC measurement with alternate verification

  • Overview

- Approved for all CE plants in CE NPSD-911-A and Amendment 1-A (TSTF 406)

- No measurement at 2/3 cycle if 40 EFPD measurement is within acceptance criteria 18 - Already implemented at many PWRs

Replacement of 2/3 Cycle MTC Measurement

  • Current Topical only applicable for ROCS

& ANC

  • PVNGS will demonstrate applicability of SIMULATE
  • Conclusions

- SIMULATE is acceptable for use

- Replacement of the 2/3 cycle MTC measurement is acceptable at PVNGS including 19 STAR Cycles

Licensing Approach

- Application of STAR to PVNGS

- Replacement of 2/3 cycle MTC Measurement 20

Licensing Approach

- SR 3.1.4.1 (HZP verification)

  • Add note allowing use of alternate BOC HZP MTC surveillance method (TSTF 486)

- SR 3.1.4.2 (At power verifications)

  • Add note allowing replacement of 2/3 cycle at power MTC Measurement (CE-NPSD-911 & TSTF 406) 21

Licensing Approach

  • Proposed Schedule

- Submit November 2013

- Requesting NRC Approval in November 2014

- First use in Spring of 2015 22

Conclusion and Discussion

  • Acceptable to implement the STAR Program at PVNGS
  • Acceptable to replace the 2/3 cycle at power MTC measurement
  • Submit both under a single LAR November 2013
  • Requesting NRC approval November 2014 23